| 1 | Cartage of PCC/ST Poles from Central Store to dump site with loading/Unloading and from JE store/dump site to work site with loading/Unloading etc. |
| 2 | Cartage of line Materal form Central Store to JE store and JE store to diffrerent work site Including Unloading at both ends. |
| 3 | Dimentling and Erection /straightening of PCC/ST Pole as single support for 11KV/LT Line after digging of pit of proper size and all type of Soil including back filling of the pole proper raming after completion of work. |
| 4 | Dismentling & Erection/ straightening of Double Pole after digging of pit of required size in all type of soil for each pole, including back filling of the pole with proper after completion of work |
| 5 | Dismentling & Laying, lifting & Sagging of 11 KV & LT bare conductor |
| 6 | Dismentling & Laying of 11KV XLPE Cable . |
| 7 | providing and Fixing of Jointing Kit off size . |
| 8 | Dismentling of old plinth & Making of Plinth with brick & other necessarie material / with gatar pole / appropriate Channel(as per site requirement) |
| 9 | Dismentling,Providing,repairing & fixing off fencing off size (as per site requirement) |
| 10 | Cartage of T/F lodded Trolly from je store & fixing of TF Trolly at work site ,after completion of work back cartage of loaded trolly to je store . |
| 11 | Providing & Fabrication of Gatar pole /MS angle as a base on plinth for transformer. |
| 12 | Providing & Fixing of Top/ Dropper /base channel (as per site requirement) |
| 13 | Installation of distribution T/F, size 250/400/630 on plinth (including compact TF) |
| 14 | Installation of distribution T/F, size 100/63 on plinth/ double pole |
| 15 | Fixing of all required accessories on double pole structure. |
| 16 | Fixing of all required accessories on single pole structure. |
| 17 | Water level earting of neutral and body of distribution transformer of 11/0.4 kv T/F by boaring of earth upto water level(15 to 20 mtr) and lowering of GI Pipe 32 mm dia upto water level and connecting the same by ms flate of size 40x4 mm wiht transformer. The transformer will be earthed porperly including/cuttingm jointing welding etc of MS earthing with the neutral bushing of transformer and other to the body of transformer at several points. The GI Pipe will be connected to each other with the help of G.I. Sockets and a cap will be provided on the upper part of the G.I. Pipe for pouling of water during summer season |
| 18 | Dismentling & Laying of LT XLPE cable of all Size |
| 19 | Dismentling & Laying of LT ABC off size |
| 20 | Providing and Fixing of 11KV Fuse Set |
| 21 | Providing & Fixing of 11 KV TPMO Set |
| 22 | Providing & Fixing of LT Fuse set Unit |
| 23 | Providing and fixing of Tail less unit on DT properly complete work in all respect(double /tripple Circuit) as per site requirment.( with all material required ) (as per site requirement) |
| 24 | Providing & Fixing of Suspension Clamp with Hook (as per site requirement) |
| 25 | Providing & fixing of LT Aluminum crimping lugs ( as per site requirement ) |
| 26 | Providing &Fixing of Distribution Box (as per site requirement) |
| 27 | Provding & fixing copper L pieces 125*65*1300 mm (as per site requirement) |
| 28 | Grouting/Concreting of Pole |
| 29 | Providing and Fixing of all type off size Clamps (pierceing,dead end etc )as per site requirement |
| 30 | Providing & Fixing of Stay Set with grouting . |
| 31 | Providing of earthing rods and Earthing of poles with gi wire complete in all respect |
| 32 | Providing & Fixing of Bracing set with clamp with bolts (as per site requirement) |
| 33 | Providing & Fixing of F-Bracket (as per site requirement) |
| 34 | Providing & Fixing of nut bolts (as per site requirement) |
| 35 | Cartage of all material received from site to central Store Please Enable Macros to View BoQ information |