| 1 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil : |
| 2 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. 2.1) All kinds of soil |
| 3 | Ordinary Rock |
| 4 | Extra for every additional lift of 1.5 m or part thereof in excavation/banking excavated or stacked material 3.1)All kinds of soil |
| 5 | Ordinary or Hard Rock |
| 6 | Removal of unhygienic materials (so classified by the site engineer) from designated sites and its disposal as per directions, all inclusive. |
| 7 | Filling empty cement bags with sand/ earth; including cost of sewing and strings; excluding cost of bags and earth / sand. |
| 8 | Silt clearance from canals. Inclusive of initial lead and lift ( 50m & 1.5m respectively ) 6.1)Wet |
| 9 | Cleaning and desilting of gully trap chamber, including removal of rubbish mixed with earth etc. and disposal of same, all as per the direction of Engineer-in-charge. |
| 10 | Supply of High Density Polyethylene Pipes of approved standard make & type as including all carriages upto site of work & necessary fitting for use.8.1)200 mm dia |
| 11 | 300 mm dia |
| 12 | Weed clearance 9.1) From lakes(using boats) |
| 13 | From canals(including extraction of roots) |
| 14 | Supply of Polyvinylchloride Pipes of approved standard make & type as including all carriages upto site of work & necessary fitting for use.10.1)200 mm dia |
| 15 | 300 mm dia |
| 16 | Slip Clearance 11.1)In ordinary soils disposal lead upto 50 m and lift upto 1.5 m. |
| 17 | In soils; mixed with moorum/Kankar/shingle/boulders; disposal lead upto 50 m and lift upto 1.5 m. |
| 18 | In soils; mixed with Decomposed Rocks; by blasting or any other means |
| 19 | Engagement of labour |
| 20 | Hire Charges for cutting saw machine (wood cutter) with operator and fuel charges. |
| 21 | Supply of Stone dust |
| 22 | Supply of Polythene sheets including all carriages & necessary fitting. |
| 23 | Hydraulic excavator (3D) with driver and fuel |
| 24 | Hire Charges/Engagement of Mechanical excavator/Poclain chain type including POL with driver including all carriages to & fro from site of work. All complete job |
| 25 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30 cm measured at a height of 1 m above ground level and removal of rubbish upto a distance of 50 m outside the periphery of the area cleared |
| 26 | Clearing grass and removal of the rubbish upto a distance of 50 m outside the periphery of the area cleared. |
| 27 | Repairs to Existing Hydraulic gates including Realigning,bendind/straightening,Screw/winch Rods,welding,opening/refixing,malfunctioning,nut bolts, primer/painting,greasing and oiling during any emergent condition. All complete Job |
| 28 | Loading/Unloading sand/earth filled bags in lorries average lead upto 50m |
| 29 | Hire charges of diesel truck 9 ton capacity including all POL/costs involved for carriages of Men & machinery and material upto Road side/ site of work. |
| 30 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 31 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns |
| 32 | 12mm Cement plaster of mix: 1 : 4 ( 1 cement : 4 fine sand) |
| 33 | Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints etc. complete26.1) 300 mm dia. R.C.C. pipe |
| 34 | 450 mm dia. R.C.C. pipe |
| 35 | 600 mm dia. R.C.C. pipe |
| 36 | 900 mm dia. R.C.C. pipe |
| 37 | Carriage of RCC pipes from source to the site of work/road side for avg. 20 Kms by Mechanical Transport including cost of loading, unloading and stacking.27.1)300 mm dia. R.C.C. pipe |
| 38 | 450 mm dia. R.C.C. pipe |
| 39 | 600 mm dia. R.C.C. pipe |
| 40 | 900 mm dia. R.C.C. pipe |
| 41 | Carriage of materials from source to the site of work by Mechanical Transport including cost of loading, unloading and stacking.28.1)20mm stone agg. for average 20 Kms |
| 42 | Sand for avg. 20 Km |
| 43 | Cement for avg. 20 km |
| 44 | Sand/dust for avg. 20 KM |
| 45 | EC bags avg. 20Km |
| 46 | Carriage of material by manual labour including loading unloading and stacking upto 100 mtrs.29.1)Sand/dust. |
| 47 | EC bags Please Enable Macros to View BoQ information |