| 1 | Earth work in excavation for roadway, including trimming bottom andside slopes in accordance with requirement of line, grades and crosssections, including disposal of surplus material with all lift and leadupto 1000 metre as per MoRT&H specification clause 301 |
| 2 | Dismantling of existing structures like culverts, bridges, retainingwalls, CC road and other structure comprising of masonry, cementconcrete, wood work, steel work, including T&P and scaffoldingwherever necessary, sorting the dismantled material, disposal ofunserviceable material and stacking the serviceable material with alllifts and lead of 50 metres as directed by Engineer |
| 3 | Providing and laying in position cement concrete of specified gradeexcluding the cost of centring and shuttering - All work upto plinthlevel 1:1½:3 (1 Cement : 1½ coarse sand : 3 graded stone aggregate 20mm nominal size). |
| 4 | Providing and laying in position cement concrete of specified gradeexcluding the cost of centring and shuttering - All work upto plinthlevel 1:3:6 (1 Cement : 3 fine/ coarse sand : 6 graded stone aggregate 40mm nominal size). |
| 5 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded20mm nominal size stone aggregate) finished with a floating coat ofneat cement including cement slurry, but excluding the cost ofnosing of steps etc. complete. including Providing /mixing ofsynthetic fibers compulsorily complying with IS 16481:2022 of 06mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e.125 gms per 50 kg Cement up to 900 gms per cum of Concrete/mortar |
| 6 | Random rubble masonry with hard stone in foundation and plinthincluding levelling up with cement concrete 1:6:12 (1 cement : 6coarse sand : 12 graded stone aggregate 20 mm nominal size) uptoplinth level with Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 7 | Brick work with FPS bricks of class designation 75 in foundationand plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 8 | Cement plastering including T&P, scaffolding, material and completelabour, including cost of water, curing, racking of joints etc. with 12mm cement plaster of mix : including Providing /mixing of syntheticfibers compulsorily complying with IS 16481:2022 of 06 mm/12 mmlength to be mixed @ 0.25% by weight of Cement i.e. 125 gms per50 kg Cement up to 900 gms per cum of Concrete/ mortar |
| 9 | Earth work for Sewer line and Manhole in excavation in foundation,trenches manholes, road side chambers etc. including dressing ofsides and ramming of bottoms, including getting out the excavatedmaterial, refilling after laying pipe/ foundation and disposal of surplusexcavated material at a lead upto 50m suitable site as per directionof Engineer for following depths, below natural ground / Road toplevel including allowances for any additional excavation beyond thedrawings (measurement for payment to be as per standarddrawings), re-handling of material/earth to complete the task |
| 10 | Structural steel work riveted, bolted or welded in built up sections,trusses and framed work, including cutting, hoisting, fixing in positionand applying a priming coat of approved steel primer all complete |
| 11 | Providing granular bedding having width = outer dia of pipe (Bc) +500mm, thickness below pipe = 0.25Bc or 100mm (whichever ishigher) and haunching = 0.5Bc, with graded hard crusher brokenstone of 100% passing through 20mm sieve, 20 to 50 % passingthrough 10mm sieve and 100 % retain on 6.3mm sieve, laying inlayers of thickness 10/15cm including ramming, consolidation etccomplete for all type of pipes of following sizes as per drawing andor as directed by Engineer |
| 12 | Providing and constructing of RR stone masonry circular manholesof \\"Type-Z\\" with internal dia 0.56m and depth upto 0.90 m having300mm thick RR stone masonry wall in cement sand mortar 1:4,including concreting PCC M-10 grade (1:3:6) for 225mm thickfoundation including curing compaction and form work etc complete,PCC M15 for benching and channel portion, PCC M15 for fixing themanhole frame and cover using stone aggregate 20mm Nominalsize, 20mm thick inside and outside plaster in C. M. 1:3, insideplaster finished with floating coat of neat cement, vata in CM1:1around pipe entering and leaving the manhole and also at thejunction of masonry and roof. Supplying and fixing heavy duty SFRCmanhole frame and cover as per IS 12592 (Part I and II) havingclear opening of 560mm, including refilling of Jhiri, including curing,watering, ramming, hydro testing of manhole, conveyance & cost ofwater, and dewatering complete as directed by the Engineer. Note-Only Excavation work will be measured and paid separately (Z-Type Manholes) |
| 13 | Construction of House Sewer Connection inside and outside ofa dwelling properties to connect all the outlets of Kitchen, Bath,toilet/WC of the property to existing inspection chamber ofSewer Network, which includes Door-to-door survey of allproperties to be connected with Sewer Network, Preparation ofsketch / drawing of arrangement for each house with all the detailsand obtain approval from Engineer In-charge or his representativeand Preparation of as built drawing (Layout plan) in AutoCAD foreach property / dwelling connection with sewer network up tomanhole |
| 14 | Providing at site, lowering & laying in trenches, aligning & jointing ofPVC-U pipes (SN 8) as per IS 15328 (amended up to date) and asper specifications with rubber rings with socket and spigot joint,(EPDM/SBR) for all depths for pipe length as per drawing andspecification including hydraulic field testing (including the cost andconveyance of water to site for testing) and commissioning etccomplete as directed by Engineer. Note : E/w to be measured andpaid separately. Length of pipe shall be measured in between theouter wall of two manholes / Inspection chambers. Pipe in themanhole/inspection chamber’s wall shall deemed to be included in |
| 15 | Supplying & fixing 560mm dia opening SFRC manhole frame &cover as per IS : 12592-2002 in existing manholes including groutingthe frame in PCC M-15 complete in all respect as directed by theEngineer. Please Enable Macros to View BoQ information |