| 1 | Dismantling Of old damaged Brick work in cement mortar |
| 2 | Excavation work for of Soil including, lift upto 1.50 M and lead Upto 30m |
| 3 | Cement Concrete with 2cm gauge brick ballast fine sand & cement proportion of 1:4:8 Complete work as per S.I. No. 281 |
| 4 | RCC Work with cement, approved coarse sand and 2 cm gauge approved stone grit in proportions of 1:1.5:3 in Reft foundation and footing |
| 5 | RCC Work with cement, approved coarse sand and 2 cm gauge approved stone grit in proportions of 1:1.5:3 in Beam |
| 6 | RCC Work with cement, approved coarse sand and 2 cm gauge approved stone grit in proportions of 1:1.5:3 in Column Or Wall |
| 7 | RCC Work with cement, approved coarse sand and 2 cm gauge approved stone grit in proportions of 1:1.5:3 in Slab |
| 8 | Supply, Fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications including supply of all material, labour, Tools & Plants etc. required for proper completion of work |
| 9 | Providing & Fixing of 110mm Internal dia P.V.C.pipe pressure of 6Kg/ Cm2 |
| 10 | Cartage for disposal of malba/Surpluse earth upto 5.0Km |
| 11 | Providing cost of dewatering including cost of boaring, laying of 4'' dia PVC pipe, Hire charges of 7.50 KV Deisel pumping Set, Hire Charges of PVC pipe & cost of 4'' dia plastic pipe for disposal of water as required distance also including wages of repairing leakage during operation with hire charges of tractor including loading and unloading of pumping set. SOR 12.45A |
| 12 | Providing & Supply gunny bags including cost of sand and stitching of bags and laying in position. |
| 13 | Removing of bags upto 100 meter |
| 14 | M.S. or iron work of small sizes and section such as holding down bolts, hold fast, tie rods grating etc. wrought to required from including supply of steel bolts, nuts wastage etc. and theirfixing required for proper completion of the work |
| 15 | Supply and Fixing inoguration black granite stone padestal including grooving matter, brick work, plaster, painting etc. all complete |
| 16 | Deduct cost of old brick bats. |
| 17 | GST 18 % Please Enable Macros to View BoQ information |