| 1 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Erection of 11KV Line on 9/11/13 mtr long ST Poles with ACSR Dog Conductor for providing Uninterrupted Power Supply to PHE Pumping Station Salmey |
| 2 | 9 mtr. Long ST Pole (ST-410 SP-33) |
| 3 | 11 mtr. Long ST Pole (ST-410 SP-56) |
| 4 | 13 mtr. Long ST Pole (ST-410 SP-69) |
| 5 | GI V Cross -arm with top Bracket including clamps |
| 6 | GI Channel X-arm including clamps and Angle for braces |
| 7 | 100mm² ACSR Dog Conductor |
| 8 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 9 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75KV Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 10 | Galvanized Nuts and Bolts |
| 11 | Danger Plates with Clamps |
| 12 | anticlimbing device with clamps |
| 13 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm |
| 14 | Painting of 9 mtr/11mtr/13mtr ST poles with two coats of Aluminium paint. |
| 15 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 16 | Cement bottoming 1:2:4 mix as per REC standard 0.5 cum per pole |
| 17 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning forErection of LT Line on 8 mtr long ST Poles with 50 sqmm AB LT Cable for providing Uninterrupted Power Supply to PHE Pumping Station Salmey |
| 18 | 8 mtr. Long ST Pole (ST-410 SP-15) |
| 19 | 50mm² AB (LT) Cable (3x50+1x16+1x35mm²) XLPE (1.1 KV, 3+1C,Al). |
| 20 | Straight through cable jointing kit |
| 21 | Suspension/Tension clamp with eye hook |
| 22 | Galvanized Nuts and Bolts |
| 23 | Danger Plates with Clamps |
| 24 | Anti climbing device with clamps |
| 25 | Earthing complete by GI Rod 20 mm, 2.5 mtr long through G.I. Strip 25X3 mm |
| 26 | Painting of 8 mtr ST poles with one coats of Red Oxide. |
| 27 | Painting of 8 mtr ST poles with two coats of Aluminium paint. |
| 28 | Cement bottoming 1:2:4 mix as per REC standard 0.5 cum per pole |
| 29 | Insulating Piercing connectors |
| 30 | PG Clamps |
| 31 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 32 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Installation of 100 KVA Sub Station for providing Uninterrupted Power Supply to PHE Pumping Station Salmey |
| 33 | Gapless surge Arrestor, 9 kv, 10 KA , LA with polymer housing stn. Type |
| 34 | 11 KV GO AB Switch 3 phase, 3 pole, 200 Amp, vertical |
| 35 | 11 KV Horn gap fuse set 3 phase 200 A |
| 36 | 120 mm² 1.1 KV Grade, PVC insulated stranded conductor FRLS Type |
| 37 | 9 mtr. Long ST pole (ST-410 SP-33) |
| 38 | PGclamps |
| 39 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 40 | GI Channel /Angle/flat of sizes including clamps |
| 41 | Galvanized Nuts and Bolts. |
| 42 | Cement bottoming 1:2:4 mix as per REC standard 0.5 cum per pole |
| 43 | Earthing of sub stn. Excavation of earth pit of dia 650mm & depth 3000mm installation of earthing pipe of 40mm Nominal bore & 4mm wall thickness & length 2.5 mtr. Long as per IS 1239. G.I Strip for neutral earthing of size 25mmx3mm for connection of transforemr body, GO Set & lightening arrestor as per IS 2629/85, GI Nuts & bolts refilled with earth enhancement materials and earth chamber with RCC Slab cover |
| 44 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 45 | LT prodigy meter |
| 46 | Danger Plates with Clamps |
| 47 | GI barbed wire for Anti climbing |
| 48 | Painting of 9 mtr ST poles with two coats of Aluminium paint. |
| 49 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 50 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Installation of 1000 KVA Sub Station for providing Uninterrupted Power Supply to PHE Pumping Station Salmey |
| 51 | 11/0.433 KV, 3-phase distribution Transformer 1000 KVA Copper wound Distribution Transformer at latest Energy Efficiency level-2(New) IS 1180 part-1 2014 as per latest upto date amnedment with externally fitted MCCB with cable box and 4x4 mtrs suitable cable of rating with heavy duty accessories complete |
| 52 | Gapless surge Arrestor, 9 kv, 10 KA , LA with polymer housing stn. Type |
| 53 | 11 KV GO AB Switch 3 phase, 3 pole, 1200 Amp, vertical |
| 54 | 11 KV Horn gap fuse set 3 phase 1200 A |
| 55 | 630 mm² 1.1 KV Grade, PVC insulated stranded conductor FRLS Type |
| 56 | 9 mtr. Long ST pole (ST-410 SP-33) |
| 57 | Pgclamps |
| 58 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75 Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 59 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 60 | GI Channel /Angle/flat of sizes including clamps |
| 61 | Galvanized Nuts and Bolts. |
| 62 | Cement bottoming 1:2:4 mix as per REC standard 0.5 cum per pole |
| 63 | Earthing of sub stn. Excavation of earth pit of dia 650mm & depth 3000mm installation of earthing pipe of 40mm Nominal bore & 4mm wall thickness & length 2.5 mtr. Long as per IS 1239. G.I Strip for neutral earthing of size 25mmx3mm for connection of transforemr body, GO Set & lightening arrestor as per IS 2629/85, GI Nuts & bolts refilled with earth enhancement materials and earth chamber with RCC Slab cover |
| 64 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 65 | Transformer Foundation/Pad/G.I Channel Bedding |
| 66 | 3 phase 4 wire Trivector meter with CT PT unit |
| 67 | Danger Plates with Clamps |
| 68 | GI barbed wire for Anti climbing |
| 69 | Painting of 9 mtr ST poles with two coats of Aluminium paint. |
| 70 | Survey, Supply, Transportation, Carriage, Erection, Testing and Commissioning for Erection of 11 kv Tapping Point Uninterrupted Power Supply to PHE Pumping Station Salmey |
| 71 | 9 mtr. Long ST Pole (ST-410 SP-33) |
| 72 | GI V Cross -arm with top Bracket including clamps |
| 73 | GI Channel X-arm including clamps and Angle for braces |
| 74 | 50mm² ACSR rabbit Conductor |
| 75 | PG Clamps |
| 76 | 11 KV GO AB Switch 3 phase, 3 pole,200 Amp, vertical |
| 77 | 11 KV Polymer composite Pin Insulator 12 KV, 5 KN, lighting impulse 75 KV Positive and 80 KV Negative, Creepage distance 320mm. |
| 78 | 11 KV Polymeric Composite Disc insulator 12 KV, min failing load 45 kn, lightening impulse 75KV Positive and 80 KV Negative, creepage distance 320mm with fitting |
| 79 | Galvanized Nuts and Bolts |
| 80 | Earthing complete by GI Rod 20mm 2.5 mtr. Long through GI Strip |
| 81 | Anti climbing device with clamps |
| 82 | Danger Plates with Clamps |
| 83 | Painting of 8mtr ST poles with two coat of Aluminium Paint |
| 84 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator (2Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 85 | Cement bottoming 1:2:4 mix as per REC standard 0.5 cum per pole Please Enable Macros to View BoQ information |