| 1 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 2 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 3 | Sand filling in plinth including supply of necessary quantity of sand the site of work & including watering, dressing etc. Rate to include cost of all materials, labour and tools & plants etc. required for proper completion of the work. (S.I.No. 255) (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 4 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 5 | Furnishing and Placing Reinforced/ Prestressed cement concrete in M20 super-structure as per drawing and Technical Specification. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 6 | (M-25) R.C.C work for Slab with cement approved coarse sand and 2cm gauge approved dalla grit proportion as per job mix excluding supply of reiforcement and its bending but uncluding its fixing and binding the same with 24BWGGI binding wire complete in all respect. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 7 | (M-30) R.C.C work for Slab with cement approved coarse sand and 2cm gauge approved dalla grit proportion as per job mix excluding supply of reiforcement and its bending but uncluding its fixing and binding the same with 24BWGGI binding wire complete in all respect. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 8 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 9 | (M-25) R.C.C work for Slab with cement approved coarse sand and 2cm gauge approved dalla grit proportion as per job mix excluding supply of reiforcement and its bending but uncluding its fixing and binding the same with 24BWGGI binding wire complete in all respect. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 10 | RCC Grade M20 using batching plant transit mixer & manual placing:-Reinforced Cement Concrete complete as per Drawing and Technical Specifications. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 11 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 110 mm dia PVC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 12 | Furnishind & fixing of Drainge Spouts or drainage pipe 100 mm dia in Bridge Deck as per specification (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 13 | Pressure relife pipe of 100 mm dia shall be provided in Raft area, 0.5x.0.5 m below pressure relife pipe shall be provided in the form of invert filter. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 14 | Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 710.1.4.of IRC:78 & 2200 (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 15 | Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 40 kg each complete as per drawing and Technical specification. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 16 | Providing and laying Filter material underneath pitching in slope complete as per drawing and Technical Specification (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 17 | Providing and laying ptching on slopes laid over prepared filter media as per drawing and technical specification clause 1302 (in pitching slope) (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 18 | Construction of Embankment with Material Obtained from Right of way:- Construction of embankment with approved material obtained from Right of way with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5I (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 19 | Providing laying and spreading Material on a prepared sub grade, adding cement @ 2% by weight to the spread Material manually mixing in place with rotavator and compacting with the road roller and OMC to achieve the desired uncomfined compressive strength and to form a layer of sub-base. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 20 | Providing laying and spreading Material on a prepared sub base, cement @ 4% by weight to the spread Material manually mixing in place with rotavator and compacting with the road roller and OMC to achieve the desired uncomfined compressive strength and to form a layer of sub-base/base (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 21 | Providing and applying tack coat with Bitumen VG-10 using bitumen distributor at the rate of 0.30 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 22 | Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type C as per Technical Specification Clause 508. (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 23 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510 (Including all material, T&P, labour cess etc. but excluding G.S.T.) |
| 24 | Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from Right of way with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 as per Technical Specification Clause 303.1..(Including all material, T&P, labour cess etc. but excluding G.S.T.) Please Enable Macros to View BoQ information |