| 1 | Excavation in foundation for retaining & breast walls in all types of soils and rocks including lead, lift and disposal of surplus material as per direction of engineer - in - charge. |
| 2 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete includingsupply of all material, labour, T&P etc. required for proper completion of the work.as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction |
| 3 | Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc.including supply of all material, labour, T&P and royaltiies etc. complete as perdrawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORDSpecifiction |
| 4 | Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, in breast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction |
| 5 | Providing and Laying of Mechanically Woven Double Twisted Hexagonal shaped Gabions of galvanized steel, of size 3mX1mX1m with two diaphragms at 1m interval, having mesh opening 100mmx120 mm, mesh wire diameter 3 mm for gabions, edge/selvedge wire diameter 3.9 mm and lacing wire diameter 2.2 mm. (The work includes filling boulders in the gabions). |
| 6 | Hand Packed stone filling in back of wallls including cost of all materials, royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) |
| 7 | Construction of coolie walling including supply of all material, labour, T&P etc. required for proper completion of the work as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) |
| 8 | Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 |
| 9 | Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 HP and disposal of the same on the valley side complete as directed by the Engineer-in-charge. |
| 10 | Cleaning of fully choked scupper and catchpit complete as directed by the Engineer in-charge. |
| 11 | Cleaning of partially choked scupper and catchpit complete as directed by theEngineer-in-charge |
| 12 | WBM Grading 3Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. By Manual Means |
| 13 | Katcha/ Pucca DrainExcavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction |
| 14 | Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction |
| 15 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 P.C.C grade M 10 Nominal mix 1:3.6 |
| 16 | Stone masonry in cement mortar for substructure complete as per drawing & technicalspecification Clauses 702, 704, 1202 and 1204Random rubble masonry In cement mortar (1:5) |
| 17 | Cement plaster 15 mm thick 1:4 on stone masonry |
| 18 | Surface Drains in SoilConstruction of unlined surface drains of average cross-sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions. Excavated material to be used in embankment with a lift upto 3m and lead of 50 m (average lead 25 m) as per Technical Specification Clause 307. Manual Means 307 Please Enable Macros to View BoQ information |