| 1 | SUB WORK NO.1: RAW WATER PUMPING MACHINERY AT WADGAON HEADWORKS |
| 2 | ITEM NO.1:- Shift Engineer / Supervisor. Providing Assistant or Shift Engineer Or Supervisier to round the clock to Elecric Superviser Liciences At WTP & HW |
| 3 | ITEM NO.2:- Electrician at 33 KV supply at other Panel : Providing Electrician to round the clock 24 Hours. |
| 4 | ITEM NO.3:- Pump Operator :Providing Opertion and Maintainces Experienced Staff Pump Operator 500 HP Pump and 33 KV supply for day to day Maintainces and operations on scheme with Keeping all related accrusd / regarding collections record of day to day including such staff used as per detailed specification and directed by Engineer-in-charge.- 3 Nos. |
| 5 | ITEM NO.4:- Pump Operator Helper : Providing Opertion and Maintainces Experienced Staff Pump Operator Helper for day to day Maintainces and operations on scheme with Keeping all related accrusd / regarding collections record of day to day including such staff used as per detailed specification and directed by Engineer-in-charge.- 3 Nos. |
| 6 | PURE WATER PUMPING MACHINERY AT WTP SHANKARPUR |
| 7 | ITEM NO.1:- Chemist cum Inharge. Providing Chemist at Water Treatment Plant Shankarpur ,Round clock work at Treatment Plant site to checking water ,Maintain dose and ,Maintain records etc as per directed site Incharge and MJP rules and regulation Chemist At WTP |
| 8 | ITEM NO.3:- Pump Operator.Providing Opertion and Maintainces Experienced Staff Pump Operator 170 HP Pump and 11 KV supply for day to day Maintainces and operations on scheme with Keeping all related accrusd / regarding collections record of day to day including such staff used as per detailed specification and directed by Engineer-in-charge.- 3 Nos |
| 9 | ITEM NO.4:- Pump Operator Helper : Providing Opertion and Maintainces Experienced Staff Pump Operator Helper for day to day Maintainces and operations on scheme with Keeping all related accrusd / regarding collections record of day to day including such staff used as per detailed specification and directed by Engineer-in-charge.- 6 Nos |
| 10 | Water Sample Analysis (A) Bacteriological Analysis water sample from Governement Laborities |
| 11 | (B)Chemical Analysis examination of water sample from Governement Laborities |
| 12 | SUB WORK NO.2: Providing Skilled -Unskilled Manpower for Proper Operation and Maintenance of the Scheme |
| 13 | ITEM NO.1:- Providing Experienced staff such as Pump Operator, filter Operator , Valve Man, Mazdoor for day to day maintence and operation of scheme with keeping all related records/ registers , collection of day to day water samples including all taxes ,duties etc complete.WTP1. Filter Operator. 4 No |
| 14 | 2. Chemist. 1 No. |
| 15 | 3. Valveman Required as Zone 1 & Zone-2 ( Valveman will have the duties to operate the valves , find out the leakages, illegal connection , loss of water in his dedicated area.)1) Besa - 2 No's 2) Beltarodi - 2 No's 3) Ghogli - 1 No. 4) Pipla - 2 No's 5) Shankarpur - 1 No. 6) Hudkeshwar - 1 No. 7) Kapsi - 2 No.8) Gonhisim - 2 No's 9) Kharbi - 2 No's 10) Bahadura - 2 No. 11).Bidgaon -1 No's 12) Tarodi (Kh) -1 No. |
| 16 | 4. Lineman.( Lineman is dedicated for everyday monitoring of Raw Water Gravity main /Raw water Rising main with its Air valve -Sluice valve. Proper functioning.Also prepare reports and same to be taken in notice of Engineer in charge.) ( HW Rama Dam to WTP Shankarpur) |
| 17 | Item No. 2 :- Providing, engaging and employing necessary skilled and unskilled labour for day-to-day operation, maintenance, and management of the entire water supply system, including regular operation of pumps at head works, complete operation of Water Treatment Plant (WTP) and pump house, and ensuring uninterrupted water supply up to consumer water meter points, as per standard specifications and instructions of Engineer-in-charge. The scope includes all required manpower for shifts, routine maintenance, cleaning, and upkeep of WTP and pumping machinery. The item excludes cost of chemicals and electricity charges. Work shall be carried out as per approved procedures to ensure treated water is delivered in compliance with quality norms. All works shall be executed in complete manner as directed by Engineer-in-charge |
| 18 | a) Zone I Civil Supervisor- One Calender year = 365 Days. = 730 Daysb) Zone II Civil Civil Supervisor - One Calender year = 365 Days. = 730 Days |
| 19 | Security Guardc) Besa Center :- 1No. d) Bahadura Center :-1 No. |
| 20 | Sub Work No. 3 :- Rectification of Leakages on H.D.P.E. Pipe (For Besa, Beltarodi, Pipla, Ghogali, Shankarpur and Hudkeshwar - 6 Village) |
| 21 | Item No.1 : Rectification of leakages on HDPE pipe line with butt fusion joint / coupler joint / flange joint including excavation , dewatreing , cutting of pipes , rejointing of pipes , testing of joints and refilling etc. complete. |
| 22 | In Other Roadsi) Electrofusion Coupler jointi) 90 mm Dia |
| 23 | ii) 110 mm Dia |
| 24 | iii) 125 mm Dia |
| 25 | iv) 140 mm Dia |
| 26 | v) 160 mm Dia |
| 27 | vi) 180 mm Dia |
| 28 | vii) 200 mm Dia |
| 29 | viii) 250 mm Dia |
| 30 | Item No.2 : Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler / specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GST levied by GI & GOM in all respect etc. complete. |
| 31 | a) 6 Kg/Sq. cm PE-100i) 90 mm Dia |
| 32 | 2) 110 mm Dia. |
| 33 | 3) 125 mm Dia. |
| 34 | 4) 140 mm Dia. |
| 35 | 5) 160 mm Dia. |
| 36 | 6) 180 mm Dia. |
| 37 | 7) 200 mm Dia. |
| 38 | 8) 250 mm Dia. |
| 39 | Item No.3 : Providing & Supply of Electro Fusion Fittings in accordance with BS EN12201: Part-3 suitable for drinking water with in black/ blue colour manufactured from compounded PE80/ PE100 virgin polymer and compatible with PE80/PE100 pipes, in pressure rating SDR11 with min PN12.5 rated for water application and shall be inclusive of all cost such as testing, inspection charges, transportation up to store, transit insurance, loading, unloading, stacking excluding GST levied by GOI & GOM in all respect, etc. complete. |
| 40 | CouplersCouplers 90 |
| 41 | Coupler 110 |
| 42 | Coupler 125 |
| 43 | Coupler 140 |
| 44 | Coupler 160 |
| 45 | Coupler 180 |
| 46 | Coupler 200 |
| 47 | Coupler 250 |
| 48 | TeeEqual Tee 90 |
| 49 | Equal Tee 110 |
| 50 | Equal Tee 125 |
| 51 | Equal Tee 160 |
| 52 | Equal Tee 180 |
| 53 | Equal Tee 200 |
| 54 | Equal Tee 250 |
| 55 | End CapEnd Cap 90 |
| 56 | Elbow 90090 mm dia |
| 57 | 110 mm dia |
| 58 | 125 mm dia |
| 59 | 160 mm dia |
| 60 | 180 mm dia |
| 61 | 200 mm dia |
| 62 | 250 mm dia |
| 63 | Reducer110 x 90 mm |
| 64 | 125 x 90 mm |
| 65 | 160 x 90 mm |
| 66 | 160 x 110 mm |
| 67 | 200 x 90 mm |
| 68 | 200 x 110 mm |
| 69 | 200 x 160 mm |
| 70 | Item No.4 : Providing and casting in situ / ready mix PCC M-20 Grade of trap metal for coping to head walls / parapet including centering, form work, compaction and curing etc. complete (With reversible drum type mixer / concrete batch mix plant (pan mixer) with SCADA with fine agreegates of required specifications (VSI sand finely washed etc |
| 71 | Item No.5 : Providing and fixing in position steel bar reinforcement of various diameters for RCC piles, caps, footings, foundations, slabs, beams, columns, canopies, staircases, newels, chajjas, lintels, pardies, copings, fins, arches, etc. as per detailed designs, drawings and schedules; including cutting, bending, hooking the bars, binding with wires or tack welding and supporting as required, etc. complete.(including cost of binding wire). (Bd-F-17/306)= 1% concrete qty. |
| 72 | Item No.6 : Rent for concrete breakar and compresser. |
| 73 | Pipeline provision for Extension of pipe for long connection and Chocking of pipe.Item No. 7 : Excavation for foundation / pipe trenches in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding back filling, etc. complete. |
| 74 | Lift 0 to 1.5 M .For 90 mm dia HDPE 6 kg per sqcm |
| 75 | For 110 mm dia HDPE 6 kg per sqcm |
| 76 | Item No.8 : Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GST levied by GI & GOM in all respect etc. complete. |
| 77 | For 90 mm dia HDPE 6 kg per sqcm |
| 78 | For 110 mm dia HDPE 6 kg per sqcm |
| 79 | Item No.9 : Lowering, Laying and Jointing H. D. P. E./M. D. P. E. pipes in proper position including all specials by compression fitting/electrofusion and butt fusion jointing procedure as per relevent IS Code complete with all materials for jointing procedure like Electrofusion machine, Electric heater/butt fusion welding machine with hydraulic jack, top loading clamp etc. and all labours as directed by engineer in charge as per IS-7634 Part II |
| 80 | For 90 mm dia HDPE 6 kg per sqcm |
| 81 | For 110 mm dia HDPE 6 kg per sqcm |
| 82 | Item No. 10 : Providing & Supply of Electro Fusion Fittings in accordance with BS EN12201: Part-3 suitable for drinking water with in black/ blue colour manufactured from compounded PE80/ PE100 virgin polymer and compatible with PE80/PE100 pipes, in pressure rating SDR11 with min PN12.5 rated for water application and shall be inclusive of all cost such as testing, inspection charges, transportation up to store, transit insurance, loading, unloading, stacking excluding GST levied by GOI & GOM in all respect, etc. complete. |
| 83 | Item No. 11 : Refilling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation, surcharging, etc. complete. |
| 84 | Sub Work No. 4 :- Rectification of Leakages on H.D.P.E. Pipe Distribution System (Gonhi sim, Bahadura, Kharbi, Kapsi,Bidgaon ,Tarodi - 6 Villages) |
| 85 | Item No.1 : Rectification of leakages on HDPE pipe line with butt fusion joint / coupler joint / flange joint including excavation , dewatreing , cutting of pipes , rejointing of pipes , testing of joints and refilling etc. complete. |
| 86 | In Other Roadsi) 90 mm Dia |
| 87 | ii) 110 mm Dia |
| 88 | iii) 125 mm Dia |
| 89 | iv) 140 mm Dia |
| 90 | v) 160 mm Dia |
| 91 | vi) 180 mm Dia |
| 92 | vii) 200 mm Dia |
| 93 | viii) 250 mm Dia |
| 94 | Item No.2 : Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler / specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GST levied by GI & GOM in all respect etc. complete. |
| 95 | a) 6 Kg/Sq. cm PE-100i) 90 mm Dia |
| 96 | 2) 110 mm Dia. |
| 97 | 3) 125 mm Dia. |
| 98 | 4) 140 mm Dia. |
| 99 | 5) 160 mm Dia. |
| 100 | 6) 180 mm Dia. |
| 101 | 7) 200 mm Dia. |
| 102 | 8) 250 mm Dia |
| 103 | Item No.3 : Providing & Supply of Electro Fusion Fittings in accordance with BS EN12201: Part-3 suitable for drinking water with in black/ blue colour manufactured from compounded PE80/ PE100 virgin polymer and compatible with PE80/PE100 pipes, in pressure rating SDR11 with min PN12.5 rated for water application and shall be inclusive of all cost such as testing, inspection charges, transportation up to store, transit insurance, loading, unloading, stacking excluding GST levied by GOI & GOM in all respect, etc. complete. |
| 104 | CouplersCouplers 90 |
| 105 | Coupler 110 |
| 106 | Coupler 125 |
| 107 | Coupler 140 |
| 108 | Coupler 160 |
| 109 | Coupler 180 |
| 110 | Coupler 200 |
| 111 | Coupler 250 |
| 112 | TeeEqual Tee 90 |
| 113 | Equal Tee 110 |
| 114 | Equal Tee 125 |
| 115 | Equal Tee 160 |
| 116 | Equal Tee 180 |
| 117 | Equal Tee 200 |
| 118 | Equal Tee 250 |
| 119 | End CapEnd Cap 90 |
| 120 | Elbow 90090 mm dia |
| 121 | 110 mm dia |
| 122 | 125 mm dia |
| 123 | 160 mm dia |
| 124 | 180 mm dia |
| 125 | 200 mm dia |
| 126 | 250 mm dia |
| 127 | Reducer110 x 90 mm |
| 128 | 125 x 90 mm |
| 129 | 160 x 90 mm |
| 130 | 160 x 110 mm |
| 131 | 200 x 90 mm |
| 132 | 200 x 110 mm |
| 133 | 200 x 160 mm |
| 134 | Pipeline provision for Extension of pipe for long connection and Chocking of pipe.Item No. 4 : Excavation for foundation / pipe trenches in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding back filling, etc. complete. |
| 135 | Lift 0 to 1.5 M .For 90 mm dia HDPE 6 kg per sqcm |
| 136 | For 110 mm dia HDPE 6 kg per sqcm |
| 137 | Item No. 5 : Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GST levied by GI & GOM in all respect etc. complete. |
| 138 | For 90 mm dia HDPE 6 kg per sqcm |
| 139 | For 110 mm dia HDPE 6 kg per sqcm |
| 140 | Item No. 6 : Lowering, Laying and Jointing H. D. P. E./M. D. P. E. pipes in proper position including all specials by compression fitting/electrofusion and butt fusion jointing procedure as per relevent IS Code complete with all materials for jointing procedure like Electrofusion machine, Electric heater/butt fusion welding machine with hydraulic jack, top loading clamp etc. and all labours as directed by engineer in charge as per IS-7634 Part II |
| 141 | For 90 mm dia HDPE 6 kg per sqcm |
| 142 | For 110 mm dia HDPE 6 kg per sqcm |
| 143 | Item No. 7 : Providing & Supply of Electro Fusion Fittings in accordance with BS EN12201: Part-3 suitable for drinking water with in black/ blue colour manufactured from compounded PE80/ PE100 virgin polymer and compatible with PE80/PE100 pipes, in pressure rating SDR11 with min PN12.5 rated for water application and shall be inclusive of all cost such as testing, inspection charges, transportation up to store, transit insurance, loading, unloading, stacking excluding GST levied by GOI & GOM in all respect, etc. complete. |
| 144 | Item No. 8 : Refilling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation, surcharging, etc. complete. |
| 145 | Item No. 9 : Providing and casting in situ / ready mix PCC M-150 Grade of trap metal for coping to head walls / parapet including centering, form work, compaction and curing etc. complete (With reversible drum type mixer / concrete batch mix plant (pan mixer) with SCADA with fine agreegates of required specifications (VSI sand finely washed etc |
| 146 | Item No. 10 : Providing and fixing in position steel bar reinforcement of various diameters for RCC piles, caps, footings, foundations, slabs, beams, columns, canopies, staircases, newels, chajjas, lintels, pardies, copings, fins, arches, etc. as per detailed designs, drawings and schedules; including cutting, bending, hooking the bars, binding with wires or tack welding and supporting as required, etc. complete.(including cost of binding wire). (Bd-F-17/306)= 1% concrete qty. |
| 147 | Item No. 11 : Rent for concrete breakar and compresser. |
| 148 | Item No. 12 : Providing double flange sluice valve confirming for IS- 14846 including worn gear arrangements as per test pressure, stainless steel spindle, caps, including inspection charges, transportation upto departmental store, unloading, stacking excluding GST levied by GOI & GOM in all respect etc.complete.Sluice valves - PN - 1 (Without by pass)100 mm Dia Sluice Valve |
| 149 | Item No. 13 : Lowering, laying and jointing in position following C.I.D/F Reflex valves, Butterfly valves and Sluice valves including cost of all labour jointing material, including nut bolts and giving satisfactory hydraulic testing etc. complete. (Rate for all class of valves.) |
| 150 | Sub Work No. 5 :- Rectification of Leakages on Various Type of D.I. Pipeline |
| 151 | Item No.1 : Rectification of leakages on following dia & type of pipe line including cost of all labour, excavation, dewatering, repairing of pipe, refilling, including hire charges of all kind of machinery required such as JCB, Gas Cutter, Welding Machine with generator set, dewatering set, Electrofusion set, Carting charges of machinery at site of work, etc. completed as per direction of engineer in charge. |
| 152 | a) For 600 mm dia D.I.Pipeline |
| 153 | b) 500 mm dia D.I. Pipeline |
| 154 | c) 400 mm dia D.I. Pipeline |
| 155 | d) 250 mm dia D.I. Pipeline |
| 156 | e) 200 mm dia D.I. Pipeline |
| 157 | f) 150 mm dia D.I. Pipeline |
| 158 | g) 100 mm dia D.I. Pipeline |
| 159 | Item No.2 : Providing D.I. pipes (push on joints pressure pipes of D. I. of following class and diameters confirming to the I. S. specification inclusive cost of jointing materials (Rubber gasket of EPDM Quality ) excluding GST levied by GOI & GOM in all respect including Third party inspection charges of TPI Agency approved by MJP including Transit insurance, Railway Freight, Unloading from railway wagon, Loading into Truck, Transportation to departmental store, unloading, stacking etc. completed as directed by Engineer in charges (IS 8329/2000 for pipes and IS 158/1969 and IS 12820/1989 or latest edition/ revision with amendments for Rubber Gaskets. |
| 160 | a) For 600 mm dia D.I. Pipe D.I. K-7 Pipe |
| 161 | b) 500 mm dia D.I. Pipe D.I. K-9 Pipe |
| 162 | c) 400 mm dia D.I. Pipe D.I. K-7 Pipe |
| 163 | d) 250 mm dia D.I. Pipe D.I. K-7 Pipe |
| 164 | e) 200 mm dia D.I. Pipe D.I. K-7 Pipe |
| 165 | f) 150 mm dia D.I. Pipe D.I. K-7 Pipe |
| 166 | g) 100 mm dia D.I. Pipe D.I. K-7 Pipe |
| 167 | Item No.3 : Providing and supplying D.I. fittings with ISI mark Mechanical joint confirming to tables 12 to table 31 of IS 9523/2000 upto latest amendments including cost of SBR/ EDPM gaskets, Nuts, Bolts, Washers and Ductile iron follower glands. Fittings should be with internally Ordinary portland cement mortor lined and externally metallic zinc coating/zinc rich paint with finishing layer of black bitumen coating including transportation upto store excluding GST levied by GOI & GOM in all respect etc. complete.MJ Collar/ Coupling |
| 168 | a) 600 mm dia D.I. |
| 169 | b) 500 mm dia D.I. |
| 170 | c) 400 mm dia D.I. |
| 171 | d) 250 mm dia D.I. |
| 172 | e) 200 mm dia D.I. |
| 173 | f) 150 mm dia D.I. |
| 174 | g) 100 mm dia D.I. |
| 175 | Item No.4 : Providing and supplying at site of ductile iron / spheroidal graphite (S.G.) iron D/F non-rising spindle resil-ient seated glandless sluice valves with handwheel &without bypass arrangement. Valves in accordance with BS 5163 of PN-10/ 16 rated, with body and bonnet of ductile iron confirming to IS 1865 Gr. 500/7 or Gr.400/15. Wedge fully encapsulated WRAS approved EPDM rubber (approved for drinking water), Wedge nut of brass,shaft of stainless steel 1.4021/1.4104, stem seals min. 3 nos. of NBR, internal fasteners of stainless steel A2. Body& Bonnet coated inside & outside with electrostatically applied epoxy powder coated blue colour (suitable for drinking water) as per DIN 30677-2 & GSK guidelines with a coating thickness of min. 250 microns. Valves should be full bore & tight shut-off. Flange drilling as per IS 1538 raised face & pressure testing at manufactures works shall be done as per IS 14846. including transportation charges excluding GST levied by GOI & GOM in all respect etc. complete. |
| 176 | 100 mm dia PN10 Sluice Valve |
| 177 | 150 mm dia PN10 Sluice Valve |
| 178 | 200 mm dia PN10 Sluice Valve |
| 179 | 250 mm dia PN10 Sluice Valve |
| 180 | Item No.5 :Lowering, laying and jointing in position following DI/CI DF Sluice valves including removing existing Valven cost of all labour jointing material, including nut bolts and giving satisfactory hydraulic testing etc. complete. |
| 181 | 100 mm dia PN10 Sluice Valve |
| 182 | 150 mm dia PN10 Sluice Valve |
| 183 | 200 mm dia PN10 Sluice Valve |
| 184 | 250 mm dia PN10 Sluice Valve |
| 185 | Item No.6 : Providing and laying in situ Cement Concrete of trap/ granite / quartzite / gneiss metal for RCC work in foundation like raft, grillage, strip foundation and footing of RCC columns and steel stanchions including normal dewatering, form work, compaction, finishing and curing, etc. complete. (By weigh batching and mix design for M250 and M-300 only. Use of L&T, A.C.C., Ambuja, Birla Gold, Manikgad, Rajashree, etc. cement is permitted.) (Excluding M.S. or Tor reinforcement) |
| 186 | Item No. 7 : Providing and fixing in position steel bar reinforcement of various diameters for RCC piles, caps, footings, foundations, slabs, beams, columns, canopies, staircases, newels, chajjas, lintels, pardies, copings, fins, arches, etc. as per detailed designs, drawings and schedules; including cutting, bending, hooking the bars, binding with wires or tack welding and supporting as required, etc. complete (including cost of binding wire). (Bd-F-17/306) |
| 187 | Item No. 8 : Rent for concrete breakar and compresser. |
| 188 | SUB WORK NO.6: CLEANING OF ESR |
| 189 | Item No.1 : Comprehensive Cleaning and Disinfection of Elevated Water Storage Reservoir (ESR), GSR, Sump, CLF etc using mechanized methods, approved disinfectants, and scaffolding – complete in all respectsProviding and carrying out thorough cleaning and disinfection of ESR, GSR, Sump, CLF etc within a given period, by deploying skilled labour, necessary safety gear, tools, and temporary scaffolding arrangements for safe access to internal surfaces. The work includes a combination of mechanized and manual cleaning techniques along with the use of certified disinfectants, executed in the following steps: |
| 190 | 1. Erection of Temporary Scaffolding: Providing and erecting strong, stable, and safe scaffolding structures (steel/pipe or bamboo as per site conditions) inside the ESR to enable proper access for cleaning of walls, ceiling, and other elevated surfaces.2. Mechanical Dewatering: Draining of stored water completely using suitable mechanical pumping systems.3. Desilting and Sludge Removal: Removal of settled dirt, debris, and sludge using sludge pumps and manual cleaning tools as needed.4. High-Pressure Jet Cleaning: Cleaning of internal walls, floor, and ceiling with high-pressure water jets (100–150 bar) to eliminate surface deposits, biofilms, and contaminants.5. Vacuum Cleaning: Suction and removal of remaining sludge and water using industrial vacuum cleaner to ensure a dry and clean tank floor. |
| 191 | 6. Manual Scrubbing and Wiping: Final thorough cleaning using nylon brushes, coir strings, and dusters, along with bailing out of water and waste material.7. Chemical Disinfection: Application of bleaching powder at the rate of 14 gm/sq.m on all interior surfaces. Triple washing of surfaces to remove chemical residue.8. Advanced Disinfection: Spraying of eco-friendly, non-toxic, biodegradable disinfectant, certified by a government-approved laboratory, followed by UV radiation treatment to kill any remaining pathogens or suspended bacteria – as per UECD guidelines dated 17th December 2001.All works shall be carried out under strict supervision, ensuring proper safety standards, and as directed by the Engineer-in-Charge. The item includes cost of all materials, labour, tools, machinery, scaffolding, and disposal of waste – completed in all respects. |
| 192 | ESR to be cleaned every 4 months in a Year, i.e 3 time in a year |
| 193 | A) Gram Panchayat AreaShankarpur Gaothan |
| 194 | Shankarpur New ESR 2.50 LL |
| 195 | Hudkeshwar Khurd 0.55 LL |
| 196 | Kapsi Gharsansar 2.30 LL |
| 197 | Kapsi Jinsi 1.41 LL |
| 198 | B) Municipal Council Area (4% MC area added)ZONE-1Belatarodi ESR 4.46 LL |
| 199 | Belatarodi ESR 4.51 LL |
| 200 | Besa 2.37 LL Bill Center |
| 201 | Besa 3.12 LL |
| 202 | Besa 2.90 LL Renuka colony |
| 203 | Besa 4.50 LL MD Hotel |
| 204 | Ghogali 2.5 LL Ramesh Estate |
| 205 | Ghogali Gaothan .45 LL |
| 206 | Pipla New ESR 3.5 LL Kamala Celebration |
| 207 | Pipla 1.29 LL Pyramid |
| 208 | Pipla Ashtha Nagar .55 LL |
| 209 | Pipla Gaothan 0.20LL |
| 210 | Bahadura 2.47 LL |
| 211 | Bahadura 2.50 LL |
| 212 | Gonhi Sim 3.63 LL |
| 213 | Gonhi Sim 2.95 LL |
| 214 | Gonhi Sim 4.25 LL |
| 215 | Kharabi 1.71 LL |
| 216 | Kharabi 4.92 LL |
| 217 | Kharabi 4.84 LL |
| 218 | Kharabi 7.97 LL |
| 219 | Kharabi 1.25 LL |
| 220 | Kharabi 3.63 LL |
| 221 | Bidgaon 2.75 LL |
| 222 | Bidgaon 2.75 LL |
| 223 | Tarodi 1.34 LL |
| 224 | Tarodi 1.34 LL |
| 225 | Pure Water Sump. |
| 226 | CLF 1 |
| 227 | CLF 2 |
| 228 | SUB WORK NO.7: Maintenance to Raw water/PureWater Transmission Main |
| 229 | Item No.1 : Providing and supplying at site of ductile iron / spheroidal graphite (S.G.) iron D/F non-rising spindle resil-ient seated glandless sluice valves with handwheel &without bypass arrangement. Valves in accordance with BS 5163 of PN-10/ 16 rated, with body and bonnet of ductile iron confirming to IS 1865 Gr. 500/7 or Gr.400/15. Wedge fully encapsulated WRAS approved EPDM rubber (approved for drinking water), Wedge nut of brass,shaft of stainless steel 1.4021/1.4104, stem seals min. 3 nos. of NBR, internal fasteners of stainless steel A2. Body& Bonnet coated inside & outside with electrostatically applied epoxy powder coated blue colour (suitable for drinking water) as per DIN 30677-2 & GSK guidelines with a coating thickness of min. 250 microns. Valves should be full bore & tight shut-off. Flange drilling as per IS 1538 raised face & pressure testing at manufactures works shall be done as per IS 14846. including transportation charges excluding GST levied by GOI & GOM in all respect etc. complete. |
| 230 | 150 mm dia PN16 Sluice Valve |
| 231 | Item No.2 : Providing and supplying at site ductile iron / Spheroidal Graphite (S.G.) iron single chamber tamper proof air valve without isolating sluice valve. Valves in accordance with BSEN 1074-4 of PN 10/16 rated, with body and bonnet of ductile iron confirming to EN 1563/IS 1865 Gr. 500/7 or Gr.400/15 floats, float guide, seat ring of stainless steel 1.4436/1.4306, seat ring gasket of WRAS approved EPDM rubber (suitable for drinking water), internal fasteners of stainless steel A2. Body & Bonnet coated inside & outside with electrostatically applied epoxy powder coated blue colour (suitable for drinking water) as per DIN 30677-2 & GSK guidelines with a coating thickness of min. 250 microns. Flange connections as per IS 1538 raised face & pressure testing at manufactures works shall be done as per IS 14845. including transportation charges excluding GST levied by GOI & GOM in all respect etc. complete. |
| 232 | 150 mm dia PN16 Air Valve |
| 233 | Item No.3 : Lowering, laying and jointing in position following DI/CI DF Sluice valves including removing existing Valven cost of all labour jointing material, including nut bolts and giving satisfactory hydraulic testing etc. complete. complete. |
| 234 | 300 mm Dia Sluice Valve PN 1.6 (Replacing existing) |
| 235 | 150 mm dia Sluice Valve PN 16 |
| 236 | Item No.4 : Providing and supplying I.S.I. mark rubber gasket suitable for C.I. or D. I. pipe of all class for tyton joints including inspection charges, transportation upto departmental stores excluding GST levied by GOI & GOM in all respect etc. complete. |
| 237 | Flat Flanged Gaskets moulded out of SBR (For Flanged Joints)For Repalcement of rubber gasket 150 mm dia |
| 238 | 300 mm dia for Scour Valve Flange |
| 239 | Item No.5 : Hire charges of JCB for excavation for pipeline trenches, Dewatering, refilling, carting etc. including fuel, driver ……….etc. complete. or as directed by Engineer in ChargeRent / Hire Charges for JCB |
| 240 | Item No.6 : Hire charges of Jeep for 50 Km & above including fuel, driver for petroling on pipeline….etc. complete. or as directed by Engineer in Charge. Exclusively RWRM and RWGM only. Hire Charges for petroling of Raw water R/M and G/M. |
| 241 | Item No.7 : Hire charges of concrete breaker & Compressor….etc. complete. Hire Charges for Concrete breaker & compressor |
| 242 | Item No.8 : Providing pipe cutter with operator including welding MS flage …etc completePipe cutter with operator |
| 243 | Item No.9 : Repairing of existing Sluice valves, Scour Valves including all labour work, necessary transportation, replacing galnd and hydraulic testing and excluding GST levied by GOI & GOM in all respect etc. complete or as directed by enigineer-in-charge. |
| 244 | CIDF valve 150 mm |
| 245 | CIDF valve 200 mm |
| 246 | CIDF valve 250 mm |
| 247 | CIDF valve 300 mm |
| 248 | CIDF valve 350 mm |
| 249 | Item No.10 : Providing of rubber coated wooden type Ball for Air Valves including inspection charges, transportation upto departmental stores excluding GST levied by GOI & GOM in all respect etc. complete or as per direction of Engineer-in-charge.150 mm dia AV Ball for KAV |
| 250 | 200 mm dua AV Ball for KAV |
| 251 | Item No.11 : Manufacturing, Providing and fixing in postion MS gland caps for 150mm diameter Sluice Valves including all material, inspection charges, transportation upto departmental stores excluding GST levied by GOI & GOM in all respect etc. complete or as per direction of Engineer-in-charge.Gland Caps for 150 mm diameter Sl. Vl. |
| 252 | Item No.12 : Manufacturing, Providing and fixing in postion CI Cowl for 150mm diameter Kinectic Air Valves including all material, inspection charges, transportation upto departmental stores excluding GST levied by GOI & GOM in all respect etc. complete or as per direction of Engineer-in-charge.CI Cowl for 150mm dia KAV |
| 253 | Item No.13 : Checking and Replacing of damaged AV balls including opening the Air valve HP & LP paltes by cutting or opening the nut bolts, replacing the damaged Air valve Balls in both LP & HP chambers with new ball and fixing all spare parts of valve and hydraulic testing and excluding GST levied by GOI & GOM in all respect etc complete or as per directions of Engineer-in-charge.Replacing of damaged AV balls |
| 254 | Item No.14 : Replacing the damaged Air Valves including opening or cutting the nut bolts, removing damaged Air valves, fixing new Air valve including hydraulic testing and excluding GST levied by GOI & GOM in all respect etc complete or as per directions of Engineer-in-charge.Replacing of Air Valves 100 / 150 mm dia |
| 255 | Item No.15 : Providing and supplying ISI standard MS specials of required thickness with 3 coats of approved make epoxy paint (Shalimar, Ciba or Mahindra & Mahindra make) from inside and outside excluding GST levied by GOI & GOM in all respect, including inspection charges, transportation to stores / site, and stacking, etc. complete. |
| 256 | Item No.16 : Providing and installing mercury water level indicator for RCC ESR and wash water tank site as per instructions of Engneer-in-charge at ground level of the tank or nearing pump house or room for RCC ESR having 15 mtrs. staging height and 5 mtrs. water storage height with indication of water height in storage tank in metre and 1/10th of meter including providing and installing 15 mm dia class ‘B’ G.I. piping with necessary accessories from bottom of the tank upto the instrument as per instructions of Engineer-in-charge.At BPT |
| 257 | Item No.17 : Rectification of leakages on following diameters & type of pipeline including cost of all labour, excavation, dewatering, reairing of pipe, refilling, including hire charges of all kind of machinery required such as JCB, Gas Cutter, Welding Machine with generator set, dewatering set, Electrofushion set, Carting charges of mahinery at site of work..etc complete as per direction of engineer in charge.800 mm diameter DI pipeline |
| 258 | 700 mm diameter DI pipeline |
| 259 | Item No.18 : Providing D.I. pipes (push on joints pressure pipes of D. I. of following class and diameters confirming to the I. S. specification inclusive cost of jointing materials (Rubber gasket of EPDM Quality ) excluding GST levied by GOI & GOM in all respect including Third party inspection charges of TPI Agency approved by MJP including Transit insurance, Railway Freight, Unloading from railway wagon, Loading into Truck, Transportation to departmental store, unloading, stacking etc. completed as directed by Engineer in charges (IS 1536/2001 for pipes and IS 158/1969 and IS 12820/1989 or latest edition/ revision with amendments for Rubber Gaskets. |
| 260 | 700 mm dia. DI K-7 pipe |
| 261 | 800 mm dia. DI K-9 pipe |
| 262 | 800 mm dia. DI K-7 pipe |
| 263 | Item No.19 : Providing and supplying D.I. fittings with ISI mark Mechanical joint confirming to tables 12 to table 31 of IS 9523/2000 upto latest amendments including cost of SBR/ EDPM gaskets, Nuts, Bolts, Washers and Ductile iron follower glands. Fittings should be with internally Ordinary portland cement mortor lined and externally metallic zinc coating/zinc rich paint with finishing layer of black bitumen coating including transportation upto store excluding GST levied by GOI & GOM in all respect etc. complete.MJ Collar/ Coupling |
| 264 | 700 mm dia Collar |
| 265 | 800 mm dia Collar Please Enable Macros to View BoQ information |