| 1 | Demolition below G.L. upto 1.50 meters depth and disposal of unserviceable material within 20 mtrs lead unreinforced cement concrete more than 15cm thickness complete in all respect. |
| 2 | Disposal of material excavated unserviceable material from site of work to dumping site at Nallah (5 Kms) |
| 3 | Providing and laying cement concrete 1:4:8(1cement:4sand:8 graded stone aggregate 40mm nominal size and curing complete excluding the cost of form work in foundation and plinth in all leads and lifts. |
| 4 | Brick work using common burnt clay building bricks in foundation and plinth in cement mortar 1:4(1cement:4sand)(2nd class) in all leads and lifts. |
| 5 | Providing and laying cement concrete 1:2:4(1cement:2sand:4 graded stone aggregate 20mm nominal size)and curing complete excluding the cost of form work in foundation and plinth within all leads and lifts. |
| 6 | Providing form work with steel plated 3.15mm thick welded with angle iron in frame 30x30x5mm, so as to give a fair finish including centring,shuttering,strutting and propping etc. with wooden battens and ballies height of propping and centering below supporting floor to ceiling not exceeding 4 meters and removal of the same for insitu-reinforced concrete and plain concrete. within all leads and lifts. |
| 7 | Flat surfaces such as soffits of suspended floors, roofs, landings and the like floors etc 200mm. |
| 8 | edge of slab and breaking in floor and walls upto 20 cm wide |
| 9 | Vertical surfaces such as walls(any thickness) partitions and the like including attached pilasters, buttresses, plinth and string courses and the like complete in all respect as per direction and to the entire satisfaction of the Engineer-in-charge. |
| 10 | Providing, Laying Tor steel reinforcement for RCC. Work including bending binding and placing in position complete upto floor two level as per disection and entire satisfaction of Engineer in charge.(Labour Rate) |
| 11 | Providing and laying cement concrete 1:2:4(1cement:2sand:4 graded stone aggregate 20mm nominal size)and curing complete excluding the cost of form work and reinforcement for reinforced concrete work within all leads and lifts in:- |
| 12 | Suspended floors, roofs, landings and shelves and their supports, balconies, beams, girders, bressumers and cantilevers upto all floor level as per direction and to the entire satisfaction of the Engineer-in-charge. |
| 13 | In walls |
| 14 | 15mm cement plaster in single coat on rough sides of bricks/concrete stone walls etc for interior plastering upto floor two level including arrises internal rounded angles chamfer and rounded angles not exceeding 80mm in girth and finished even and smooth in cement mortar 1:3 (1cement:3sand) in all leads and lifts. |
| 15 | Applying cement slurry on RCC slab or cement concrete work using 2.75 Kg. of cement per square meters of floor area before laying cement concrete flooring including roughening, cleaning of the concrete surfaces complete within all leads and lifts as per direction and to the entire satisfaction of Engineer in Charge. |
| 16 | Providing and fixing SFRC Man hole for frame of internal size with frame of 500mm internal dia . The weight of cover & frame should not be less than 58 kg. complete within all leads and lifts. |
| 17 | (Extra heavy duty duty) |
| 18 | Medium duty |
| 19 | Providing 200mm wide PVC insulated MS rungs with chequarred or ribbed non slip surface including fixing in manholes with 200mmx200mmx100mm cement concrete 1:3:6(1cement:3sand:6graded stone aggregate 20mm nominal size within all leads and lifts as per direction and to the entire satisfaction of Engineer-in-charge. |
| 20 | Tracing of manhole , breaking RCC cover and renoving malwa from manhole chamber and stacking within 20m from the edge as per direction of Engineer in charge |
| 21 | Providing sewerage house connection complete within all leads and lifts as per direction and to the entire satisfaction of Engineer-in-charge. Please Enable Macros to View BoQ information |