| 1 | Replacement of existing damaged expansion joint by Providing and laying of Strip Seal Expansion Joint System, including cleaning of gaps, dismantling of deck slab portion near expansion joint, wearing coat etc. and back filling of the recess up to final finish level with concrete of grade M - 35, complete as per approved drawing(s), M.O.R.T&H technical specification section 2607 Sl-17.17 (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 2 | Lifting of superstructure span by jacking up from below i.e. by placing the jacks on piers/abutment caps for span length of 30m. Lifting of deck uniformly by deploying appropriate hydraulic jacks in combination of screw jacks with centralized power pack upto 50mm to facilitate for removing of existing bearing appropriately without damaging the girders. After complection of the restoration of main girders at support strengthning/restoration of pedesral by micro concrete/ polymer concrete/epoxy mortar with reinforcement cage replacmnt of proposed according previously damaged metalic bearing rockers and roller same and specified design lowering of deck shall be carried out to its original position without causing any damage to the as per drawing and standard practice. the item includes of all labour, materials, equipment etc complete as per direction and intructions of E/I including MORT&H tecnical specification (clause 2810) (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 3 | Replascement of Elastomeric bearing supplying fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specification complete as specification in Dwrawing includes all materials as per drg. and design approved by competent authority complete as per specification and instructions of Engineer in charge but Excluding cost of lifting of Deck slab (Size of bearing is 65.00x40.00x9.00 cm) (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 4 | Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical Specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion of grouting with Cement/Epoxy (Analysed) (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 5 | Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1. (Analysed) (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 6 | Epoxy bonding of new concrete to old concrete (Analysed) (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 7 | All charges manufacturing and , replacement of GI Drainage spout as per Morth specificationscomplete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation. including cost of all materials, Labour, cess T&P etc. and all taxes complete but Excluding GST. (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 8 | GP2 grouting material applying and concreting work M35 in Expension both ends including cost of form work including supply of all material labour T&P etc complete as per direction of Engineer Incharge (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 9 | Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength not less than 25 Mpa and workmanship conforming to clause 2807.6. (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 10 | Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications (for Bearing Coat) (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 11 | Steel work welded in built up tubler (Round,square or reqtengular, hollows tube etc) truses etc includjng cutting, hoisting,fixing in position and applying a priming coat of approved steel primer including welding and bolted with special shape washer etc. complete As per DSR 10.16.1 (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 12 | Dismantling of existing sructure like culvert, bridges, retaining walls and other structure cumprising of mesonery, cement concrete, wood work, steel work, including T&P and scafolding where ever nacessure , shorting the dismenteled meterial disposal of unserviceble material and stacking the serviceble meterai with all lift and lead of 1000 meter by mechenical means cement conctrete grade M-15 &M-20 As per SOR 2.1/ 202(II)A Chepter-4 (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 13 | Plain cement concrete (PCC grade M-20) in open foundation complete as per drawing and technical specifications clause 1500,1700 and 2100 As per SOR 12.08B-case-1 chepter-6 (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 14 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade Two or more coats on new work including cost of all materials, labour T&P etc. required for proper completion of work. Wood and steel As per DSR 13.62 (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) |
| 15 | Flexible Median Marksr As Per IRC 79:2019:Flexible lMedian N4arker (Flv4Nl) should be used for improving medlan visib lity dlrring dark hours. , Use of l/edian ]Varker provides safely againsl colision happening wilh med ans during n ght lime , or seveTe weather' Flexib e l\.4edian Markers shall be provided with fluorescenl yellow colour retro-reflecting sheeting Type Xl as per IRC:87. Flexible lt4edian lMarker shaLl be ol lough, high impact resistant, lnieclion molded, lhermoplastic body with propery of flexibility io provide high durability'and U shape structure having rebound / bollnce back properly. the sheeting shall be of Type Xl conforming to lRCl67 and ii should be on both the faces whereby providing maximum refleclivity at l,anger distances with adequate durabllity. The logo of the manufacturer shall be embossed on either side of the body during the lnjection molding process. FI\4M shall be fixed by a combination bf epoxy adhesive and grouting/ drilLing on concrete medians or property conslructed solid medians Heighl: The marker height shall be a minimum of 180 mm width 120 mm & Body Thickness: 6.5 mm. the shanks shall not be less lhan 20 mm and depth shall not be less than 30 mm Reflective Area: Shall not be less than g0 cm square .Proof of lhe same Report shall be uploaded which quollng lender. The body of FN,4[,4 shall bounce back to ils origlnal position of afier 750 number of hits using pendulum of 1.8 kg conforming 40 ASTM D256 adhesion between the body and outer casing body of FMI\4 shall with stand 50 kg I Tensile loads conforming to ASTM D63B method. The rate shall include all materials, labour,T&P, transportation, installation and incidentals all complete as per direclion of the Engineer-ln-Charge.As per SOR item 8 of Chepter 6 (Including Supply of Material, Labour and T&P work complete as per direction of E-in-C. Including all taxes but excluding GST.) Note - 1- Rates are inclusive of all taxes but excluding GST which shall be paid extra as applicable 2- Labour cess @ 1% will be deducted from contractor's bill at the time of payment Please Enable Macros to View BoQ information |