| 1 | Construction of embankment with approved material obtained from Right of Way with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2.(Embankment)(excluding gst) |
| 2 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MORD Technical Speicification Clause 401(excluding gst) |
| 3 | Providing,laying and spreding material on a prepared Sub Base, cement @ 4% by wet to the spread material manually mixing in place Rotavator and compcting with the road roller at OMC to achive the desired unconfined Compressive strength and to form a Layer of Base.(excluding gst) |
| 4 | Providing and applying tack coat with bitumen (VG-10)using bitumen pressure distributor at the rate of 0.35 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Speicification Clause 503 including cost of bitumen (VG-10)(excluding gst) |
| 5 | Providing, laying and rolling of open-graded premix carpet of 20mm thickness composed of 13.2 to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line grade and level to serve as wearing coarse on a previously Prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100kN static roller capacity finished to required lavel and grades to be followed by seal coat as per Techincal Specification clause 508 including cost of bitumen.(excluding gst) |
| 6 | Providing and applying seal coat type \\"C\\" comprising of a layer of bituminous binder followed by a cover of stone chipping of specified grading and rolling with power roller 8-10 tonne kN Static roller and finishing to required level and grades as per Technical Specification Clause 510 including cost of bitumen(excluding gst) |
| 7 | (Construction of subgrade and Earthen shoulders)Construction of sub-grade and earthen shoulders with approved material obtained from Right of Way with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 as per Technial Specification Clause 303.1..(excluding gst) |
| 8 | Earthwork in excavation for foundation of structures upto 3.00m depth as per drawing and technical specification clause 1104 including setting out,construction of shoring and bracing,removal of stumps and other deleterious matter,dressing of sides and bottom and back filling with approved material.(excluding gst) |
| 9 | Plain cement concrete M10(1:3:6 nominal mix) in levelling course below open foundation of head wall as per drawing and technical specification clause 1109.(excluding gst) |
| 10 | Laying of ( 40mm S.S.B. )Bedding on well compacted sand,moorum or approved granular material as per Clause 1105(ii) .(excluding gst) |
| 11 | Brick Masonry Work in cement mortar (1cement :4 coarse sand) in foundation of head walls complete excluding poining and plastering as per rawing and technical specification Clause 1109l.(excluding gst) |
| 12 | Providing and laying R.C.C.Pipe NP3 for culverts on first class bedding of granular material in sigle row including fixing collar with (1cement :2 coarse sand cement mortar but excluding excaation protection work,back filling,concrete ad masonry wok in head wall and parapet Clause 1106.(excluding gst) |
| 13 | Pointing with cement mortar (1cement:2 fine sand) on brick work as per technical specification clause 613.3(excluding gst) |
| 14 | Backfilling from granular material in foundation trenches as per drawing and technical specification Clause 1108. (excluding gst) |
| 15 | The maintenance of constructed for next five year after comletion of work shall be paid As per GO No.17/2024/सा0-113/23-1-2024-23-1099-113/2023 लोकनिर्माण विभाग अनुभाग-1 दिनांक 16-01-2024 एवं कार्यालय प्रमुख अभियन्ता यातायात वर्ग लो0नि0वि0 लखनऊ का पत्रांक -3689सी-ओ0पी0आर0एम0सी0/मूल-23-24 दिनांक 17-02-2024.Payment Shall be done as per satisfaction of Engineer incharge regarding maintenance work carried our by contractor(Including labour cess bur GST will paid extra as applicable)Ist Year maintenance cost total construction of cost Item no.1 to14 @ Zero percent & For 2nd year @0.75 % |
| 16 | For 3rd Year @1.5% |
| 17 | For 4rd Year @2.25% |
| 18 | For 5rd Year @3% Please Enable Macros to View BoQ information |