| 1 | [10.7]Providing and laying of conglomerate floor 50mm thick cement concrete topping 1:2:4 [Through Rate] |
| 2 | [11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] |
| 3 | [13.29.2]Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 2. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works [Through Rate] |
| 4 | [17.14.1]Granular Sub-Base with Close Graded Material - (Table:- 400-1) Plant mix method Construction of granular sub-base by providing Material as per Grading III (Table 400-I of MORTandH 5th revision) mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per technical clause 401 of MORTandH specifications 1. Grading I material [Through Rate] |
| 5 | [17.69.2]Interlocking Concrete Block Pavement 2. Providing and Laying 80 mm thick ISI marked Interlocking Paver Blocks conforming to IS 15658:2006/IRC SP 63: 2004 of all shapes and colours in design mix cement M 40 over the bed of 30 mm thick fine sand complete in all respect. [Through Rate] |
| 6 | [21.53]Constructing standard drain type I drain moulded and laid over lime concrete foundation rendered and finished smooth with 6 mm thick rendering concrete to be of 1.3.6 parts by volume of cement sand stone bajri and rendering to be 1:1 cement sand mortar [Through Rate] |
| 7 | [3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [5km] |
| 8 | [4.33]Excavating, supplying and filling of local earth (including royalty) by mechanical transport up to a lead of 1 km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. [Through Rate] |
| 9 | [5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate] |
| 10 | [6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 11 | [6.16]Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor four level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). [Through Rate] |
| 12 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate] |
| 13 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more [Through Rate] |
| 14 | [7.21.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] |
| 15 | [9.57.3]Providing and fixing on wall face Unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes. 3. 150 mm diameter [Through Rate] Please Enable Macros to View BoQ information |