| 1 | E/W in excavation in foundation in B.C. soil lead up to 30m And lift up to 1.5m including all complete. (chapter no. 4 as S.I. No. 257) |
| 2 | Boring of pile hole 300 mm diameter ,3.50 m deep single under reamed of 50 cm diameter I/c all as directed by engineer in charge. (chapter no. 4 new item 3) |
| 3 | R.C.C. work in 1:1½ :3 cement, coarse sand and 20mm gauge stone grit including all complete for Pile & Plinth beam etc. (chapter 5 no. as S.I. No. 284 |
| 4 | R.C.C. work in 1:2:4 cement, coarse sand and 20mm gauge stone grit including all complete but for T beam and slab roofs and R.C.C. columns.(chapter no. 5 as S.I. No. 284 |
| 5 | M.S. or iron work (Tor or plain bar) in plain work such as R.C.C. /R.B. work I/c all complete as directed by engineer in charge as chapter 10 as SI No. 504 |
| 6 | Local Sand filling in plinth i/c supply of necessary quantity of sand from a distance of not exceeding 8 km.from the site of work including watering, dressing etc. as chapter 4 SI No. 255 |
| 7 | Cement Concrete with 4cm gauge approved stone ballast, approved coarse sand and cement in proportion of 8:4:1 i/c supply of all material, Labour and T&P etc. required for proper completion of the work. as chapter 5 SI No. 281 |
| 8 | Class-150 brick work in 1:4 cement & fine sand mortar in foundation and plinth I/c all complete as chapter 6 as S.I. No. 305 |
| 9 | Plaster 12mm thick with cement, fine sand mortar in proportion of 1:6 in fair side of wall I/c all complete as directed by engineer in charge etc. (chapter 13 as SI no 17.58 (ii)) |
| 10 | Supply of stone boulder stone (25 to 50 Kg) Quartz @ sand stone l/c all cost of material labour t&P all taxes. |
| 11 | Dry Stone pitching hand places l/c carriage labour all taxes etc. complete all respect. |
| 12 | Supply to GEO sheet made of 200 gsm fgwoven fabric confirming to 15351 (2015) ic all cost material. Carriage loading, unloading, stacking all taxes etc. |
| 13 | laying of GEO sheet made 200 GSM woven fabric confirming to 15351 (2015) T&P labour all taxes complete in all respect. |
| 14 | Finishing walls with water proofing cement paint of approved make and quality on new work with two coat to give an even shade, including supply of all material, labour and T&P etc.required for proper completion of the work.(chapter 15 S.I. No. 660+661) |
| 15 | Laying of 80 mm thick cement concrete paver block (interlock bricks) with 40 mm thick stone dust including preaparation of base and joint filling all complete. C.h. No. 14 new item no. 3 |
| 16 | Providing and displating bamboo buddga vallyvariety wity umbrella shape having 120 to 135 ht. with fresh & healthy foliage well developed in 40 cm cement pot multy branch bushy as per direction of the officer in charge. |
| 17 | Washingtonia filifea palm stem ht. 120-135 cm. with 8-10 healty leaves lush green leaves well developed in big size HDPE bag (DSR 2020 sn. 7.90) |
| 18 | Foxtail palm ht. 240-270 cm botoome girth 35-40 cm well developed in big size HDPE bag (DSR 2020 sn. 7.44) |
| 19 | Ficus black (F vivion) (bushy) of height 150-165 cm with 8-10 branches and healthy foliage in earrthen pot of size 30cm (DSR 2020 sn. 8.23) |
| 20 | Providing and stacking of ficus religiosa (peepal) of height 150-165 cm in big polly bags of size 30 cm as per direction of the officer in charges (DSR 2020 sn. 7.36) |
| 21 | Garden Benches I/C all complete (GEM). |
| 22 | Supply and fixing of Add Sign board / Sila Patt & photography etc. (For Estimate Purpuse) |
| 23 | Less 5% As Competitive Charges |
| 24 | Less 1% Labour Cess Please Enable Macros to View BoQ information |