| 1 | Providing new cable trench for installation of new 11 / 11kV cable from thermal plant to CSS in FACT Cochin Division, Ambalamedu, Kochi. |
| 2 | Demolishing R.C.C. work manually / by mechanical means including stacking of reinforcement bars and disposal of unserviceable material within 50m lead as per direction of Engineer in-charge. |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains, in all kinds of soil, including dressing of sides and ramming of bottoms, lift up to 1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed by the Engineer-in-charge, with in a lead of 50m. The rates shall include bailing out water, and keeping the sides from collapsing using necessary timbering, planking, and shoring. |
| 4 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. |
| 5 | Providing and laying plain cement concrete work in 1:4:8 mix (1 cement: 4 coarse river sand/manufactured sand: 8 40mm nominal size graded hard granite broken stones) including all charges for mixing concrete, laying, consolidating, curing, cost for bailing out of water, oil, liquid mud etc. from all sources in excavated pits, trenches, etc. complete at all levels as per standard specifications but excluding the cost of shuttering, and as directed by the Engineer in-charge for foundation / levelling course etc. |
| 6 | Supplying, fabricating, conveying, and fixing reinforcement to RCC works at all levels with high strength deformed bars Fe 500D/ 550D grade Thermo Mechanically Treated (TMT) bars conforming to IS 1786 including all charges for uncoiling and straightening rods, cutting rods, bending cold, placing in position and supplying & tying with black annealed tying wire of 16 gauge, etc. complete. |
| 7 | Providing form work to cement concrete and RCC works with necessary plywood / steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks etc. including removal after completion /curing at all levels for foundation footings, bases of columns and walls and for mass concrete with straight sides. |
| 8 | Reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) work at all levels, excluding cost of centering, shuttering, finishing and reinforcement & including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer in-charge-For yard/cable trench. |
| 9 | Erection & Installation of Precast Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting placing & alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to floor five level- for solid concrete drain elements |
| 10 | Disposal of moorum/ building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved dumping ground for lead up to 10 km for all lifts, within the premises of FACT CD, complete as per directions of Engineer in-Charge. |
| 11 | Supplying, Conveying, fabrication and erection of structural steel work bolted or welded at all levels as per scope drawing for trusses, purlins, louver brackets, louver runners bracings, stair cases, platforms, hand rails ladder, threaded sag rods, splices, etc. with M.S angles, channels, tees, flats, RSJs, rods, pipes and plates including cutting, welding, cleaning, erecting and painting with two coats of zinc chromate primer (one shop coat and one coat after erection) and two coats of chemical resistant enamel paint of approved quality and colour over the primer including supply of necessary MS bolts and nuts other than holding down bolts.(The structural steel material shall be of M/s. SAIL / RINL / TISCO /JINDAL make) - Required gas and electrodes will be supplied free of cost by FACT at stores Please Enable Macros to View BoQ information |