| 1 | Carriage, loading-unloading with proper stacking of following material from Central Store /department store to JE STORE distance approx 20 Km. |
| 2 | PCC pole 8.5 Mtr. Long |
| 3 | 9/11 Mtr. Long ST pole |
| 4 | 11 KV XLPE cable 3x70/120/185/300 |
| 5 | 11 KV CT & PT Unit |
| 6 | Line material Like Angle 65x65x6 & M.S. Channel 10x50x6 Sq.mm./Conductor |
| 7 | Transformer 25 KVA |
| 8 | Transformer 63 KVA |
| 9 | Transformer 100 KVA |
| 10 | Transformer 250/400 KVA |
| 11 | LT AB cable1x16/ 3x120 |
| 12 | LT DP Box |
| 13 | Stay set |
| 14 | Cable Jointing Kit O/D & I/D 3x70/120/185/300 Sq.mm. |
| 15 | ACSR/DOG/WEASEL CONDUCTOR |
| 16 | Carriage, loading-unloading with proper stacking ofPCC/ST Pole from JE dump store to site |
| 17 | Fabrication erection of Substation D/P on 9/11 Mtr. ST pole Long with fixing of necessary clamps accessories required including supply and fixing of straight MS Channel 100x50 mm. (2240 mm long ) one Nos with arrangement of fixing 3 Nos. pin insulator,(ST pole/ PCC Pole supplied by the deptt). |
| 18 | Fabrication erection of Single pole 11 Mtr. Long STP/8.5 long PCC Pole with fixing of necessary clamps, X-Arm/T-of Channel accessories required including digging of pit and fixing of all necessary clamps for 11 KV line. (Pole shall be supplied by the departmrment ) |
| 19 | Grouting of poles with help of cement sand & brick ballast. |
| 20 | Plinthing of pole with the help of cement core sand & stone ballast. |
| 21 | Painting of pole with aluminum and rex oxide paint |
| 22 | Erection of stays with stay set of 16x1800 mm rod duly painted with red oxide, anchor plate, thumble turn buckle and stay insulator etc. digging of pit of size 0.4x0.6x1.6m for grouting by 1:3:6 cement concrete, with stay of size 7/10 swg,nozzling& grouting. (stay set & stay wire will be provided by the depatrtment) |
| 23 | Earthing of poles as per RESPO Norms with earth rod (All the material supplied by the contractor ) |
| 24 | Stringing, sagging, binding, jump ring of 11 KV 3 phase 3 wire line with ACSR/DOG/WEASEL CONDUCTOR |
| 25 | Laying of AB conductor 1X16/3x120 Sq.mm/3x95. (Cable supplied by the Department) |
| 26 | Mounting & Fixing of 3 phase Distribution Box as per Norms (Only Box supplied by the department ) |
| 27 | Mounting of 25 KVA Transformer on D/P structure as per RESPO Norms (Except T/F all the materials will be supplied by the contractor ) |
| 28 | Mounting of 63 KVA Transformer on D/P structure as per RESPO Norms (Except T/F all the materials will be supplied by the contractor ) |
| 29 | Mounting of 100 KVA Transformer on D/P structure as per RESPO Norms (Except T/F all the materials will be supplied by the contractor ) |
| 30 | Installation comminsning of 250 KVA/400 KVA Transformer including its connection on plinth. |
| 31 | Laying of 11 KV 3x70/120/185 sq.mm. in normal soil by digging of trench of size 900 mm deep 500 mm wide. The cable will be laid in between two rows of first class bricks with sand local sand from each (Only cable will provided by the department). |
| 32 | Cardel Type guarding of 11 KV line made of GI No. 10, GI wire shall be supplied by the department |
| 33 | Fixing of guarding Angle of size 40x40x5x1500 mm. (All material Supplied by the contractor ) |
| 34 | Hoisting of 11 KV 3x70/120/185/300 Sq.mm. XLPE cable on existing pole cable will be passed through MS pipe of required size duly clamped with pole at bottem, middel and top of thepole (All the material Arrenged by the contractor) |
| 35 | Fixing of MS Channel of size 750x75x50x3mm. |
| 36 | S/F of T off channel100x50x1500mm |
| 37 | Pipe type earthing with 20 Mtr. Deep boring and providing of GI pipe 1.5 Dia (20 Mtr. GI pipe ) of total Jindal Make and GI strip 25x5 mmx6 mtr. Long attached with clamps L-Piece Nut & Bolts and GI pipe cape All Mterial Shall be supplied by contractor. |
| 38 | Installation and commissioning of CT/PT metering Unit including its connection connection in between TVM meter. And CT/PT Unit with required size of copper cable . Cable will be arranged by the contractor as his own cost . |
| 39 | Construction of plinth suitable of 250 KVA/400 KVA Transformer including excavation of foundation base concerting of CC 1:6:12 (cement , fine sand & bricks Ballast ) first class brickwork in cement motor of ratio 1:4 foundation CC in 1:4:8 ration (cement fine sand & brick Ballast) and CC work with ratio 1:2:4 cement coarse sand and stone grit of 20 mm. Gauge per RESPO Norms. |
| 40 | Fabrication & erection of wire mesh fencing of size 3x2x1/5 Mtr height. |
| 41 | Construction of massonary type distribution piller box with first class brick ballast cement coarse sand, local sand, brick ballast and MS round bar of 10 mm. Dia including fixing of 1 Nos 500 Amp/650 Volt fuse unit & 2 Nos 300 Amp/500 Volt fuse unit with Copper Busbar etc. |
| 42 | Making of circuits |
| 43 | Providing Copper L Piece for 250/400 KVA Transformers. |
| 44 | Taping of line |
| 45 | Providing & fixing of 11 KV TPMO (All material will be arranged by the contractor). |
| 46 | Supply & Laying of GI pipe 4' Dia under road X-ing |
| 47 | Supply & Fixing of D o fuse set. |
| 48 | Supply and fixing at different size nuts and bold Please Enable Macros to View BoQ information |