| 1 | Excavating in trenches n exc 1.5 metre wide and n exc 1.5m in depth , for foundation ,etc or for shafts, wells , cesspits, main holes etc.n exc 10 sqm on plan and n exc 1.5 metre depth and getting out in soft/ lose soil complete all as specified and directed. |
| 2 | Returning, filling including spreading , levelling , watering and well ramming in layers not exc 25cm of any soil complete all as specified and directed. |
| 3 | Removing excavated materials(soils) to a distance n exc 50m and depositing where directed at a level n exc 1.5m above the starting point complete all as specified and directed. |
| 4 | Material and labour for spreading of dry river bed sand for cushioning and covering the under ground cable in trenches all as specified and as directed. (Note : Punned down thickness 18 cm shall be measured) |
| 5 | Supply, laying in repair of PCC covers, class LV type-1 flat size 250mmx150mmx40mm, ISI marked complete all as specified and directed. |
| 6 | Supply, laying in repair of PCC covers, class LV type-2 flat size 300mmx180mmx40mm, ISI marked complete all as specified and directed. |
| 7 | Supply & laying in repair HDPE pipe 65mm bore for covering of LT cables etc. with all accessores complete all as specified and directed. |
| 8 | Supply and Laying in repair in trenches or drawn through pipe or fixed on wall / poles , LT UG cable 1100 Volts, heavy duty XLPE insulated, screened, PVC bedded, galvanised steel strip or wired armoured with aluminium conductor after removing old one complete all as specified and directed of following size (Excavation & earth work, sand cushioning & cable covers shall be measured and paid for separately) :-(a) 16 sqmm 4 core |
| 9 | (b ) 25 Sqmm 4 core |
| 10 | (c) 35 Sqmm 31/2 core |
| 11 | (d) 50 Sqmm 31/2 core |
| 12 | (e) 70 Sqmm 31/2 core |
| 13 | (f) 95 Sqmm 31/2 core |
| 14 | (g)120 Sqmm 31/2 core |
| 15 | (h) 150 Sqmm 3.5 core |
| 16 | (j) 185 Sqmm 3.5 core |
| 17 | Material and labour in reair for GI pipe light grade 50 mm dia Tubes, with all fitting and fixed complete to walls and ceilings or laid in floors complete for protection of cables complete all as specified and directed. |
| 18 | All as per Item No 17 above but 80 mm dia tubes |
| 19 | Material and labour for boring under paths/roads for passing the LT cable by using bookie or other resources including removing the suplus soil complete all as specified and directed Please Enable Macros to View BoQ information |
| 20 | Material and labour for boring under paths/roads for passing the LT cable by using bookie or other resources including removing the suplus soil complete all as specified and directed Please Enable Macros to View BoQ information |