| 1 | Clearing Jungle including uprooting of vegetation,grass,bush,wood trees and sapling of girth up to 30 cm,measured at a height of 1m above ground level and removal of rubbish upto a distance of 50 m.Outside the periphery of area cleaned (Sl No.259) |
| 2 | Scarifying the old painted surface including disposal of all scarified material at a distance of 30 m as directed by E/I (S.I. 772) |
| 3 | Earth Work in excavation of foundation of structures as drawing and technical specification, including setting out, construction of shoring and braching, removal of stumps and other deleterious matter, dressing of sides and bottom back filling the excavation earth to the extent required and and utilising the remaining earth locally for road work. (Morth Specification 3.13 304 B) |
| 4 | Construction of embankment with approved material obtained from borrow pits with all lifts and lead, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 as per MORT&H specification No.305 |
| 5 | Construction of Subgrade and earthen shoulders with apporved material obtained from borrow pits with all ifts and leads transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300.2 as per Tecnical Specification Clause 303.2 |
| 6 | Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grador on prepared surface mixing by mix in place method with rotavator at OMC and compacting with vibratory roller to achieve the desired density,complete as per clause 401 |
| 7 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with garader in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. for proper completion of the work as per MORT & H specifications Sr No. 4.14 (406 (B)). |
| 8 | Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 310 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing. |
| 9 | Providing & applying Primer coat with bitumen emulsion on prepared surface of granular base including clearing of road surface and spraying primer at the rate of 0.70 kg/Sqm. Using mechanical means including cost of all material, labour, T&P etc. required for proper completion of the work as per MORT&H specifications (2019) No. 5.01 (502). |
| 10 | Providing and applying tack coat with Bitumen (VG-10) using pressure distributor at the rate of 0.20 kg per sqm on the prepared granular surfaces cleaned with mechanical broom including cost of all type of materials,labour T&P etc. required for proper completion of the work as per MORT&H specification (2001) no.503 |
| 11 | Providing and laying dense graded bituminous mecadam (Grade-2) 100 mm thick compacted with 100-120 THP batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.50 percent by weight of total mix and filler, transporting the hot mix to work site ,laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment , rolling with smooth wheeled, vibratory and tendem rollers to achieve the desired compaction as per MORT&H specification clause No.507 complete in all respect |
| 12 | Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder(VG-30) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects |
| 13 | Earth Work in excavation of foundation of structures as drawing and technical specification, including setting out, construction of shoring and braching, removal of stumps and other deleterious matter, dressing of sides and bottom back filling the excavation earth to the extent required and and utilising the remaining earth locally for road work. |
| 14 | Cement concrete with 4 cm guage approved stone ballast ,approved coarse sand and cement in the proportion of 1:3:6 including supply of all material labour T & P etc. required for proper completion of the work. |
| 15 | Plain/Reinforced Cement Concrete in drain/Culvert complete as per Drawing and Technical Specifications. complete as per MORTH IInd Revision 2019 Specification Clause 1500,1700& 2100 (M-20) |
| 16 | Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specification Clauses 1000 and 1202 |
| 17 | Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. |
| 18 | Supply and laying of compacted 40 mm guage brick ballast around and below hume pipe(As per N.S. Item No.6C) |
| 19 | Providing ,laying and fixing of 600 mm RCC NP4 class hume pipe in proper position in culvert. |
| 20 | Providing ,laying and fixing of 1000 mm RCC NP4 class hume pipe in proper position in culvert. |
| 21 | Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications |
| 22 | Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications complete as per MORTH IInd Revision 2019 Specification 1300& 2100. Please Enable Macros to View BoQ information |