| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. All kinds of soil |
| 2 | Supplying and filling in plinth with sand under floors,including watering, ramming, consolidating and dressing complete. |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources). |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 5 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement- All work up to plinth level :1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form forCentering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form forCentering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers |
| 9 | Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing inposition and applying a priming coat of approved steelprimer all complete. |
| 10 | Providing and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete. Fixed to steel windows by welding |
| 11 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade :One or more coats on old work |
| 12 | Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50mm including strengthening with 2mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge. Made of G.I. wire of dia 4mm. |
| 13 | Providing and laying European standard ITF certified 8 layers acrylic synthetic providing and laying European standards ITF certified standards system with thickness upto 3mm. 1 Layer of deep patch for cracks only. 2 Layer of acrylic primer. 3 layers of acrylic resurfacer. 4 layars of acrylic cushion . 5 layers of colour coat 6.Line marking as per international standards. As per direction of Engineer-Incharge. |
| 14 | Brick work with FLY ASH BRICK in Superstructure in cement morter 1:6( 1 Cement: 6 coarse sand) etc. complete as per instruction of the EIC. |
| 15 | 12 mm cement plaster of mix :1:6 ( 1 cement: 6 fine sand) |
| 16 | Boulder/murrum filling in plinth including watering, ramming compaction etc. cost of all materials & labour complete as per instruction of EIC (100cft boulder & 40 cft murrum for 100cft finished work) |
| 17 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |