| 1 | E/W in excavation in foundation trenches in all kinds of soil -do- -do- all complete job as per specification and direction of E/I.(5.1. |
| 2 | Providing sand filling in foundation trenches -do- -do- all complete job as per specification & direction of E/I. |
| 3 | Providing Class 75B brick flat soling joint filled with local sand -do- -do- all complete as per specification and direction of E/I. |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)In Foundation |
| 5 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 5.2.2 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).In Column |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete. |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts. |
| 8 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) |
| 9 | Providing 75B brick work in C.M. (1:6) in super structure -do- -do- all complete job as per specification and direction of E/I. |
| 10 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).In Band at Lintel Level |
| 11 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers. |
| 12 | Providing 12mm thick Cement Plaster in CM (1:6) over walls -do- -do- all complete as per specification and direction of E/I. |
| 13 | Providing TMT steel reinforcement 8mm dia rods to 10mm dia -do- -do- all complete as per specification and direction of E/I.(I) 8MM dia |
| 14 | 10mm dia - |
| 15 | Earth work filling in foundation and plinth -do- -do- all complete job as per specification and direction of E/I.Quantity 1/3rd vide item no. 1 |
| 16 | Providing two coats of snowcem over new surface -do- -do- all complete job as per specification and direction of E/I.Quantity vide item no. 11 |
| 17 | Providing and fixing concertina coil fencing with punched tape concertino coil 600mm dia 10 metre openable length (total length 90m) , having 50 nos rounds per 6m legth, upto 3m height of wall with existing angle iron shaped placed 3m apart and 9 horizontal R.B.T reinforced barbed wire ,stud tied with G.I staples and G.I clips to retain horizontal , including necessary bolts or G.I barbed wire tied to angle iron, all complete as per direction of E/I with reinforced barbed tape (R.B.T ) / spring core (2.5 m thick) wire of high tensile strength do do all |
| 18 | Carriage of materials including loading, unloading, stacking -do- -do- all complete job as per specification and direction of E/I. (i)cement |
| 19 | (ii) Sand |
| 20 | (iii) Stone Chips |
| 21 | (iv) Steel |
| 22 | (v) Bricks |
| 23 | GST @ 18 % |
| 24 | Labour cess @ 1% Please Enable Macros to View BoQ information |