| 1 | Restoration & strengthening of bank and daowla in all type of soil mixed with chharry, karail, black cotton soil including all lead & lift with manual compaction dressing and T&P etc. required for proper completion of the work. |
| 2 | Earth work in excavaion of foundation in ordinary soil/sandy loam, clay or sand including lift up to 1.50m and lead up to 30M including filling, watering, ramming of excavated eart into the foundation trenches or plinth or upto the place directed by engineer in charge. |
| 3 | Preparation of Sub-grade for Lining excluding cost of earth work. |
| 4 | Laying .C.C.(1:3:6) with coarse sand ,cement, stone, ballast 20mm to 40mm in size in foundation including cost of all material, labour, T&Petc. |
| 5 | C.R.Stone masonry in 1:3 cement sand mortar including cost of all material for proper completion of work. |
| 6 | Deep struck cement pointing in 1:2 cement, sand mortar on stone masonry including cost of all materials labour T&P etc. |
| 7 | Providing and laying C.C.(1:1.5:3)with coarse sand cement and 10 mm to 20mm crushed stone grite including cost of material, labour, T&Petc. proper completion of work as per direction of Engineer-in-charge. |
| 8 | Colour washing of two coat of parapet including cost of all materials,labour and T&P etc. |
| 9 | Fixing wheel guard stone inclding cost of all of all materials, labours and T&P etc. |
| 10 | E/W in embankment for restoration of canal section on VRB nearby in all type of soil mixed including all lead, lift dressing etc. |
| 11 | Providing superviser for watching and warding of work as per direction of Engineer in charge. |
| 12 | C.C 1:2:4 on D/S floor and top of crest including cost of all materials labour T&P etc. |
| 13 | 1st class brick masonry in 1:3 cement sand mortar including cost of all material for proper completion of work. |
| 14 | Providing and fixing of 150 mm dia HDPE 6 kg/m² pressure Pipe Avg. = (12.00+8.00)/2= 10.00 |
| 15 | Cement pointing in 1:2 cement, sand mortar on brick masonry including cost of all materials labour T&P etc. required for praper for completion of work. |
| 16 | Fixing of RCC Precast Boundry piller including cost of all materials, labour and T&P etc. required for proper completion of work as per direction of Engineer-in-Charge. |
| 17 | Supply and placing of steel reinforcement including cost of material, labour, T&P etc. Proper completion of work as per direction of Engineer-in-Charge. |
| 18 | Centering and shuttering of RCC Precast boundry piller size 300x300x1650 (mm) including cost of material, labour, T&Petc. proper completion of work as per direction of Engineer-in-charge. |
| 19 | Painting of RCC Precast boundry piller size 250x250x1650 (mm) including cost of material, labour, T&Petc. proper completion of work as per direction of Engineer-in-charge. Please Enable Macros to View BoQ information |