| 1 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. Ordinary soil Mechanical Means (Depth upto 3 m). |
| 2 | Providing and laying of PCC M15 levelling course 100mm thick below the pile cap. PCC Grade M15 using batching plant & Concretepump |
| 3 | Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm) |
| 4 | Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification. RCC Grade M 35 using batching plant & Concrete pump |
| 5 | Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and technical specifications |
| 6 | Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specifications. RCC Grade M 30 Height above 10m With Batching Plant, Transit Mixer and Concrete Pump |
| 7 | Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications |
| 8 | Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications |
| 9 | Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firmcondition complete as per drawing and technical specification. |
| 10 | Construction of Embankment with Material Obtained from Borrow Pits Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 |
| 11 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction |
| 12 | Providing and Laying of Mechanically Woven Double Twisted Hexagonal shaped Gabions of galvanized steel, of size 3mX1mX1m with two diaphragms at 1m interval, having mesh opening 100mmx120 mm, mesh wire diameter 3 mm for gabions, edge/selvedge wire diameter 3.9 mm and lacing wire diameter 2.2 mm. (The work includes filling boulders in the gabions). Please Enable Macros to View BoQ information |