| 1 | Earthwork in excavation of foundation in ordinary soil /sandy loam , clay or sand including lift up to 1.5 m, and lead up to 30 m including filling, watering, ramming, of excavated earth into the trenches or up to spaces and sides of the foundation trenches with dressing and manual compaction as per the direction of Engineer-in-charge. |
| 2 | Laying plain cement concrete(1:3:6) in foundation with stone ballast up to 3.00 m lift and 60m lead including mechanical vibration, cost of all material, labour and T&P, etc as per direction of Engineer -in-charge. |
| 3 | Centering & Shuttering for RCC Work including cost of all material, labour and T&P etc as per direction of Engineer-in-charge.. |
| 4 | Providing and Fixing Steel Reinforcement including cutting, bending, binding, and placing in position of reinforcement (Tor steel Fe 550) incluing cost of binding wire as per direction of site-in-charge |
| 5 | Providing and Laying RCC 1:1.5:3 CC Mix (M20) with maximum size of aggregate 20 mm size crushed stone ballast and coarse sand having F.M. not less than 2.0 including cost of all material, labour,and T&P etc complete as per direction of Engineer-in-charge. |
| 6 | E.w. in restoration of bank in all type of soil with manual compaction and dressing and lift up to 1.5 m, and lead up to 30 m, including all cost of labour, material, T&P etc complete as per direction of site-in-charge. |
| 7 | Providing and Laying 1:2:4 CC mix (M15) in coping with coarse sand, cement and 10 mm to 20 mm crushed stone grit including cost of all material, labour and T&P etc as per direction of Engineer-in -charge. |
| 8 | Providing and fixing of Boundary Pillar in I section 15 cm × 15 cm as per drawing with total length 1.65 m, grouted in 30cm×30 cm section cement concrete M 20 in 75 cm depth, with 07 nos, wire of 4 mm dia including top cap, painting and lettering as per instruction of Engineer-in-charge. |
| 9 | Centering & Shuttering for precast RCC Work including cost of all material, labour, etc as per direction of Engineer-in-charge.. |
| 10 | Painting of KM stone Pillar and tail wall with premium quality plastic emulsion paint to give an even shade after curing and cost of all material as per direction of Engineer-in-charge |
| 11 | Writing Letter on both side of KM stone Pillar and gauge pillar including all cost of material, sand paper and labour as per direction of Engineer-in-charge |
| 12 | Brick masonry in 1:4 cement and coarse sand mortar complete as per direction of Engineer-in-charge. |
| 13 | Deep struck pointing on brick masonry in 1:2 cement sand mortar including cost of all material, Labour and T&P, etc complete as per direction of Engineer-in-charge |
| 14 | Fabrication and fixing of head regulator gate of distributries taking off from Sagra Distributory complete as per direction of Engineer-in-charge |
| 15 | Fabrication and fixing of head regulator gate of Minors taking off from Sagra Distributory as per direction of Engineer-in-charge Please Enable Macros to View BoQ information |