| 1 | Laying of 40 mm dia MS round bar 0.7 Meter below ground level including cutting, bending, straightening, welding, and painting, excavation, back feeling & all other associated work to complete the job satisfactorily as per direction of Engineer in charge (M.S. round bar shall be provided by department). |
| 2 | Fabrication of electrode by 40 mm dia MS rods in length of 3 mtr by making an edge at one end for ease in piercing below 1200mm into the ground using wooden hammer completely at all the junction points along with welding & painting at outer periphery of earth mat as per relevant IS (M.S. round bar shall be provided by department). |
| 3 | Interconnection of the earth mat laid with the existing earth mat of the 132 KV S/S DLW at specified point by welding as that complete earth mat acts in coherent manner to provide proper earthing of the substation. |
| 4 | Sorting counting shifting of GI structure to loading point and loading on private vehicle at EFU Naini, Prayagraj (1.7 MT Approx.). |
| 5 | Safe Carriage of GI structure(1.7 MT Approx.) from EFU Naini Prayagraj to 132 KV S/S DLW (Approx distance 140KM) through private vehicle to be provided by the contractor. |
| 6 | Unloading of structure(1.7 MT Approx.) from vehicle, its sorting counting and proper stacking at the premises of 132 KV S/S DLW at suitable place. |
| 7 | Erection of structure parts of Main & Auxiliary structure. The job consist to shifting of all material, structure parts, nut bolts washers etc from store to work site, erection of structure as per relevant drawing and practices. |
| 8 | Painting of pale fencing by scratching,rubbing,with wire brush, cleaning applying one coat of red oxide primer and two coat of synthetic enamel paint of bus green color of standard quality. |
| 9 | Dismantling of 3 No. CT , 1 No BSI etc including shifting and proper stacking of the received material to the store of the Sub station. |
| 10 | Safe Carriage of Equipments/Structures/Conductor ETC from Different Storage location of ETD-I varanasi as and when required and as per Direction of AE/JE Concerned for Satisfactorily completion of Work . |
| 11 | Erection of following equipments including shifting from different storage location under this Division to 132KV SS DLW erection site including all other associated works to complete the job satisfactorily. |
| 12 | 36 KV VCB |
| 13 | 36 KV CT |
| 14 | 36 KV CT Junction Box |
| 15 | 36 KV LSI |
| 16 | 36 KV LSI Junction Box |
| 17 | 36 KV BSI |
| 18 | 36 KV BSI Junction Box |
| 19 | 33KV Tripple Feeder C&R Panel(Numerical) |
| 20 | Jumpering of following bay equipments with the help of Twin ACSR Panther conductor including cutting bending clamping with all other associated work from main bus to outgoing isolators for all phases. |
| 21 | Laying of following sizes of control cable in the cable trenches from C&R Panel to various type of equipments, junction boxes in switch yard as per cable schedule, its clamping/binding at every two meter distance with aluminium sticks 25x1mm size including carriage of cable drums from store to laying site and shifting back to store and all other associated work to complete the job satisfactorily as per tech. specification: |
| 22 | 2x2.5mm²Control Cable |
| 23 | 4x2.5mm²Control Cable |
| 24 | 6x2.5mm²Control Cable |
| 25 | Termination of following size of cable as laid above as per cable schedule including making necessary holes in glands plate or boxes where ever required. Supply and fixing of cable glands of appropriate size. Supply and providing ferrules and No. for each core of cable and its termination with crimping type lugs of Dowell/Tension and all other associated work to complete the job satisfactorily as per tech. specification: |
| 26 | 2x2.5mm²Control Cable |
| 27 | 4x2.5mm²Control Cable |
| 28 | 6x2.5mm²Control Cable |
| 29 | Cutting straitening bending laying of 75x10 mm MS flat for earthing of main structures including welding with main earth mat below 500-700 mm of ground level with object to earth excavation of trenches its back filling, painting with one coat of red oxide primer and two coats of synthetic enameled green colour with all cost of MS flat, Paint, T&P required for completion of work. Note- M.S. Flate will be provided by Contractor. |
| 30 | Cutting straitening bending laying of 50x6 mm MS flat for earthing of main structures including welding with main earth mat below 500-700 mm of ground level with object to earth excavation of trenches its back filling, painting with one coat of red oxide primer and two coats of synthetic enameled green colour with all cost of MS flat, Paint, T&P required for completion of work. Note- M.S. Flate will be provided by Contractor. |
| 31 | Earthing of trench alongwith 25x6mm MS flat after cutting and welding with cable rack and trench with all cost of MS flat, including painting with one coat of red oxide primer and two coats of synthetic enamelled paint. Note- M.S. Flate will be provided by Contractor. |
| 32 | Fabrication of display board made of M.S. angle iron 50x50x6mm, 3 long support and M.S. board of 2'x1' M.S. sheet 18 gauge and M.S. flat iron 25x6mm size 2'x1' welded on M.S. sheet after then M.S. pipe of 1.5\\" dia. fitted around M.S. flat on the sheet board and 0.5\\" dia M.S. pipe 4\\" long welded in M.S. angle iron from two places at one side and two at other to complete the display board. Digging pit size 2'x2'x3' and grouting above board with 1:2:4 cement, ballast, sand ratio and making plinth of size 1'x2'. Board shall duly painted by yellow color and equipment name shall be written in black. |
| 33 | Supply |
| 34 | Supply & fixing of 150W outdoor type LED flood light complete fitting with all fixing accessories including bracket and clamps of Philips/Crompton/Havells/Bajaj/Halonix make. Original warranty card should also be submitted along with above material. |
| 35 | Suspension fitting suitable for 70kN disc insulator complete with all accessories suitable for Single Moose conductor as per sample. |
| 36 | PG clamp Moose to Moose made of LM-6 alloy four bolted type complete with good quality nut bolt washer and spring washer exactly as per sample in ready to use condition. |
| 37 | Supply of 33KV Isolator clamp for twin panther conductor made up of LM-6 alluminium alloy with nut bolt and washer & as per Sample. |
| 38 | Supply of 33KV Isolator clamp for twin moose conductor made up of LM-6 alluminium alloy with nut bolt and washer & as per Sample. |
| 39 | Supply of 33KV CT clamp for twin panther conductor made up of LM-6 alluminium alloy with nut bolt and washer & as per Sample. |
| 40 | Supply of 33KV CB clamp for twin panther conductor made up of LM-6 alluminium alloy with nut bolt and washer & as per Sample. |
| 41 | Supply of 33KV Rama make Isolator Jaw having capacity 1250A made up of Electrolytic Copper with nut bolt and washer & as per Sample. |
| 42 | Supply of GI Nut bolt of Size 16x40mm |
| 43 | Supply of GI Nut bolt of Size 16x45mm |
| 44 | Supply of Spring Washer Size 16x3.5mm |
| 45 | GI Perforted Cable Tray 225 MM |
| 46 | GI Perforted Cable Tray 75 MM Please Enable Macros to View BoQ information |