| 1 | Earth work in excavation in foundation structures as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious materials and disposal upto any lead, dressing of sides and bottoms and back filling in trenches with excavated suitable materials complete within all leads, lifts carriage of material and other incidentals. |
| 2 | Providing and laying cement concrete 1:4:8 (One cement : four sand : eight graded stone aggregate 25mm (Twenty Five millimeter) nominal size) and curing complete including cost of form work in retaining walls/breast walls, as per drawing and technical specification clause 802, 803, 1202 & 1203 as per HPPWD specification within all leads and lifts and as per the direction of Engineer-in-charge. |
| 3 | Providing and laying plain / Reinforced cement concrete 1:2:4 (One cement : two sand : four graded crushed stone aggregate 25 mm (forty millimeters) nominal size curing complete including the cost of formwork for plain / Reinforced concrete in Retaining / Breast walls as per drawing and H.P.P.W.D. specification and carriage of materials all leads and lifts. |
| 4 | Providing concrete for plain/reinforced concrete grade M 20 Nominal mix (1:1.5:3) in superstructure complete as per drawings and technical specifications Clause 800, 1205.4 & 1205.5 and curing complete including the cost of form work and carriage of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. |
| 5 | Supplying fitting and placing HYSD (High Yield Strength Deformed bar) reinforcement in Sub-Structure made of TATA TISCON/SAIL , RINL including cost of bending, binding and cutting and placing in position of bars complete including cost of binding wire as per drawing , MORTH technical specification clause 1600 and 2200 (one thousand six hundred and two thousand two hundred) and direction of Engineer-in-Charge, including entire carriage of materials with in all leads , lifts and other incidentals. The rates are inclusive of octroi, royalty, Malkana, toll tax, sale tax, GST or other taxes imposed by the Government. |
| 6 | Stone soling properly hand packed filling interstices with kharanja stone and consolidating with power road roller to the required gradient and camber including spreading watering and rolling of binding materials moorum or earth etc extra complete as per HP.PWD. specification. 100mm (one hundred millimeter) spread thickness (finished work including materials and labour) including carriage of material in all leads, lifts as per the entire satisfaction and direction of Engineer-in-charge. |
| 7 | Providing and laying plain cement concrete M-10 (ten) grade nominal mix 1:3:6 (one cement : three sand : six graded stone aggregate 40 mm (forty millimeter) nominal size) in open foundations and plinths as per drawings and technical specification for rural roads clause 802, 803, 1202 and 1203 and curing complete including the cost of form work and carriage of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. |
| 8 | Providing and laying boulder apron laid in wire crates with 4 mm diameter G.I. wire confirming to IS:280 and IS:4826 in 100mmx 100mm (one hundred into one hundred millimeter) mesh (woven diagonally) including 10 % (ten percent) extra for laps and joints laid with stones boulders weighting not less than 25 kg. (twenty five kilogram) each as per drawing and technical specifications clause 1301 including carriage of material in all leads, lifts as per the entire satisfaction and direction of Engineer-in-charge. |
| 9 | Back filling behind Retaining wall with granular material complete as per drawing and M.O.R.D. technical specification clause 1204.3.8. Including carriage of material within all lead and lifts and other incidentals. |
| 10 | Construction of embankment with approved material obtained from borrow pits within all leads and lifts , transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300.1 and 300.2 as per technical specification clause 301.5 and as per the entire satisfaction and direction of Engineer-in-charge. Please Enable Macros to View BoQ information |