| 1 | Loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 2 | Renewing damaged PSC/RCC Transformer DP structure with new A type Transformer DP and re-erecting all accessories & Transformer (excluding renewal of pipe earthing). |
| 3 | Loading LT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 4 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading. |
| 5 | Erecting one LT PSC Pole in position incl. digging & back filling pit. |
| 6 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit. |
| 7 | Providing Stay for LT poles incl. digging & back filling pit. |
| 8 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of all material (as per specification). |
| 9 | Providing Transformer fencing to a height of 1.8 m above ground level using MS Angle frames of size ISA 50x50x6mm for outer frame, 2 runs of 40 x 6 MS flat for horizontal bracing and grills with MS rods 8 mm Dia @ 10cm c/c for verticals, providing gate with locking arrangements, providing danger board & name board, embeding the legs in cement concrete 1:2:4, footing of size 30cmx30cmx50cm, painting with synthetic enamel paint two coats over one coat of iron primer etc complete, incl cost of materials. |
| 10 | Providing yard metalling with 6mm & 40mm thick blue metal as specified after constructing a curb wall. |
| 11 | Additional rate for refitting/redoing one Shackle set and reshackling one span while renewing any type of pole. |
| 12 | Providing one Earth using earth pipe incl. digging separate pit at standard distance away from the pole/structure & backfilling. |
| 13 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 14 | Renewal of existing damaged/broken old 11kV Stay to the existing stay rod. |
| 15 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Laterite. |
| 16 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Hard Laterite. |
| 17 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole incl. conveyance of materials. |
| 18 | Additional rate for excavation of Pit for A type pole in Hard Laterite. |
| 19 | Additional rate for excavation of one Earth Pit (2.5m depth) in Hard Laterite. |
| 20 | Additional rate for excavation of one Earth Pit (2.5m depth) in Laterite. |
| 21 | Pole numbering using printed Aluminium sheets / Painting the surface of pole with anti algal yellow paint and painting Letters with black paint as specified incl. cost of paint. Please Enable Macros to View BoQ information |