| 1 | ( Aug. 63 kVA to 400 kVA S/Stn.) |
| 2 | Prov.Distribution Transformer (Ordinary), 400 KVA, 11/0.4 kV |
| 3 | Prov.Steel Tubular Poles (9 m, Working Load > 200 kgf/m²) Provided by HPSEBL |
| 4 | Prov.Muffs with concerete filling |
| 5 | Prov.X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for incomer line |
| 6 | Prov.MS Angle Iron (50X50x6 mm), Length: (2800 mm) x1 Nos for LA's |
| 7 | Prov.X-Arm: [Channel Iron (75x40x6 mm), Length : (2800 mm X 4 Nos] for supporting DO fuse unit & GO switch |
| 8 | Transformer Bed, Belting & Knee Bracing |
| 9 | X-Arm:[Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos]forTransformer Bed |
| 10 | X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of Transformer] |
| 11 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 12 | MS Angle Iron (35X35x5 mm), Length : (460 ) x 2 Nos |
| 13 | MS Angle Iron (50X50x6 mm), Length : (950 mm) x 2 Nos for Bed Knee Bracing |
| 14 | Transformer LT Distribution Box and GO Switch fixing Assembly |
| 15 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 16 | MS Angle Iron (50X50x6 mm), Length : (450 mm) x 1 Nos |
| 17 | GO Switch Handle Supporting: [Channel Iron (75x40x6 mm), Length : 460 mm |
| 18 | GO AB Switch Unit (11kV, 400A, 25 KA ) Tripple pole O/D type |
| 19 | D.O Fuse Unit |
| 20 | Surge Arrester, 9 kV Station Class (Porcelain Type) |
| 21 | Discs insulator sets (comprising 1No.Disc(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 22 | Stay set complete |
| 23 | Stay Wire (7/3.15 mm) (7.0 kg Per Stay Set) |
| 24 | Pipe Earthing Set |
| 25 | GI wire for Earthing |
| 26 | LT Distribution Panel Box with ACB(1000A, 50 kA, 4P,) and SFU(100A, 6No, rewirable) |
| 27 | Half Clamp (M.S. Flat 50X6 mm) Provided by HPSEBL |
| 28 | Full Clamps (M.S. Flat 50X6 mm) Provided by HPSEBL |
| 29 | Nuts and Bolts of Various Sizes (with flat and spring washers)] |
| 30 | Aluminium Thimble Provided by HPSEBL |
| 31 | Aluminium Thimble Provided by HPSEBL |
| 32 | Danger Plate |
| 33 | Barbed Wire |
| 34 | LT Cable (3.5 Core) 400 mm² X 2 incommer |
| 35 | LT Cable (3.5 Core) 70 mm² X 6 Outgoing |
| 36 | Energy Meter (3-Phase, 4-Wire) DLMS compliant1000/5 A CT Type for 400KVA Transformer |
| 37 | Aluminium Paint. |
| 38 | Red oxide |
| 39 | a)Transformer Bed( Civil Work |
| 40 | b) Chain Link fencing , Angle Iron ,Gate etc for transformerfencing |
| 41 | CT-PT Unit Belting & Knee Bracing |
| 42 | X-Arm:[Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos]for CT-PT Unit |
| 43 | X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of CT-PT Unit] |
| 44 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 45 | MS Angle Iron (35X35x5 mm), Length : (460 ) x 2 Nos |
| 46 | MS Angle Iron (50X50x6 mm), Length : (950 mm) x 2 Nos for Bed Knee Bracing |
| 47 | Prov. CT-PT Combined Unit 11 KV 15/5 Amp |
| 48 | Prov.Energy Meter 11 KV HT -/5 Amps |
| 49 | PVC Multistrand 4 mm² copper wire with Φ-1 inch GI pipe for concealing |
| 50 | Addl. Civil work along the line for strengthening of poles L/s |
| 51 | Add Erection charges complete in all respect |
| 52 | Add Transportation charges complete in all respect |
| 53 | 3-Phase L.T Line |
| 54 | AAAC 7/3.15 (55mm²) {Includes 3 conductor lengths for 3Φ and Additional 1% (Sag, Jumpering and wastage} |
| 55 | Steel Tubular Poles (8 m, Working Load > 200 kgf/m²) (with Ruling Span 67 m) |
| 56 | Muffs with concerete filling |
| 57 | Shackle Insulator (16 kN) |
| 58 | D-Iron (U- Clamps) |
| 59 | Prov. LT AB Cable Size 3X120+16+70mm2 |
| 60 | Earth Knob |
| 61 | LT Stay Set |
| 62 | Stay Wire (7/3.15 mm) (6.0 kg Per Stay Set) |
| 63 | Full Clamps [ 2 No for A.I + 1 No for Stay Set] |
| 64 | Spool Tie |
| 65 | Earth wire (GI, 8 SWG) {Additional 1% (Sag and wastage)} @ 0.102 kg/m |
| 66 | Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 67 | Spiral PVC Spacer |
| 68 | Aluminium Paint |
| 69 | Add Erection charges for Cond. complete in all respect |
| 70 | Add Transportation charges complete in all respect |
| 71 | Add Erection charges for Cable complete in all respect Quantities are mentioned above are tentative and Actual Quantity shall be worked out after Check Survey to be carried out by the successful Tender and detailed Engineering and finalization of Tower location Chart.Payment shall be made as per Approved Bill of Material/Actual Quantities measured at site. Please Enable Macros to View BoQ information |