| 1 | Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 2 | Construction of Embankment with Material obtained from Borrowpits (Lead 3 Km.) :-Construction of embankment with approved material obtained from borrow pits with all lifts and leads with 3 Km, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 3 | Construction of Subgrade and Earthen Shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 4 | Construction of embankment with approved material deposited at site form roadway cutting and excavation form drain and foundation of other structures graded and compacted to meet requirement to table 300-2. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 5 | Construction of granular sub-base by providing well graded Material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and and compacting with vibratory roller to achieve the desired density, complete as per clause 401 Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 6 | Wet Mix Macadam (Plant Mix Method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 7 | Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 8 | Dense Graded Bituminous Macadam Grading-1Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder (VG-30) @ 4.0 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 9 | Providing and applying tack coat with bitumen VG-10 grade bitumen pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 10 | Dense Graded Bituminous Macadam Grading-2Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder (VG-30) @ 4.50 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 11 | Providing and applying tack coat with bitumen VG-10 grade bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 12 | Bituminous Concrete:- Grade-2Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder (VG-30) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 13 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 14 | Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 15 | Providing, Laying & Fixing reinforced concrete pipe 600 mm dia NP-3 for culvert in single row including cost of all material, Labour and T&P ect. Complete Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 16 | Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 17 | RCC Grade M20 using batching plant transit mixer & Concrete Pump. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 18 | Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in sub-structure complete as per Drawing and Technical Specifications. Including all material, labour, T&P, Taxes, Cess etc. complete as per direction of Engineer-in-charge but excluding GST. |
| 19 | 05 years Maintenance Charge @ 2.5% Routine maintenance of road for 05 years after the completion of work vide GO No. - 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 & Latter No. 36890C/RMC/Mool-23-24, Date 17.02.2024 of ENC PWD, Lucknow Rate Excluding Cost of G.S.T.First year Maintenance Charge @ 0.00%Second year Maintenance Charge @ 0.25% |
| 20 | Third year Maintenance Charge @ 0.50% |
| 21 | Fouth year Maintenance Charge @ 0.75% |
| 22 | Fifth year Maintenance Charge @ 1.00% Please Enable Macros to View BoQ information |