| 1 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil : including all leads, lift and carriage complete |
| 2 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed: All kinds of soil :1 meter from cutting edge |
| 3 | Providing & laying stone Agg. Using 40 mm n/s Agg. |
| 4 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 5 | Dry random rubble masonry with hard stone in foundation and plinth Without bond stone including all leads, lift and carriage complete |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns etc. for mass concrete. |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for: 2 Walls (any thickness) attached pilasters, buttresses, plinth and string courses etc. |
| 8 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. including all leads, lift and carriage complete |
| 9 | Construction of CIB (includes concrete Pedestrial/Brick 3*2, Plastering,Painting complete job as per direction of Engineer in charge |
| 10 | Carriage of Cement from an avg. distance of 20 KM by MT & 500 Meter by AT. |
| 11 | Carriage of sand from an avg. distance of 65 K.M by MT & 500 Meter by AT. |
| 12 | Carriage of s aggregate & sand from an avg. distance of 65 K.M by MT & 500 Meter by AT. |
| 13 | Carriage of stone from an avg. distance of 0 K.M by MT & 600 Meter by AT. Please Enable Macros to View BoQ information |