| 1 | Supplying of all materials, labour, T&P for earthwork in excavation of foundation in all kinds of soil including dressing and levelling the bed with cost and conveyance of all materials, labour royalty T&P etc all complete as per the direction of Engineer in charge |
| 2 | Filling in foundation and plinth with sand watered and rammed including cost of sand & labour etc. all complete |
| 3 | Cement concrete (1:3:6) with 4cm. Size crusher broken hard Granite metal including cost of all labour, materials with all taxes, lead,T & P etc all complete . |
| 4 | R,C.C work M25 grade with 20 mm and down grade bhg CB chips including hoisting and laying |
| 5 | Supplying, fitting and placing uncoated HYSD bar reinforcement complete as per drawing and technical specification. |
| 6 | Fly ash bricks of 25cmx12cmx8cm. Size having crushing strength not less than 75 Kg/Sqcm. With dimensional tolerance +2%. percentin cement mortar (1:6) in foundation and plinth |
| 7 | Fly ash brick work in Super structure in cm (1:6) |
| 8 | Supplying 0f stainless steel gate of 304 grade including all cost etc |
| 9 | Fitting fixing of stainless steel including buffling ,polishing etc |
| 10 | Painting Two coats of weather coat over one coat of primer including painting charges of painter for decorative painting as per direction of Department |
| 11 | Providing and fixing in position 3 seaters cement Bench of approved design and make of minimum area 1.5 meter x 0.60meter. Overall all minimum height 0.80 m |
| 12 | providing and transplanting best quality shurbs and Hedges species 2 sides of pathway includingcost of all materials |
| 13 | providing and transplanting best quality healthy tree species 2 sides of pathway includingcost of all materials |
| 14 | providing and transplanting best quality edge plant species species 2 sides of pathway includingcost of all materials |
| 15 | Rigid smooth centering and shuttering for RCC works (column) |
| 16 | Rigid smooth centering and shuttering for RCC works (plinth) |
| 17 | 12mm cenent plaster in cm(1:6) including cost of labour ,material |
| 18 | 16mm cenent plaster in cm(1:6) including cost of labour ,material |
| 19 | Supplying of all materials Labour T&P for Providing weather coat of two coats of approved make & finished including cost of paint etc, all charges complete. |
| 20 | Cement washing one coat over the wall including cost of all materials etc comolete |
| 21 | Supplying of earth by mechanical means including all cost materials, labour etc complete Please Enable Macros to View BoQ information |