|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge.(DSR 2.6.1) |
| 2 | Providing and laying 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :(DSR 4.1.10)) |
| 3 | Brick work in foundation & plinth with old dismantled bricks (supplied by department free of cost) and coarse sand mortar in 1:6 including supply of all other materials, labour, removing mortar & cleaning of old & used bricks,T&P etc complete.( CSI:6.18) |
| 4 | Demolishing brick work In cement mortar manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge(DSR 15.7.4). |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts(DSR 5.9.6) |
| 6 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 Cement mortar 1:6 (1 cement : 6 coarse sand) in superstructure above plinth level up to floor V level in all shapes and sizes in (DSR 6.4.2) |
| 7 | 12 mm cement plaster1:4 (1 cement: 4 coarse sand) of mix :(DSR 13.4.1) |
| 8 | Providing and laying 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level .(DSR 4.1.2) |
| 9 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete.(DSR 13.80) |
| 10 | Finishing walls with Acrylic Smooth exterior paint of required shade :New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm) (DSR 13.46.1) |
| 11 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.(DSR 10.2) |
| 12 | Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture. (DSR 13.62.1) |
| 13 | Providing and fixing concertina coil fencing with punched tape concertina coil 600 mm dia 10 metre openable length ( total length 90 m), having 50 nos rounds per 6 metre length, upto 3 m height of wall with existing angle iron 'Y' shaped placed 2.4m or 3.00 m apart and with 9 horizontal R.B.T. reinforced barbed wire, stud tied with G.I. staples and G.I. clips to retain horizontal, including necessary bolts or G.I. barbed wire tied to angle iron, all complete as per direction of Engineer-in-charge, with reinforced barbed tape(R.B.T.) / Spring core (2.5mm thick) wire of high tensile strength of 165 kg/ sq.mm with tape (0.52 mm thick) and weight 43.478 gm/ metre (cost of M.S. angle, C.C. blocks shall be paid separately)(DSR16.53 Please Enable Macros to View BoQ information Special Condition :- |
| 14 | Tenderers are required to quote their offer as “above / at par / below” in the estimated cost. |
| 15 | The rates are to be filled up in figures and words both. |
| 16 | Departmental rates are exclusive of GST.GST will be borne by department as per applicable rules. Labour Cess, Royalty and all other Taxes are liable to be paid by Firm/Contractor. |
| 17 | In case of any discrepancy between the language of the items of bill of quantity and that of PWD the later shall prevail. |
| 18 | Tenders are advised to visit the site of work and make themselves acquainted with the site conditions. No claim whatsoever shall be entertained after submission of tender. |
| 19 | Quantities are approximate and may vary up to any extent on either side as per requirement of the site conditions in the direction of Engineer-In-charge or may not be executed at all for which no extra claim shall be entertained. |
| 20 | All above works shall be executed as per U.P.P.W.D/ U.P.P.T.C.L. specification or as directed by Engineer-In-charge. |
| 21 | The work may be carried in energized s/s area having high voltage installation contractor must employee trained supervisor & labour to work in such electrical/ hazardous area. All risk to men & materials shall be contractor's resposibilitiy |
| 22 | All risk to men, labour & materials shall be contractor’s responsibility. |
| 23 | All materials shall be arranged by the contractor’s at his own cost. |
| 24 | No handling charges of T&P and labour will be paid for extended period of contract, if any. |
| 25 | Rates quoted by Tenderer will remain firm till completion of scope of work of contract. |
| 26 | Contractor shall register his labour engaged in construction work in the office of Dy. Labour Commissioner ¼Hkou ,oa vU; lfUuekZ.k deZdkj ¼fu;kstu rFkk lsok ‘krZ fofu;eu½ v/khfu;e 1996. |
| 27 | Testing of material if any, required expenditure shall be borne by the contractor. Nothing shall be paid extra by the department. |
| 28 | Contractor has to made available 12 No cube at site and will frequently fill the cube at site. Accordingly cube test report will be submitted by contractor at his own cost. Final bill of work will be paid to contractor only after he will submit all satisfactory test result from authorized lab. |
| 29 | The contractor should have all related T&P like as concrete mixture, Needle & Surface vibratory, Slump test equipment & survey equipment etc. |
| 30 | Contractor has to put up all relevant drawing to SE (Civil) Prayagraj for approval at his own cost; nothing shall be paid extra for it. |
| 31 | As per G.O No. 622/23-12-2012-2. Audit/08 TC dt. 08 June 2012, Contractor has to deposit extra Security/ Performance guarantee, if the tendered rates are found below to the department rates. |
| 32 | As per section 171 of CGST Act, 2017 Any reduction in rate of tax on any supply of goods or service or the benefit of input tax credit shall be passed on the recipient by way of commensurate reduction in prices. Hence supplier/manufacturer to ensure to pass the benefit of reduced prices to UPPTCL, Further price quoted by supplier/Manufacturer is subject to scrutiny under above section” |
| 33 | Security of work will be released after six month from the date of completion of the work if no defect has been found after six month. |
| 34 | All the civil work carried out in potable water on contractor own cost. No Payment will made by department. However in case of departmental water supply 1.5% deduction will be made from contractor’s bill for water charges for the item which involve water consumption. |
| 35 | The bill Processing / Payment will be done according to existing UPPTCL Rule of ERP Portal. |
| 36 | If Tender has been cancelled after inviting due to any reason between tender call to final process, the tender cost will not refund to contractor, only EMD Will be refunded to Firm. |
| 37 | The 60% amount of brick available from dismantaling shall be recovered @ Rs. 3744.00/thousand + GST to Firm/Contractor. |
| 38 | The 30% amount of brick available from dismantaling shall be recovered as brick bats @ Rs. 1680.00/Cum + GST to Firm/Contractor. |
| 39 | The amount of Steel available from dismantaling will be recovered @ Rs. 20.00/KG + GST to Firm/Contractor. |
| 40 | Replaced CP Bib cock/piller cock/brass bib cock shall be recovered @ Rs. 25.00/each + GST to Firm/Contractor. |
| 41 | Old door and windows, shutter with chaukhat shall be recovered @ Rs. 70.00/Sqm. + GST to Firm/Contractor. SIGNATURE OF TENDERER / AUTHORISED PERSON ALONGWITH SEAL OF THE FIRM Name ……………………………..………..... Full Postal Address:………………………. ………………………………………………….. Phone No……………….. Mob. No………… |