| 1 | Total Amount of BoQ |
| 2 | Amount after unconditional Rebate |
| 3 | OHE WORK |
| 4 | BoQ 3: SCHEDULE - 1 OHE Work( TKM-7 ) |
| 5 | BoQ 4: SCHEDULE - 2 (OHE Work under Power Block & Dismantling work) |
| 6 | BoQ 5: SCHEDULE - 3 ( SSP & SCADA WORK) |
| 7 | BoQ 6: SCHEDULE - 4 (Provision of illumination of Yard and other places.) |
| 8 | BoQ 7: SCHEDULE - 5 (IIlumination of pathway) |
| 9 | BoQ 8: SCHEDULE - 6 (Cable Crossing for 33 KV Power Line (Only Crossing Part to be executed by RITES in Pipe Push Method) |
| 10 | Foot by foot survey for preparation of OHE pegging plan and Preparation of Design , Drawing of Overhead equipment and feeder |
| 11 | Concrete for Foundation & Plinth (i) Ordinary soil (Grade M-15) as per RDSO spec No. ETI/C/0058 or latest. |
| 12 | Concrete for Foundation & Plinth in Hard soil including rock requried chiselling (Grade M-15) as per RDSO spec No. ETI/C/0058 or latest. |
| 13 | Reinforced Concrete of M-15 grade of 1:2:4 graded stone of aggregate 20mm nominal size |
| 14 | Supply, Transportation, Testing & Commissioning of traction mast/other special masts (BFB/RSJ/B-Series/S-Series etc as required) as per RDSO Spec No.ETI/OHE/13(4/84),Drawing no. ETI/ C/ 0071, IS:2062(2011),IS:800 or latest & Core specification . |
| 15 | Erection of above mast. |
| 16 | Supply, Transportation, Testing & commissioning of TTC/Portals assembly complete with galvanization. As per RDSO Spec No.ETI/OHE/13(4/84),Drawing no. ETI/ C/ 0071, IS:2062(2011),IS:800 or latest & Core specification . |
| 17 | Erection of the above TTC/ Portal |
| 18 | Supply, Transportation, Testing & commissioning of Anti-monkey climbing device with barbed wire. |
| 19 | Erection of the above |
| 20 | Supply, Transportation, Testing & commissioning of Hard drawn grooved copper contact wire (107 Sq.mm). As per RDSO Spec No.ETI/OHE/76(6/97) & A&C slip No.1,2,3,4,5,6,7,8&9 or latest. |
| 21 | Supply, Transportation, Testing & commissioning of Cadmium copper catenary wire (65 Sq.mm),As per RDSO Spec No.ETI/OHE/50(6/97) & A&C slip No.1 to 5 or latest. |
| 22 | Supply, Transportation, Testing & commissioning of fabricated steel works other than mast (SPS). As per RDSO Spec No. ETI/OHE/13(4/84 ), Drawing no. ETI/ C/ 0071, IS:2062(2011),IS:800 or latest & Core specification . |
| 23 | Erection of the above. |
| 24 | Supply, Transportation, Testing & commissioning of Guy rod assembly, as per RDSO Spec No.ETI/OHE/P/5000 or latest. |
| 25 | Erection of the above. |
| 26 | Supply of Single bracket assembly for conventional OHE with composite insulator(1050 mm CD) |
| 27 | Erection(in NPB) |
| 28 | Supply and Erection of Over Head Equipment |
| 29 | Supply, Transportation, Testing & commissioning of regulating equipment ( 3 pulley modified type, as per RDSO Spec No.T/SPC/OHE/ATD/0060/08/06 or latest.) with normal counter weight assembly for, guide tube for conventional OHE. |
| 30 | Erection of the above. |
| 31 | Supply of Termination of double conductor of OHE with Composite Insulator |
| 32 | Erection of the above. |
| 33 | Supply of Termination of single conductor of OHE with Composite Insulator |
| 34 | Erection of the above. |
| 35 | Supply Anti-Creep with Cadmium copper Catenary wire & 9-tonne insulator(Composite), including termination and suspention arrangement |
| 36 | Erection of the above. |
| 37 | Supply, Transportation, Testing & commissioning of large 160 sq mm Copper jumper (G jumper), as per RDSO spec no.ETI/OHE/3(2/94) ,A&C Slip no.1 or latest. |
| 38 | Erection of the above. |
| 39 | Supply , Transportation, storage & guarding of small 50 sq mm Copper jumper (C/F jumper/ATJ),as per RDSO spec no.ETI/OHE/3(2/94) .with slip no.1 or latest. |
| 40 | Erection of the above |
| 41 | Supply, Transportation, Erection, testing & commissioning of Structure Bond/Longitudinal Bond/Transverse & special bond |
| 42 | Supply, Transportation, Testing & commissioning of single earth electrode with earth pit box cover complete, as per RDSO spec no.ETI/OHE/P/7021,Rev-A or latest. |
| 43 | Erection of the above. |
| 44 | Supply of Section Insulator assembly &associated fittings & fastners for OHE with Porcelain insulators 1050 CD & Bar Insulator |
| 45 | Erection of the above. |
| 46 | Supply, Transportation, Testing & commissioning of pull off arrangement for one OHE |
| 47 | Erection of the above. |
| 48 | Supply & Erection of Retro reflective type Boards-25 KV AC OHE (Danger/Caution/Number Plate etc) |
| 49 | Supply, Erection, Transportation, storage & guarding of sectioning Diagram Board (Size 4'x2') |
| 50 | Supply, Transportation, Testing & commissioning of 25 KV Single Pole Isolator 1600A( as per RDSO spec no.ETI/OHE/16(1/94) Rev.2(Mar-04) or latest.) complete with post insulator. |
| 51 | Erection of the above. |
| 52 | Supply ,erection, Transportation, storage & guarding of various types of caution boards/retro reflective boards ( To be supplied as per RDSO Specification) |
| 53 | Erection of the above. |
| 54 | Supply, Erection, Transportation, storage & guarding of Key Box for isolator |
| 55 | Supply, Transportation, Testing & commissioning of 25 KV Post Porcelain Insulator, as per RDSO spec no. TI/SPC/OHE/INS/0070(04/2007) with A&C slip no, 1 & 2 or latest |
| 56 | Erection of the above. |
| 57 | Supply, Transportation, Testing & commissioning of 25 KV/240V 25 KVA Auxiliary Transformer (as per RDSO spec no.ETI/PSI/15(8/2003) or latest) with DO fuse switch assembly complete |
| 58 | Erection of the above |
| 59 | Supply, Transportation, Testing & commissioning of cable for 240 V A.C Supply (2 Core x 70 Sq.mm) Aluminium, RDSO spec no.IS:694/2010 or latest. |
| 60 | Erection of the above. |
| 61 | Supply, Transportation, Testing & commissioning of earth bus of MS flat size 50 mm x 6 mm. |
| 62 | Erection of the above. |
| 63 | Supply, Transportation, Testing & commissioning of copper strips size (25mm x 3mm) for equipments earthing, as per RDSO spec no.IS 191/1981 & IS :613/1984 or latest |
| 64 | Erection of the above |
| 65 | Supply, Transportation, Testing & commissioning of 25 KV Cross Feeder wire 37/2.25 mm, 150 sq mm copper, As per RDSO spec no.TI/SPC/OHE/HDSCF/0030(06/03) or latest. |
| 66 | Erection of the above |
| 67 | Supply, Transportation, Testing & commissioning of suspension copper feeder complete(insulator rate not to be considered) |
| 68 | Erection of the above |
| 69 | Termination of 25 KV Cross Feeder wire 37/2.25 mm, 150 sq mm copper, As per RDSO spec no.TI/SPC/OHE/HDSCF/0030(06/03) or latest. |
| 70 | Erection of the above |
| 71 | Supply, Transportation, Erection, testing & commissioning of suspension copper feeder complete(insulator rate not to be considered) |
| 72 | Erection of the above |
| 73 | Supply, Transportation, Erection, testing & commissioning of termination arrangement of feeder wire |
| 74 | Erection of the above |
| 75 | Supply, Transportation, Erection, testing & commissioning Splicing & extension of an anchored overhead equipment. |
| 76 | Preparation of working Rule Diagram and Appendix G |
| 77 | Preparation and approval of of LOP/Pegging plan of OHE and feeder |
| 78 | Preparation and approval of As Erected LOP/SED drawings |
| 79 | Electrical related work during NI Period |
| 80 | Supply, Transportation, storage & guarding of 130 Sqmm Large Span Wire, RDSO spec no.ETI/OHE/50(6/97) with A&C slip no.1,2,3,4 & 5 or latest. |
| 81 | Erection of the above |
| 82 | Supply, erection, Transportation, storage & guarding of Antitheft charging with 5KVA transformer |
| 83 | Hiring charges of 1 no vehicle for inspection by Railway officials & RITES staff |
| 84 | Inspection Checking by Railway officials at various levels. |
| 85 | Cost for preparation of EIG documents and approval and issuance from Railways |
| 86 | Site clearance (tree trimming,rock/debris cleaning,cutting/removel of infringement) excavation. Rates will be as per govt/DSR/CPWD notified rate. |
| 87 | Hiring of Tower wagon charges for SED checking for 30 days or as per the Invoice of Railways |
| 88 | Other Misclleneous expenditure including purchasing of measuring and testing instruments & equipments and guarding (Both Armed & withoout arm if needed as per Govt. notified rates in the erected OHE) |
| 89 | Paper Public notification for charging before EIG |
| 90 | Liasioning work with Railway both at Division & HQ for the approval of the drawings and other related work up to handing over of the site. |
| 91 | Purchasing of triffer, ladder, ropes, wiring trolley and other tools for OHE work |
| 92 | Traffic & Power block charge to be paid to Railway or actual demanded by Railway |
| 93 | Furniture and office equipment including desktop/laptop and 5 in 1 printers (1 % of the estimated rate) |
| 94 | OHE spares (3% of the estimated cost) |
| 95 | Environmental Charge @1% of the total cost |
| 96 | Cutting of old mast/TTC/Portal & SPS under power block |
| 97 | Dismantling of cantilever assembly |
| 98 | Dismantling of BWA assembly |
| 99 | Dismantling of Guy rod assembly |
| 100 | Dismantling of Anticreep |
| 101 | Dismantling of Termination |
| 102 | Dismantling of 9 Tonne insulator |
| 103 | Dismantling of OHE |
| 104 | Dismantling of sectioning insulator |
| 105 | Dismantling of SP/DP Isolator |
| 106 | Slewing of OHE |
| 107 | Erection of Jumper |
| 108 | Erection of pull off arrangement |
| 109 | Splicing & extension of an anchored overhead equipment under Power Block including supply of contact & catenary splices |
| 110 | Erection of Single Bracket Assembly |
| 111 | Erection of traction mast |
| 112 | Erection of SPS |
| 113 | Erection of OHE |
| 114 | Erection of regulating equipment (3 pully type) with normal counter weight assembly for conventional OHE |
| 115 | Erection of Termination(Single/Double) |
| 116 | Erection of Section Insulator & adjustment |
| 117 | Erection of 9 Tonne Insulator |
| 118 | Transfer of OHE from one mast to other |
| 119 | Erection of 25 KV single pole isolator |
| 120 | Adjustment of OHE under power block |
| 121 | Erection of Guy rod |
| 122 | Erection of 25 KV Double pole isolator |
| 123 | Erection of cross feeder wire |
| 124 | Erection of Anticreep |
| 125 | Erection of 25kv post insulator |
| 126 | Erection of TTC |
| 127 | Erection of Aluminium feeder wire |
| 128 | Transportation of relased material to Railway / NTPC store |
| 129 | Other miscelenous items related to dismentalling and modification at SRJ |
| 130 | Preparation, Design ,Drawing and approval of all the drawings of new SSP |
| 131 | Foot by foot survey and preparation of Design & Drawing for feeder wire |
| 132 | Concrete for foundation & trench in ordinary soil. Grade: M-15 |
| 133 | Concrete for foundation & trench in hard soil. Grade: M-15 |
| 134 | Reinforced concrete for foundation, trench & baffle Wall. |
| 135 | Supply, Transportation, Testing & commissioning of main mast of Switching Station, As per RDSO Spec No.ETI/OHE/13(4/84),Drawing no. ETI/ C/ 0071, IS:2062(2011),IS:800 or latest & Core specification . |
| 136 | Erection of the above (NPB) |
| 137 | Supply, Transportation, Testing & commissioning of fabricated steel other than mast (SPS) |
| 138 | Erection of the above (NPB) |
| 139 | Supply, Transportation, Testing & commissioning of 25KV, 1600A vaccum circuit breaker, as per RDSO spec no. TI/SPC/PSI/LVCBIN/0120 (Dec , 2013) ver.0 with A & C slip no.1 (oct 2016) or latest. |
| 140 | Erection of the above. |
| 141 | 25 kV Single Pole Vacuum Interuptor with steel structure and control machanism, rating 1600Amps as per RDSO specification no. ETI/SPC/PSI/167(9/97) |
| 142 | Erection |
| 143 | Supply, Transportation,Testing & commissioning of 25 kV double Pole Isolator 1600 Amp with Insulators and accessories. |
| 144 | Erection of the above. |
| 145 | Supply, Transportation, Testing & commissioning of interlocking device |
| 146 | Erection of the above. |
| 147 | Supply, Transportation, Testing & commissioning of feeder suspension of copper feeder complete without insulator. |
| 148 | Erection of the above. |
| 149 | Supply, Transportation, Testing & commissioning of materials for termination of 25KV feeder wire |
| 150 | Erection of the above. |
| 151 | Supply, Transportation, Testing & commissioning of Porcelain 9-tonne Insulators (RI 6020-1) (1050 mm CD) as per RDSO specification no. TI/SPC/OHE/INS/0070 (04/2007) with A&C Slip No.-1 & 2 or latest. |
| 152 | Erection of the above. |
| 153 | Supply, Transportation, Testing & commissioning of 25kv PT type-II |
| 154 | Erection of the above. |
| 155 | Supply, Transportation, Testing & commissioning of 25kv PT type-I |
| 156 | Erection of the above. |
| 157 | Supply, Transportation, Testing & commissioning of 25kv current transformer (1000-750/5A) Type-II |
| 158 | Erection of the above. |
| 159 | Control and relay panel Numerical type of 1no CB and 1 nos BM |
| 160 | Erection of the above. |
| 161 | Supply, Transportation, Testing & commissioning of 42 kV Metal Oxide gapless Lightning Arrestor with Surge monitor and isolation device as per RDSO specification no. TI/SPC/PSI/ MOGTLA/ 0101 (2/2015) or latest. |
| 162 | Erection of the above. |
| 163 | Supply, Transportation, Testing & commissioning of low maintanence lead acid battery 110v,200AH with floor mounted stand. |
| 164 | Erection of the above. |
| 165 | Supply, Transportation, Testing & commissioning of battery charger for 110v, 200AH for low maintanence lead acid battery as per RDSO spec no. ETI/PSI/24(6/81) or latest. |
| 166 | Erection of the above. |
| 167 | Supply, Transportation, Testing & commissioning of single earth electrode with earth pit box cover complete, RDSO spec. no.ETI/OHE/P/7021, rev- A or latest. |
| 168 | Erection of the above. |
| 169 | Supply, Transportation, Testing & commissioning of large copper jumper 160sqmm (G jumper) |
| 170 | Erection of the above. |
| 171 | supply of Structuure bond of MS flate size 50x6mm |
| 172 | Erection of the above. |
| 173 | Supply of earth bus of GI flat size 50x6mm |
| 174 | Erection |
| 175 | Supply, Transportation, Testing & commissioning of copper strip of size 25x3mm for equipment earthing. |
| 176 | Erection of the above. |
| 177 | Supply, Transportation, Testing & commissioning of 2.5 sq mm 7 core Copper cables conform to IS: 1554/pt.I/1988. |
| 178 | Erection of the above. |
| 179 | Supply, Transportation, Testing & commissioning of 2.5 sq mm 2 core Copper cables for catenary indication. IS: 1554/pt.I/1988. |
| 180 | Erection of the above. |
| 181 | Supply, Transportation, Testing & commissioning of 4 sq mm 2 core AL. cables for heater supply. |
| 182 | Erection of the above. |
| 183 | Supply, Transportation, Testing & commissioning of 4 sq mm 2 core copper. cables for 110V DC supply . |
| 184 | Erection of the above. |
| 185 | Supply, Transportation, Testing & commissioning of Tubular Al. busbar 36mm x 28mm dia . |
| 186 | Erection of the above. |
| 187 | Supply, Transportation, Testing & commissioning of Earthing heel |
| 188 | Erection of the above. |
| 189 | Supply, Transportation, Testing & commissioning of fencing panel including gate panel. |
| 190 | Erection of the above. |
| 191 | Supply and erection of various type of enamelled plate /board. |
| 192 | Supply, erection , Transportation, storage & guarding of shock treatment chart laminated |
| 193 | Supply, Transportation, Testing & commissioning of Guy rod assembly |
| 194 | Erection of above |
| 195 | Supply, erection, Transportation, storage & guarding of Key box for isolator |
| 196 | Supply, erection, testing & commissioning of 240 Volt AC and 110 V DC distribution boards in the control room |
| 197 | Inpection & Checking by railway officer at various level |
| 198 | Internal wiring of control room and fixing of light , fan.(it includes supply, erection, testing and commissioning of electrification of the building as per site requirement.) |
| 199 | Cost of EIG approval |
| 200 | Building Civil work in SSP control room. |
| 201 | Supply, Transportation, Erection, testing & commissioning of feeder wire 150 sq mm as per RDSO spec. TI/Spec/OHE/HDSCF/0030 or latest |
| 202 | Design & Drawing of SCADA |
| 203 | Provission of SCADA equipment Hardware & Software at post |
| 204 | At RCC |
| 205 | Modification of SCADA equipment Hardware & Software at POST |
| 206 | Modification of SCADA equipment Hardware & Software at RCC |
| 207 | Supply of RTU at SSP including testing & commisioning (Rev-2) |
| 208 | Erection charge for RTU |
| 209 | Testing and seccussfull commissioning SSP & SCADA which include hiring & purchasing of testing equipments such as meggar, multimeter, tounge tester etc. |
| 210 | All earth work including excavation and filling |
| 211 | Public Notication in the Daily News paper before charging |
| 212 | Liasioning with Railway officials both at Division & HQ up to handing over of site. |
| 213 | Other Misclleneous expenditure including purching of measuring and testing instruments & equipments and guarding of erected equipment (Both Armed & withoout arm if needed as per Govt. notified rates |
| 214 | Supply of safety items i. e. Fire extinguishers, set of fire bucket with stand and first aid box, key box with suitable key chain, locks and other misc items required for commissioning of switching station. |
| 215 | Erection of Above |
| 216 | Providing, laying & fixing 100 mm dia GI Pipe (medium class) in ground complete with GI fittings including trenching & refilling etc as required |
| 217 | Supplying and laying of following size DWC HDPEpipe ISI marked along with all accessories like socket, bend, couplers etc. conforming to IS 14930, Part II complete with fitting and cutting, jointing etc. in the existing trench, complete as required.200 mm dia (OD-200 mm & ID-175 mm nominal) |
| 218 | Excavation, cleaning, trimming and other miscellenous unforseen work (Rate will be as per the Govt.Notified scheduled rate. Prior approval is required from RITES before starting of work. |
| 219 | Traffic and power block charge or as per the actual demanded by Railways |
| 220 | PSI spares as per Rly requirement @ 3% of the estimate |
| 221 | Furniture and office equipment including computer/laptop and printer @1% of the estimated cost |
| 222 | Environmental charge @1% of the total cost. |
| 223 | Supply,erection, testing , commissioning of 30 mtr High Mast tower along with feeder pillar consisting with Top Dia-150mm, Bottom Dia -625mm, section -3 (section length -10500mm) thickness-6, 5 & 4mm Base plate -840 x 36mm, PCD -740mm, with following items: High Mast sections with base plate, Lantern carriage suitable to fix 20 Nos. of Luminaries (350W LED) Symmetric, 3 suspension Head frame with Double drum winch (Gear Ratio - 53:1), Motor, 8mm SS wire rope (Grade-AISI 316) Compensating Disc, L-stopper (3 Nos.), Manual/Electrical operating handle mounting plates lightening Arrester and earthing spikes (MS GI). Traling cable (1set 5core x 4 sqmm EPR PCP Round Copper), MS GI juction box and astronomical timer. (M30 x 850 mm foundation bolts) |
| 224 | Supply, erection, testing and commissioning of 20 mtr High Mast tower along with feeder pillar panel consisting with Top Dia-150mm, Bottom Dia -410mm, section -2(section length -10300mm) thickness- 5 & 4mm Base plate -570 x 30mm, PCD -490mm, with following items: High Mast sections with base plate, Lantern carriage suitable to fix 12 Nos. of Luminaries (250W LED) Symmetric, 3 suspension Head frame with Double drum winch (Gear Ratio - 53:1), Motor, 8mm SS wire rope (Grade-AISI 316) Compensating Disc, L-stopper (3 Nos.), Manual/Electrical operating handle mounting plates lightening Arrester and earthing spikes (MS GI). Traling cable (1set 5core x 2.5 sqmm EPR PCP Round Copper), MS juction box and astronomical timer. (-M30 x 850 mm foundation bolts) |
| 225 | Foundation RCC with M-20 grade concrete Erection, testing & commissioning of 30/20Mtr. High mast |
| 226 | Supply Installation Testing & Commissoning of LED type single dome avation obstruction light for 30/20 Mtr. High mast. |
| 227 | Supply Installation Testing & Commissoning of 350W flood light fitting high power LED lamps for 30 Mtr. High mast. |
| 228 | Supply Installation Testing & Commissoning of 250W flood light fitting high power LED lamps for 20 Mtr. High mast. |
| 229 | Freight, Loading, unloading and shifting etc as requried for 30/20 Mtr. High mast. |
| 230 | Earthing with G.I. earth plate 600 mm X 600 mm X 6 mm thick including accessories, and providing masonry enclosure with cover plate having locking arrangement and watering pipe of 2.7 metre long etc. with charcoal/ coke and salt as required. |
| 231 | Supplying and laying 25 mm X 5 mm G.I strip at 0.50 metre below ground as strip earth electrode, including connection/ terminating with G.I. nut, bolt, spring, washer etc. as required. (Jointing shall be done by overlapping and with 2 sets of G.I. nutbolt & spring washer spaced at 50mm) |
| 232 | Supply of circular armoured XLPE insulated 4 core x 25sq.mm Al, L.T power FRLS cable 1100V grade. |
| 233 | Supply of 1.1 kV grade, XLPE insulated, armoured, FRLS, PVC outer sheath aluminium cable of following sizes conforming to IS:7098-(Pt-I)-1998 or latest and ISI marked - 4 C X 70 sqmm |
| 234 | Supply of 1.1 kV grade, XLPE insulated, armoured, FRLS, PVC outer sheath aluminium cable of following sizes conforming to IS:7098-(Pt-I)-1998 or latest and ISI marked - 4 C X 50 sqmm |
| 235 | Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size direct in ground including excavation, sand cushioning, protective covering and refilling the trench etc as required up to 35 sq.mm |
| 236 | Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size direct in ground including excavation, sand cushioning, protective covering and refilling the trench etc as required Above 35 sq. mm and upto 95 sq. mm |
| 237 | Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size in the existing RCC/ HUME/ METAL pipe as required up to 35 sq.mm |
| 238 | Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size in the existing RCC/ HUME/ METAL pipe as required Above 35 sq. mm and upto 95 sq. mm |
| 239 | Laying and fixing of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size on wall surface as required upto 35 sq mm( clamped with 1 mm thick saddle) |
| 240 | Supplying and making end termination with brass compression gland and aluminium lugs for following size of PVC insulated and PVC sheathed / XLPE aluminium conductor cable of 1.1 KV grade as required 3½ X 70 sq. mm (38mm) |
| 241 | Supplying and making end termination with brass compression gland and aluminium lugs for following size of PVC insulated and PVC sheathed / XLPE aluminium conductor cable of 1.1 KV grade as required 4 X 50 sq. mm (35mm) |
| 242 | Supplying and making end termination with brass compression gland and aluminium lugs for following size of PVC insulated and PVC sheathed / XLPE aluminium conductor cable of 1.1 KV grade as required 4 X 25 sq. mm (28mm) |
| 243 | Supplying and embedding following dia G.I. pipe (medium class) in pole collar/ foundation (during casting) for cable entry including bending the pipe to the required shape complete as required upto 40 mm dia |
| 244 | Supply and erection of MS cable route marker of size not less than 200x150x3mm thick M.S.Plate and welded to MS rod of min 5 mm dia including bending and fixing with the cable. |
| 245 | Supply and erection of LT feeder pillar Panel 250 Amp comprising of the items indicated as underi) Incoming MCCB 250 A,FP 35kA Ics=100%Icu)Fixed Type - 1 Noii) Outgoing MCCB 125 A, FP 35kA(Ics=100%Icu) Fixed Type - 2 Nosiii) Outgoing MCCB 63 A, FP 25kA(Ics=100%Icu) Fixed Type - 4 Nosiv) Outgoing MCB 40 Amps, FP, 10kA - 4 Nosv) Outgoing MCB 32 Amps DP 10 KA - 4 Nosvi) Outgoing MCB Single pole 32A, 10kA -4 Nosvii) Modular digital time switch and 3 phasecontactor 63 A - 2 Setviii) Sleeved/Epoxy coated copper bus-bar 400 Ain bus bar Chamberix) Indication lights |
| 246 | Supply and erection LT feeder pillar panel 125 Amp comprising of the items indicated as underi) incoming MCCB 125A, 4 pole, 35kA (Ics=100%Icu) - 1 Noii) Outgoing MCCB 63A, 4 pole, 25kA (Ics=100%Icu) - 4 Nosiii) Outgoing MCB 40A, 4 pole, 10kA - 4 Nosiv) Outgoing MCB 32A, DP, 10kA, 4Nosv) Outgoing MCB Single pole 32A, 10kA-4Nosvi)Modular digital time switch and 3 phase contactor 63 A - 2 Setvii) Sleeved/Epoxy coated copper busbar 250A in bus bar Chamberviii) Indication lights |
| 247 | Supply and erection of LT feeder pillar panel 63Amp comprising of the items indicated as under ;(i) incoming MCCB 63A, 4 pole, 35kA, fixed type (Ics=100%Icu) - 1 Noii) Outgoing MCCB 40A, 4 pole, 25kA, fixed type (Ics=100%Icu) - 4 Nosiii) Outgoing MCB double pole, 40A,10kA-2Nosiv) Outgoing MCB Single pole, of 40 A, 10kA- 4Nos v) Sleeved/Epoxy coated copper bus-bar 200 A in bus bar Chambervi) Indication lights |
| 248 | Testing , Commissioning Charge and purchasing of measuring and testing instruments |
| 249 | Excvation and earth work etc. (Rates will be as per govt/DSR/CPWD notified rate.) |
| 250 | Foot by Foot survey,Design, Drawing and approval |
| 251 | Supply of 3.0 M Long octagonal pole for path way lumeneries |
| 252 | Supply and erection of Single Arm Bracket suitable for street/pathway light fixure |
| 253 | Supply, Erection, Testing & Commissioning of LED Street/pathway fitting, pressure di-cast aluminium housing with suitable cover suitable to work on 220-240 V AC supply - 45 Watt |
| 254 | Erection of steel tubular or rail pole strut in cement concrete 1:3:6 (1 cement : 3coarse sand : 6 graded stone aggregate 40 mm nominal size ) foundation including excavation and refilling and secured with holding clamps, bolts, nuts, etc. as required. |
| 255 | Supply and erection LT feeder pillar panel 125 Amp comprising of the items indicated as underi) incoming MCCB 125A, 4 pole, 35kA (Ics=100%Icu) - 1 Noii) Outgoing MCCB 63A, 4 pole, 25kA (Ics=100%Icu) - 4 Nosiii) Outgoing MCB 40A, 4 pole, 10kA - 4 Nosiv) Outgoing MCB 32A, DP, 10kA, 4Nosv) Outgoing MCB Single pole 32A, 10kA-4Nosvi)Modular digital time switch and 3 phase contactor 63 A - 2 Setvii) Sleeved/Epoxy coated copper busbar 250A in bus bar Chamberviii) Indication lights |
| 256 | Supply and erection of LT feeder pillar panel 63Amp comprising of the items indicated as under ;(i) incoming MCCB 63A, 4 pole, 35kA, fixed type (Ics=100%Icu) - 1 Noii) Outgoing MCCB 40A, 4 pole, 25kA, fixed type (Ics=100%Icu) - 4 Nosiii) Outgoing MCB double pole, 40A,10kA-2Nosiv) Outgoing MCB Single pole, of 40 A, 10kA- 4 Nos v) Sleeved/Epoxy coated copper bus-bar 200 A in bus bar Chambervi) Indication lights |
| 257 | Supply of 1.1 kV grade, XLPE insulated, armoured, FRLS, PVC outer sheath aluminium cable of following sizes conforming to IS:7098-(Pt-I)-1998 or latest and ISI marked. (4 C X 25 sqmm) |
| 258 | As above of size 4 C X 16 sqmm |
| 259 | Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size direct in ground including excavation, sand cushioning, protective covering and refilling the trench etc as required up to 35 sq. mm |
| 260 | Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size in the existing RCC/ HUME/ METAL pipe as require up to 35 sq mm |
| 261 | Laying and fixing of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV grade of following size on wall surface as required up to 35 sq mm ( clamped with 1 mm thick saddle) |
| 262 | Supplying and making end termination with brass compression gland and aluminium lugs for following size of PVC insulated and PVC sheathed / XLPE aluminium conductor cable of 1.1 KV grade as required 3½ X 25 sq. mm (28mm) |
| 263 | Supplying and making end termination with brass compression gland and aluminium lugs for following size of PVC insulated and PVC sheathed / XLPE aluminium conductor cable of 1.1 KV grade as required 4 X 16 sq. mm (25mm) |
| 264 | Supplying and laying of following size DWC HDPE pipe ISI marked along with all accessories like socket, bend, couplers etc. conforming to IS 14930, Part II complete with fitting and cutting, jointing etc.direct in ground (75 cm below ground level) including excavation and refilling the trench but excluding sand cushioning and protective covering etc. , complete as required. 200mm Dia HDPE pipe |
| 265 | Supplying, transportation, storage ,guarding and making cable route marker with cement concrete 1:2:4 (1 cement : 2coarse sand : 4 graded stone aggregate 20 mm nominal size ) of size 60 cm X 60 cm at the bottom and 50 cm X 50 cm at the top with a thickness of 10cm including inscription duly engraved as required. |
| 266 | Earthing with G.I. earth pipe 4.5 meter long, 40 mm dia including accessories, and providing masonry enclosure with cover plate having locking arrangement and watering pipe etc. with charcoal/ coke and salt as required. |
| 267 | Supplying , laying, transportation, storage & guarding 25 mm X 5 mm G.I strip at 0.50 metre below ground as strip earth electrode, including connection/ terminating with G.I. nut, bolt, spring, washer etc. as required. (Jointing shall be done by overlapping and with 2 sets of G.I. nutbolt & spring washer spaced at 50mm) |
| 268 | Providing and fixing 6 SWG dia G.I. wire on surface or in recess for loop earthing along with existing surface/ recessed conduit/ submain wiring/ cable as required. |
| 269 | Supply and erection of LT panel, 1x100Amp. MCCB 4pole 35KA fixed as incoming & 2x63A MCB TPN 415V as outgoing, for the above pumps |
| 270 | Supply, Transportation, Testing & commissioningof 10KVA silent DG set three phase coupled with kirloskar Engine of 16BHP 1500 RPM Air cooled with AMF panel battery lead acid type fuel tank with all accessories as per CPCB norms-II |
| 271 | Erection & commissioning charge of above |
| 272 | Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m. |
| 273 | Foot by Foot survey, Design, Drawing and approval |
| 274 | Cleaning of site, cleaning of debries triming and dismenteling existing stucture |
| 275 | Supply and Laying of HDPE pipe as per IS: 4984-1995 (PN-4/PE-80, with minimum wall thickness of 6.2 mm) of different sizes under the Railway track with trenchless boring method and making good the damage as required. (Outer Dia - 160 mm) |
| 276 | Laying of one number XLPE power cable of 33 KV grade of following size in the existing RCC/ HUME/ METAL pipe as required. |
| 277 | Supply and erection of MS cable route marker of size not less than200x150x3mm thick M.S.Plate and welded to MS rod of min 5 mm dia including bending and fixing with the cable. |
| 278 | Earth Work at both sides of Railway Track |
| 279 | Supervision charges @ 6% of concerned SEB |
| 280 | Design & Approval of Drawing from TPCODL & Railway Please Enable Macros to View BoQ information |