| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kind of soil. |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 cement : 4 coarse sand (zone-iii) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) |
| 3 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand (zone-iii) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 4 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement 1:1.5:3 (1 cement : 1.5 coarse sand(zone-iii) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 5 | centering and shuttering including strutting, propping etc. and removal of form for : foundations, footings, bases of columns, etc. for mass concrete |
| 6 | centering and shuttering including strutting, propping etc. and removal of form for lintels, beams, plinth beams, girders, bressumers and cantilevers |
| 7 | centering and shuttering including strutting, propping etc. and removal of form for columns, pillars, piers, Abutments, posts and Struts |
| 8 | Steel reinforcement for r.c.c. work including straightening, cutting, bending, placing inposition and binding all complete upto plinth level.thermo-mechanically treated bars of grade fe-500D or more. |
| 9 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 150 in superstructure above plinth level up to floor V level in all shapes and sizes Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 10 | 12 mm thick cement plaster in 1:4 |
| 11 | Finishing walls with water proofing cement paint of required shade :New work (Two or more coats applied @ 3.84 kg/10 sqm) |
| 12 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. Please Enable Macros to View BoQ information |