| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. |
| 2 | All kinds of soil. |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lif. |
| 4 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : |
| 6 | 1:2:4 (1 cement : 2 coarse sand (zone-Ill) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 7 | 1:4:8 (1 Cement : 4 coarse sand (zone-Ill) derived from natural sources: 8 graded stone aggregate 40 mm nominal size derived from natural sources) |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form work for: |
| 9 | Foundations, footings, bases for columns |
| 10 | Extra for providing and mixing water proofing material in cement concrete work in doses by weight of cement as per manufacturer's specification. |
| 11 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : |
| 12 | 1:1.5:3(1 cement: 1.5 coarse sand (zone-Ill) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 13 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement: |
| 14 | 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 15 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15 degree landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). |
| 16 | Centering and shuttering including strutting, propping etc. and removal of form for |
| 17 | Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. |
| 18 | Suspended floors, roofs, landings, balconies and access platform |
| 19 | Edges of slabs and breaks in floors and wallsi) Under 20 cm wide |
| 20 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. |
| 21 | Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 22 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level. |
| 23 | Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 24 | Providing and fixing in position copper plate as per design for expansion joints. |
| 25 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. |
| 26 | 40 mm thick with 20 mm nominal size stone aggregate |
| 27 | 12 mm cement plaster of mix: |
| 28 | 1:4(1 cement: 4 fine sand) |
| 29 | 12 mm cement plaster finished with a floating coat of neat cement of mix: |
| 30 | 1:4(1 cement: 4 fine sand) |
| 31 | Finishing walls with Acrylic Smooth exterior paint of required shade: |
| 32 | New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm) |
| 33 | Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc. External work |
| 34 | 80 mm dia nominal bore |
| 35 | Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality : |
| 36 | 80 mm diameter pipe Please Enable Macros to View BoQ information |