| 1 | Schedule 'A' B/R |
| 2 | Excavation post holes (or similar holes) each not exceeding 0.5 cum getting out in soft/loose soil returning filling in and ramming earth or broken rubble mixed with earth around in layers not exceeding 25cm watering and removing surplus soil to a distance not exceeding 50m and making good surfaces, complete all as specified and directed by Engr-in-Charge. |
| 3 | Excavation in trenches not exceeding 1.5 Metre wide and not exceeding 1.5 Metre deep and getting out in any type of soil, complete all as specified and directed by Engr-in-Charge. |
| 4 | Returning and filling in soil including levelling, watering and well ramming in layers not exceeding 25cm in foundation trenches, complete all as specified and directed by Engr-in-Charge. |
| 5 | Removing excavated soil not exceeding 50 Metre and depositing where directed at a level not exceeding 1.5 Metre, complete all as specified and directed by Engr-in-Charge. |
| 6 | Material & Labour for PCC 1:4:8 type D-2 (using 40mm graded stone aggregate) in foundations, filling and mass concrete, complete all as specified and directed by Engr-in-Charge. |
| 7 | Supply and fixing rolled mild steel for roof trusses (framed), trussed, purlins, crane gantries, rails, and fastenings and heavy brackets framing (Beam, tee, angle, channel or flat sections) including distance pieces etc., confirming to Fe-410-W (Gde-E-250) quality B, complete all as specified and directed by Engr-in-Charge. |
| 8 | Supply and fixing Mild steel hand rails, half round or other steel section or core for wooden hand rail straight portion, drilled and countersunk for balusters running bars, for doors, balusters, nosing to steps including embedding in concrete and screwing etc. Wind ties for roof including securing bolts, posts and struts in fencing including cutting tops to shape as directed, drilling holes, notching for wire, etc, flat iron fillets (for securing wire mesh etc.,) including all necessary drilling, bolting or riveting etc., and similar work conforming to Fe-290 Gde E-165, complete all as specified and directed by Engr-in-Charge. |
| 9 | Supply and fixing mild steel bolts with hexagonal or square head one end and screwed the other or screwed both ends each screwed end to be fitted with washers and one hexagonal or square nut exceeding 10 cm long not exceeding 15 cm long dia metre of neck and not exceeding 5 cm long, complete all as specified and directed by Engr-in-Charge. |
| 10 | Supply and fixing pre-painted galvalume aluminium zinc coating GI based corrugated steel sheet 0.50 mm thick of any colour having tensile strength of 550 Mpa as in roof covering/cladding to wall, fixed with self-tapping screws, complete all as specified and directed by Engr-in-Charge. |
| 11 | Supply and fixing pre-painted galvalume aluminium zinc coating GI based plain steel sheet 0.50 mm thick of any colour having tensile strength of 550 Mpa as in cladding to wall, as in ridges, flashing, eaves board valley gutter of any shape etc., cut to designed shape (Jhhallar) as directed at site fixed with self-tapping screws, complete all as specified and directed by Engr-in-Charge. |
| 12 | Material & Labour for preparation of new steel surfaces over 10cm width or girth and applying two coats of synthetic enamel paint over one coat of zinc chrome primer, complete all as specified and directed by Engr-in-Charge. |
| 13 | Material & Labour for Hard-core of gauge exc 63mm but not exceeding 100mm deposited spread and levelled in layers not exceeding 15cm thick watered an reamed to a true surface with broken stone or boulders, complete all as specified and directed by Engr-in-Charge. |
| 14 | Material & Labour for 100mm thick Plain Cement concrete 1:4:8, type D-2 (using 40mm graded aggregate) as in sub base of floors, complete all as specified and directed by Engr-in-Charge. |
| 15 | Material & Labour for 100mm thick Plain Cement concrete type B-1, 1:2:4 (using 20mm graded aggregate) as in flooring with alternate panel including necessary formwork, Finishing cement concrete surface even and smooth without using extra cement in alternate panels, adding with fibre reinforcement, complete all as specified and directed by Engr-in-Charge. |
| 16 | Material & Labour for Pre-cast cement concrete block masonry with solid blocks, exc. 10 cm in width and setting in mortar, type C-1, 1:3:6 20mm graded aggregate in Cement Mortar 1:4, complete all as specified and directed by Engr-in-Charge. |
| 17 | Material & Labour for Rendering 10mm thick in Cement Mortar 1:4 for finishing the surface even and smooth w/o using extra cement, complete all as specified and directed by Engr-in-Charge. |
| 18 | Material & Labour for cement concrete 1:2:4 type B-1 using 20mm stone aggregates as in Coping, complete all as specified and directed by Engr-in-Charge. |
| 19 | Material & labour for PCC 1:3:6 type C2 using 40mm graded stone aggregate as in foundation of electric poles, struts, blocks with and including necessary form work, and fair finish to exposed surfaces without using extra cement, complete all as specified and as directed by Engineer-in-Charge. |
| 20 | Schedule 'A' E/M |
| 21 | Supply, install, testing and commissioning of silent Diesel Engine Generating set factory assembled, floor mounted 415 volts, 3 phase, 4 wire engine as per IS: 10001/10002 and alternator as per IS: 13364 of capacity 58.5 KVA at site complete with relay panel for automatic starting on mains failure, control panel having meters, sound proof canopy as per CPCB IV norms etc., including necessary foundation & plinth work of DG set all accessories as per manufactures standard and as per the details given below :-AC Generator should be suitable for ambient conditions and confirming to IS. Make of Engine: -CUMMINS/Crompton Greaves/Ashok Leyland/ Kirloskar /Mahindra.Make of Alternator - Jyoti/Stamford/Crompton Greaves/Kirloskar /Mahindra.Note: The capacity of Generator set shall be net after all derating factor as per relevant IS design. |
| 22 | (a) Alternator: Synchronous alternator for continuousoperation at 1500 RPM generating 415 volt at 0.8 PF suitable for 50 hz, three phase 4 wire system. The alternator shall be brushless, single bearing, self-excited & self-regulated with an AVR. The alternator will be suitable for tropical climate and shall generally conform to IS: 4722. The salient features of the alternators are :-(i) +- 1% voltage regulation (max) in static conditions. (ii) IP 23 protection with H insulation (iii) Permanent lubricating bearing (iv) Permissible overload 10% for one hour in 12 hours of operation.b) Diesel Engine: Having adequate capacity for 58.5 KVA alternator, BHP not less than capacity for 58.5 KVA alternator, water cooled to drive alternator with cold starting with an over load capacity of 10% for one hour in any 12 hours continuous running complete with all standard accessories all as specified. supply for starting system or as recommended by manufacturer, Maintenance free battery with initial charging, residential type exhaust silencer complete with exhaust pipe, hour meter, water temp gauge, oil pressure gauge, Fuel tank with capacity for full load non-stop 8 hrs running. |
| 23 | (c) Sound proof Canopy All as per stipulated in CPCB IV norms & the Govt of India.(d) AMF Panel: Supply, install, testing and commissioning of AMF Panel outdoor type, cubical body, dust and vermin proof made up of CRCA sheet 3 mm thick painted with two coats of synthetic enamelled paint over a coat of red oxide primer confirming to IP 45 with front and rear opening with louvers and mounted on floor with PCC pedestal pillars with a clearance of at least 0.3 Metre above ground level with glands sockets etc with provision of cable entry from bottom all pre wired and connected complete with following accessories:-(i) AMF Controller (ii) Power Contactor heavy duty suitable for generator and mains (iii) Over load relay for Gen set (iv) Suitable rating isolating switch MCCB for both DG & main Specification. |
| 24 | Air intake system : (i) Air intake manifold (ii) Dry type air cleaner (iii) Vacuum Indicator Exhaust System:- (i) Expansion below (ii) Exhaust manifold Cooling system (For Air cooled) : (i) Blower fan in built engine (ii) Exhaust fan For Water cooled (i) Engine water pump (ii) Coolant (iii) Radiator with pusher type fan Lubricating System:- (i) Lube Oil cooler (ii) Lube oil Filter \\"Spin-on\\" type Fuel System:- (i) Filter \\"Spin-on\\" type (ii) 12 V DC solenoid coil (iii) Inline fuel injection pump and fuel feed pump Starting System:- (i) 12 Volt starter (ii) 12 volt DC solenoid coil (iii) 12 Volt DC Battery charging Alternator Instrument Panel:- (i) Start/Stop Push Bottom (ii) Lube oil pressure indication (iii) water temperature indication (iv) RPM indication (v) Engine running hour indication (vi) Low lube oil trip indication (vii) High Engine temperature trip indication (viii) Battery Charging Indication (ix) Over/under Speed trip indication (x) Low Fuel level indication (xi) Over load trip Indication Safety Controls: (i) Low lube oil pressure trip (ii) High Engine temp trip (iii) Low fuel level trip (iv) Overload trip (v) Over /under speed trip Please Enable Macros to View BoQ information |
| 25 | Air intake system : (i) Air intake manifold (ii) Dry type air cleaner (iii) Vacuum Indicator Exhaust System:- (i) Expansion below (ii) Exhaust manifold Cooling system (For Air cooled) : (i) Blower fan in built engine (ii) Exhaust fan For Water cooled (i) Engine water pump (ii) Coolant (iii) Radiator with pusher type fan Lubricating System:- (i) Lube Oil cooler (ii) Lube oil Filter \\"Spin-on\\" type Fuel System:- (i) Filter \\"Spin-on\\" type (ii) 12 V DC solenoid coil (iii) Inline fuel injection pump and fuel feed pump Starting System:- (i) 12 Volt starter (ii) 12 volt DC solenoid coil (iii) 12 Volt DC Battery charging Alternator Instrument Panel:- (i) Start/Stop Push Bottom (ii) Lube oil pressure indication (iii) water temperature indication (iv) RPM indication (v) Engine running hour indication (vi) Low lube oil trip indication (vii) High Engine temperature trip indication (viii) Battery Charging Indication (ix) Over/under Speed trip indication (x) Low Fuel level indication (xi) Over load trip Indication Safety Controls: (i) Low lube oil pressure trip (ii) High Engine temp trip (iii) Low fuel level trip (iv) Overload trip (v) Over /under speed trip Please Enable Macros to View BoQ information |