| 1 | Sub Head - I |
| 2 | SITE CLEARANCE |
| 3 | Clearing and Grubbing Road Land.Clearing and grubbing road land including uprooting wild vegetation , grass, bushes, shrubs, saplings and trees of girth upto 300 mm , removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MoRT&H Technical Specification clause 201. (A)In area of light jungle |
| 4 | Making 50 mm x 50 mm FurrowsMaking 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to the center line of the road and at one metreinterval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated material within 1000 metres lead as per MoRT&H Technical Specification Clause 404.3.1.(ii) 50 mm deep furrow cutting |
| 5 | Sub Head - II |
| 6 | EARTH WORK |
| 7 | Compacting Original ground(i) Compacting orginal ground supporting Subgrade.Loosening of the ground upto a level of 500 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of Tables 300.2 for subgrade construction as per MoRT&H Technical Specification clauses of section 300. |
| 8 | Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with Disposal upto 1000 metres.Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections and transporting to the embankment location with all lifts and lead upto 1000 m as per MoRT&H Technical Specification clauses of section 300. |
| 9 | Construction of Embankment with Material deposited from Roadway Cutting.Construction of Embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300.2 and as per MoRT&H Technical Specification clauses of section 300. |
| 10 | Construction of Embankment with Material Obtained from Borrow PitsConstruction of embankment with approved material obtained from borrow pits with all lifts, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 5000 m as per MoRT&H Technical Specification clauses of section 300. |
| 11 | Construction of Subgrade and Earthen ShouldersConstruction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site , spreading, grading to required slope and compacted to meet requirement of Table 300.2 as per MoRT&H Technical Specification clauses of section 300. |
| 12 | Sub Head - III |
| 13 | DRAINAGE WORK |
| 14 | Surface Drains in Ordinary Soil Construction of unlined surface drains of average cross-sectional area 0.4 sqm in ordinary soil to specified lines, grades, levels and dimensions as per MoRT&H Technical Specification clauses of section 300. Excavated material to be used in embankment with a lift upto 3 m and lead of 50 m (average lead 25 m(A)Mechanical Means |
| 15 | Road side Pucca drains.Construction of road side pucca drain with M10 (1:3:6 with jhama brick aggregate) to specified lines, grades, levels and dimensions as per approved design and MoRD Technical Specification Clause 307, 1606. Excavated material to be used in embankment at site. (including centering, shuttering, etc. but excluding reinforcement) (C)Trapezoidal drain ( top clear width 600 mm, bottom clear width 300 mm and clear depth of 600 mm)(I) In Ordinary Soil |
| 16 | RCC DrainExcavation for StructuresEarthwork in excavation for structures as per drawing and MoRT&H technical specifications Clause 304 including setting out, construction of shoring & bracing, removal of stumps & other deleterious material and disposal upto a lead of 50 m, dressing of sides & bottom and backfilling in trenches with excavated suitable material.(I) Ordinary soil(A) By Manual Means(i) Upto 3 m depth |
| 17 | Sand Filling in foundation trenches as per drawing & MoRT&H technical specification clause 304. |
| 18 | PCC 1:3:6 in FoundationPlain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days as per drawings & MoRT&H technical specifications Clauses 2100. (including centering, shuttering, staging etc. but excluding reinforcement) |
| 19 | Plain/reinforced cement concrete in substructure complete including formwork as per drawings & MoRT&H technical specification Clauses 1500, 1700, 2200. (including centering, shuttering, staging etc. but excluding reinforcement) vi) RCC M25 Gradea. Upto 5 m heightCase:I: Using Concrete Mixer |
| 20 | Supplying, fitting & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar reinforcement in substructure complete as per drawings & MoRT&H technical specification Clauses 1600, 2200. |
| 21 | Plastering with cement mortar (1:4) 12 mm thick on brickwork/ C.C. work including a finishing coat of neat cement punning with 2.75 kg of cement per sqm in substructure as per MoRD technical specification Clauses 613.4 & 1204. |
| 22 | Sub Head -IV |
| 23 | PROTECTION WORK ( Retaining Wall ) |
| 24 | Excavation for StructuresEarthwork in excavation for structures as per drawing and MoRT&H technical specifications Clause 304 including setting out, construction of shoring & bracing, removal of stumps & other deleterious material and disposal upto a lead of 50 m, dressing of sides & bottom and backfilling in trenches with excavated suitable material.(I) Ordinary soil(A) By Manual Means(i) upto 3 m depth |
| 25 | Sand Filling in foundation trenches as per drawing & MoRT&H technical specification clause 304. |
| 26 | PCC 1:3:6 in FoundationPlain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days as per drawings & MoRT&H technical specifications Clauses 2100. (including centering, shuttering, staging etc. but excluding reinforcement) |
| 27 | Plain/reinforced cement concrete in substructure complete including formwork as per drawings & MoRT&H technical specification Clauses 1500, 1700, 2200. (including centering, shuttering, staging etc. but excluding reinforcement) vi) RCC M25 Grade |
| 28 | Plain/reinforced cement concrete in substructure complete including formwork as per drawings & MoRT&H technical specification Clauses 1500, 1700, 2200. (including centering, shuttering, staging etc. but excluding reinforcement) vi) RCC M25 Gradea. upto 5 m heightCase I: Using Concrete Mixer |
| 29 | Supplying, fitting & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar reinforcement in substructure complete as per drawings & MoRT&H technical specification Clauses 1600, 2200. |
| 30 | Providing weepholes in brick masonry/ stone masonry, plain/ reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe or uPVC pipe (110 mm OD of 6.0 Kg/cm2 pressure) extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and MoRT&H technical specification clauses 2706, 2200. |
| 31 | Providing & laying filter media with jhama brick aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil & bigger size towards the wall & providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and MoRT&H technical specification clause 2504.2.2 |
| 32 | Sub Head -V |
| 33 | GRANULAR SUB - BASES, BASES( Non -Bituminous ) AND SHOULDERS. |
| 34 | Granular Sub-base with Well Graded Material (Table 400.1)(A) By Mix in Place MethodConstruction of granular sub-base by providing well graded material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per MoRT&H Technical Specification Clause 401.i)For Grading I Material |
| 35 | Wet Mix MacadamProviding, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver finisher in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density as per MoRT&H Technical Specification Clause 406. |
| 36 | Sub Head - VI |
| 37 | BASES AND SURFACE COURSES ( Bituminous ) |
| 38 | Prime CoatProviding and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.6 kg/sqm using mechanical means as per MoRT&H Technical Specification Clause 502. |
| 39 | Tack CoatProviding and applying tack coat with bitumen emulsion (RS-1) using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous / granular surface cleaned with Hydraulic broom as per MoRT&H Technical Specification Clause 503. |
| 40 | Dense Graded Bituminous MacadamProviding and laying dense graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRT&H specification clause No. 507 complete in all respects.(B) Grading II (For layer thickness 50-75 mm)i. With Viscosity Graded Bitumen of VG-30. |
| 41 | Bituminous ConcreteProviding and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.40 Percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects.(B) Grading II (For layer thickness 30 - 40 mm)i. With Viscosity Graded Bitumen of VG-30. |
| 42 | Sub Head -VII |
| 43 | TRAFFIC SIGN, MARKINGS & OTHER ROAD APPURTENANCES |
| 44 | Retro-reflectorised Traffic SignsProviding and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of high intensity grade shetting vide MoRT&H technical specification Clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and MoRT&H Technical Specification Clause 801. |
| 45 | (i) with 900 mm equilateral triangle |
| 46 | (ii) with 600 mm equilateral triangle |
| 47 | Direction and Place Identification Signs with upto 0.9 sqm Size board.Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 x 450 x 600 mm, 600 mm below ground level as per approved drawing and MoRT&H Technical Specification Clause 801. |
| 48 | Road Marking strips (retro-reflective) of specified shade/colour using Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous SurfaceProviding and applying of 2.5 mm thick thick Road marking strips ( retro - reflective ) of specified shade / colour using hot thermoplastic material including reflectorising glass beads @ 250 gms per sqm area by fully / semi automatic thermoplastic paint applicator machine fitted with profile shoe, glass beads dispenser, propane tank heater and profile shoe heater including cost of cleaning the road surface of all dirt, seals, oil, grease and foreign materials etc, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 . The finished surface to be level, uniform and free from streaks and holes. as per MoRT&H Technical Specification Clause 803. |
| 49 | Kilo Metre StoneReinforced cement concrete M 15 grade kilometre stone of standard design as per IRC:8, fixing in position including painting and printing, etc. as per drawing and MoRT&H Technical Specification Clause 804. (ii) Ordinary Kilometre Stone(precast) |
| 50 | Type - B, \\"THRIE\\" : Metal Beam Crash Barrier Providing and erecting a \\"Thrie\\" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per MoRT&H Technical Specification Clause 811. |
| 51 | Road Markers/Road Stud with Lense Reflector Providing and fixing of road stud 100x 100 mm, die-cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973 |
| 52 | Maintenance for 5 years |
| 53 | Maintenance for 1st year |
| 54 | Maintenance for 2nd year |
| 55 | Maintenance for 3rd year |
| 56 | Maintenance for 4th year |
| 57 | Maintenance for 5th year Please Enable Macros to View BoQ information |