| 1 | installation of Tubewell |
| 2 | Transportation pf Drilling equipment up to the site including erection and dismantling ,loading /unloding returning of Rig machin ,Drilling equipments and Tube well pipes (with fuel & lubricants ) |
| 3 | Transportation of OP Compressor including instalation dismantling loading /unloading and returning the with fuel and lubricants. |
| 4 | Transportation of OP unit including instalation dismantling loading /unloading and returning the with fuel and lubricants. |
| 5 | Driling of untial pilot bore have 500 mm dia meter from GL t0 60 meter BGL. |
| 6 | Reaming of drilled pilot bore up to 450 mm diameter finished bore by using suitable sizes RR bits from 60 BGL to 100 meter BGL. |
| 7 | Reaming of drilled pilot bore up to 450 mm diameter finished bore by using suitable sizes RR bits from 100 BGL to 200 meter BGL. |
| 8 | Lowring of 200 mm dia MSERW 7.1 mm thick plain pipe from 54 meter BGL with welding etc. |
| 9 | Lowring of 150 mm dia MSERW 7.1 mm thick slotted pipe from 54 meter BGL 100 meter BGL with welding etc. |
| 10 | Lowring of 150 mm dia MSERW 7.1 mm thick slotted /plain pipe from 100 meter BGL 200 meter BGL with welding etc. |
| 11 | Devlopment of Tubewell with the help of 250 PSI Air Compressor . |
| 12 | Devlopment of Tubewell with the help of OP unit . |
| 13 | Testing of geophysical Zonal logging and sealing . |
| 14 | Supply of 200 mm dia MSERW housing pipe of |
| 15 | Supply of 150 mm dia MSERW thick slotted pipe . |
| 16 | Supply of 150 mm dia MSERW thick plain pipe . |
| 17 | Supply of 200x 150mm dia MS reducer of 16 mm thick . |
| 18 | Supply of 150mm dia MS well cap of 12mm thick . |
| 19 | Supply of 200 mm dia MS half thread nipple 16 mm thick . |
| 20 | Supply of 200mm dia MS ring of 200mm x12 mm thick |
| 21 | Supply of 200mm dia MS ring of 200mm x12 mm thick |
| 22 | Supply of 200mm dia MS clamp . |
| 23 | Tube well supportive frame |
| 24 | Supply of 200 mm dia MS bail plug |
| 25 | Supply of 200 mm dia half thread scoket . |
| 26 | Supply of Gravel/bajri (1.6 x4.8 mm) |
| 27 | Supply of MS column pipe of 80 mm dia along packing and mountion nuts and bolts . |
| 28 | Supply of MS sluce valve of 80 mm dia along packing and mountion nuts and bolts . |
| 29 | Supply of MS Reflex valve of 80 mm dia along packing and mountion nuts and bolts . |
| 30 | Supply of MS DF pipe of 80 mm dia along flange packing and mountion nuts and bolts . |
| 31 | Supply instalation Testing and Commissiong (SDC) of 600 LPM 45 meter head of 11.2 KW (10 HP ) submercible clear water pumping plant suitable to operte at 415 volt .50 Hz for AC supply (as per IS 8034 -1989 ) including starter ,control panel ,cable complete in all the respect with all the accessories and T&P. |
| 32 | Extension of 200 meters three phase HT line with required nos of poles along with instalation labour ,T&P etc all complete including supply and commissioning of 25 . |
| 33 | grider (2 Nos ) with first class brick work super structure with cement and coarse sand mortar in the ratio of 1:4 inclding cutting and molding of bricks as required excavation of foundation and supply of all the materials labour chargs . T&P etc for Completion of work inclding pillers 12 mm thick with cement and local sand mortar in the ratio of 1:6 including supply and fixing of MS garter of size 150 mm x 100mm having of 2.5 meters complete in all he respect as required for proper completion of work . |
| 34 | add GST 18 % Please Enable Macros to View BoQ information |