| 1 | [11.5.1]12 mm cement plaster of mix : 1. 1:2 (1 cement: 2 fine sand) [Through Rate] |
| 2 | [11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] |
| 3 | [21.28]Providing and fixing steel bar embedded plastic steps of size 263mm x 165mm of orange colour, confirming to specification in pump chambers, manholes etc., having minimum 3mm thick polypropylene polymer confirming to is:10910 encapsulated on 12mm dia ribbed steel bars per IS :1786. The rate include cost of setting the same to correct lines and levels duly embedded in 1:2:4 cement concrete including carriage, loading, uploading, stacking, handling, re-handling etc., complete in all respect to the satisfaction of Engineer-in-charge [Through Rate] |
| 4 | [21.43]Extra over the rate laid down in this schedule for cement concrete work more making and finishing benching and complicated floor work in manholes, including formation of channels and bulldozing and smooth finishing the surface accurately to template. [Through Rate] |
| 5 | [21.93.1]Providing and fixing SFRC MANHOLE COVERS AND FRAMES MARKED WITH IS: 12592 including setting the same to correct lines and levels in 1:3 cement sand mortar over manhole including carriage loading unloading stacking handling re-handling etc. complete in all respects to the satisfaction to the Engineer-in-charge. 1. Type:- Extra Heavy Duty Set (EHD-35) 560MM Clear Opening [Through Rate] |
| 6 | [21.97.5]`Providing, lowering, laying, aligning, fixing in position and jointing at all level/ depths ISI marked HDPE pipe of PE-100 grade and PN-6 for sewer. application as per IS 14333-1996 (amended up to date) in trenches in complete including cost of HDPE Specials, labour, sectional hydro testing (including the cost and conveyance of water to site for testing) and commissioning as per Technical Specifications and as per direction of Engineer.Note: E/w to be measured and paid separately. Rate includes cost of all specials like bends, tees required during laying of pipe line along required alignment.` 5. 315 mm Outside Dia [Through Rate] |
| 7 | [21.97.7]`Providing, lowering, laying, aligning, fixing in position and jointing at all level/ depths ISI marked HDPE pipe of PE-100 grade and PN-6 for sewer. application as per IS 14333-1996 (amended up to date) in trenches in complete including cost of HDPE Specials, labour, sectional hydro testing (including the cost and conveyance of water to site for testing) and commissioning as per Technical Specifications and as per direction of Engineer.Note: E/w to be measured and paid separately. Rate includes cost of all specials like bends, tees required during laying of pipe line along required alignment.` 7. 400 mm Outside Dia [Through Rate] |
| 8 | [3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [5km] |
| 9 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] |
| 10 | [4.16.1.2]Excavating trenches of required width and depth for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m. 1.2. All kind of soil Pipes, cables etc, exceeding 80 mm dia but not exceeding 300 mm dia. [Through Rate] |
| 11 | [4.17]Extra for excavating trenches for pipes, cables etc. in all kinds of soil for depth exceeding 1.5 m, but not exceeding 3 m. (Rate is over corresponding basic item for depth up to 1.5 metre). [Through Rate] |
| 12 | [6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 13 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 14 | [6.1.3]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 3. 1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 15 | [6.1.6]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 16 | [6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 17 | [6.33.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate] |
| 18 | [7.20.2]Brick work with common burnt clay modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement Mortar 1:6 (1 cement : 6 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |