| 1 | Earth work in excavation Earth work in excavation by machanical means (hydraulic excavator)/manual means in foundation trenches or drains(not exceeding 1.5mtr.in width or 10 sqm on plan) excavated soil and disposal of surplus excavated soil as directedearth in to the trenches or in to the space between the building and the side of foundation trenches or in to the plinth and removal and disposal of surplus earth as directed by th within a lead of 50m including dressing of sides and ramming of bottoms lift upto 1.5m including getting out the all kind of soil..PWD SCH.(2/2.8) |
| 2 | Providing and Laying, in cement concrete 1:6:12 (1cement : 6 Finesand : 12 brick ballast 40mm./ Nominal size) and curring complete, including cost of form work in foundation and floos.PWD SCH.(273) |
| 3 | R.C.C. in (1:1.5:3) with cement, C/sand and 20mm gauge stone gritt i/c all comp. at site. Raft PWD SCH.16/(5.1.2) |
| 4 | M-150 class brick work in foundation in 1:4 etc all complete.PWD SCH (1/6.1.1) |
| 5 | R.C.C. in (1:1.5:3) with cement, C/sand and 20mm gauge stone gritt i/c all comp. at site. Beam PWD SCH.16/(5.1.2) |
| 6 | R.C.C. in (1:1.5:3) with cement, C/sand and 20mm gauge stone gritt i/c all comp. at site. Column PWD SCH.16/(5.1.2) |
| 7 | M-150 class brick work in super structure in 1:4 etc all complete.PWD SCH (2/6.4.1) |
| 8 | 12mm thick plaster in 1:4 etc all complete.PWD SCH (2/13.4.1) |
| 9 | Providing and Laying of1mm thick putty etc all complete.PWD SCH (15/23/13.8) |
| 10 | Providing and Laying of oil destemper paint of two coat etc all complete.PWD SCH(7/649+8/650) |
| 11 | Mild steel or Iron in plain work such as reinforced concrete or Reinforced brick work wrought to required shape as necessary incuding bemdimg for proper compeletion of the work and including supply of steel its wastage bend books and authorised overlapping sall be measured upto floor two level. |
| 12 | Steel reinforcement for RCC work including straighting ,cutting,bending,placing in position and binding all complete upto plinth level.PWD SCH (22/5.22.6) Thermo machaniacally trated bars of grade Fe-500D or more(Labour only) Thermo machaniacally trated bars of grade Fe-500D or more(Labour only) |
| 13 | Centering and Shuttring including strutting propping etc and removal of form for Raft PWD SCH.(20/5.9.1) |
| 14 | Centering and Shuttring including strutting propping etc and removal of form for Column PWD SCH.(20/5.9.6) |
| 15 | Centering and Shuttring including strutting propping etc and removal of form for Beam PWD SCH.(20/5.9.4) |
| 16 | Supply and fixing of MS gate etc all complete.PWD SCH (21/10.25.2) |
| 17 | Providing and Laying of iron paint etc all complete.PWD SCH(1/641+642) |
| 18 | Supply & Fixing of Granite stone with letter writing board. |
| 19 | GST (18%) Please Enable Macros to View BoQ information |