| 1 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts,wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sidesand ramming of bottoms lift upto 1.5 m, including getting out excavated earth anddisposal of surplus excavated earth as directed, within a lead of 50 metres:: All kinds of Soil |
| 2 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts,wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sidesand ramming of bottoms lift upto 1.5 m, including getting out excavated earth anddisposal of surplus excavated earth as directed, within a lead of 50 metres:: Ordinary Rock |
| 3 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts,wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sidesand ramming of bottoms lift upto 1.5 m, including getting out excavated earth anddisposal of surplus excavated earth as directed, within a lead of 50 metres:: Hard Rock ( Blasting Prohabitted ) |
| 4 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 5 | Random Rubble masonry with hard stone in foundation and plinth including leveling up with cement concrete 1:6:12 (1 Cement : 6 coarsesand : 12 graded stone aggregate 20mm nominal size) upto plinth level and curing complete with: Cement mortar 1:6 (1 Cement : 6 coarse sand) Nallah |
| 6 | Dry Random Rubble Masonary with hard stone in foundation and plinth: (Without bond Stone) Nallah |
| 7 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering.All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 8 | Back filling with stones behind abutment, wing walls and return walls complete as per drawing and technical specifications. Stone Boulder Nallah nominal size 225mm: |
| 9 | Hand-packing stones in wire-crates; including cost of stones and excluding Cost of Crates |
| 10 | supply of Wire- Crates with 4mm dia G I Confirming to IS 280 &4826 in 100mmX100mm incl. 10% extra for laps and Joint incliding all lead lift and Carriages |
| 11 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°, landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto five level including curing but excluding the cost of centring, shuttering, finishing and reinforcement with 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 12 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 13 | Centering and shuttering including strutting, propping etc. and removal of form for: Suspended floors, roofs, landings, balconies and access platforms. Shelves (cast-in-situ) Lintel, beams, plinth beams, girders, bressumers and cantilevers |
| 14 | Centering and shuttering including strutting, propping etc. and removal of form for: Walls (any thickness) including attached pilasters, buttresses, plinth andstring courses etc. |
| 15 | Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns etc. for mass concrete. |
| 16 | Carriage of Material by M T |
| 17 | Carriage of sand at an average distance 15 Km /MT |
| 18 | Carriage of stone aggregate at an average distance 15 Km /MT |
| 19 | Carriage of stones at an average distance 10 Km /MT Please Enable Macros to View BoQ information |