| 1 | HSR Items |
| 2 | [11.5.2]12 mm cement plaster of mix : 2. 1:3 (1 cement: 3 fine sand) [Through Rate] |
| 3 | [20.91]Providing and Lowering 225 mm outer dia UPVC pipe threaded (10kg/CM2) duly ISI marked IS Code 12818:1992 complete in all respect as per directions of Engineer-in-charge [Through Rate] |
| 4 | [20.94]Providing and fixing UPVC cap for 225mm outer dia UPVC pipe (10kg/cm2) duly ISI marked IS Code 12818:1992 complete in all respect as per directions of Engineer-in-charge [Through Rate] |
| 5 | [21.95.7]Providing lowering cutting jointing and testing RCC pipe class NP3 as per IS-458-2003 with spigot and socketed joints manufactured with ISI marked sulphate resistance cement as per ISI 12330 with rubber rings ISI marked antiternmite as required at site in to trenches for all depths and laying out the same to correct alignment gradients and levels including dressing and trimming and cutting of concrete beds and side of trenches, if required jointing with rubber rings in trenches and jointing with 1:3/2 cement sand mortar and with end dowels filled with 1:3/2 cement sand mortar and finishing the joints at an angle of 45 degree with faces of spigot of socket joints cutting and finishing the cut surface to a uniform finish etc. as fully described in item No. 21.38, item 21.44, item 21.45, and item 21.46 including cartage loading and unloading complete in all respects. the internal diametric of the sewer being: 7. 800 mm [Through Rate] |
| 6 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 7 | [6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 8 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 9 | [6.29.1]Centering and shuttering including strutting, propping etc. and removal of form work for : 1. Foundations, footings, bases for columns [Through Rate] |
| 10 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more [Through Rate] |
| 11 | [7.21.3]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 3. Cement mortar 1:3 (1 cement : 3 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |