Name of Work:- Estimate for laying of U/G RCC Pipeline Outlet RD 74080/L of Sanaur Disty.
Sl. No.
Item Description
1
Earth work in excavation in foundations trenches etc. in all kinds of soil where Pick-Jumper work is not involved and not exceeding 2.0 metres depth including dressing of bottom and sides of trenches, stacking the excavated soil clear from the edge of excavation and subsequent filling around masonry in 15 cm, layers with compaction including disposal of all surplus soil as directed within lead of 30 metres.
2
First class brick masonary 229 mm thick laid in cement sand mortar 1.6 in foundation and plinth including supply recarriage of bricks cement .
3
10mm thick cement plaster 1.4 on sides walls (-) Rs.1.25/- for scaffolding.
4
10mm thick cement plaster 1:4 on bed and top.
5
Reinforced cement concrete 1:2:4 hand mixed but including steel reinforcement
6
Cement Conc.1:2:4 including supply, carriage & with stone ballast or shingle
7
Cement concrete 1:4:8 with brick ballast 40mm gauge
8
Lowering, jointing of RCC NP-2 plain end pipes 400 mm dia laying same to correct gradient and alignment and jointing ends and fixing collars with cement mortar 1:2 as per IS 458:2003 in all depths complete in all respect. Plain End
9
Jointing and cutting of RCC NP-2 plain end pipes 150 mm dia for vent pipe into Trenches and laying same to correct alignment as per IS 458:2003 ( @2.50 metre / No)
10
Wrought Iron and mild steel ladders, framed grills, grating etc. complete fixed in position in D-tank
11
Providing & fixing M.S. foot rests made of 23x25 mm square bar including fixing in Haudis complete with cement concrete 1:2:4
12
Providing and fixing of Alfa Alfa Valve fitted on riser pipe to act as Nakka (D regulators)
13
Centreing & Shuttering for Concerte faces
14
Providing & Fixing of Steel Shutter Gate Assembly in Main Pipeline complete in all respect
15
Excavation by mechanical means (JCB or hydraulic excavation) in trenches for pipeline with straight or open cutting in streets or open area including dressing sides levelling of beds of tranches to correct grade, cutting joint holy, refiling consolidation including the cost of diversion for traffic crossing over trenches for across to houses watching fencing etc. and removal of surplus soil outside inside the town involving lead up to 15 m complete in all respect. Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.