| 1 | PART - A Construction Work |
| 2 | Construction of Embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirment of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 (GSTshall be paid extra as per applicable) |
| 3 | (A) By Mix in Place MethodConstruction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MORD Technical Speicification Clause 401 (GSTshall be paid extra as per applicable) |
| 4 | Providing, laying and spreading WBM Graded material on a prepared sub base, cement @ 4% by weight to the spread material manualy, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub base. as per MORD Technical Speicification Clause 401(GSTshall be paid extra as per applicable) |
| 5 | Providing and applying tack coat with Bitumen (VG-10) using bitumen pressure distributor @ 0.35 kg/sqm on the prepared bituminous surfaces as per Technical Specification Clause 503. (GSTshall be paid extra as per applicable) |
| 6 | Providing laying and rolling of open-graded premix carpet of 20 mm thickness, composed of 13.2 mm to 5.6 mm aggregates and using Bitumen VG-10, to required line, grade and leval to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller, finished to required level and grades to be followed by seal coat as per Technical Specification Clause 508. (GSTshall be paid extra as per applicable) |
| 7 | Providing and laying seal coat type C, composed of as chipping of 6.7mm size passing 100% passing 9.5 mm sieve and retained on 2.36 mm sieve and VG-10 Bitumen, to seal the voids in a bitumenous surface, including its mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller, finished to required level, grades and cross fall, as per Technical Specification Clause 508. (GSTshall be paid extra as per applicable) |
| 8 | Construction of Subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads trasportion to site spreding grading to required slope and compacted to meet requirement of Table 300.2 as per Technical specification Clause 303.1 (3.14) (GSTshall be paid extra as per applicable) For Patri work |
| 9 | Earthwork in excavation for structures as per drawing and technical specification clause 305.1 including setting out,, construction of shoring and bracing ,removal of stums and other deleteriousb material and disposal upto a lead of 50m dressing of sides and bottom and backfilling in trenches with excavated suitable material. as per MORD Technical Speicification Clause 3.2(ii)(GSTshall be paid extra as per applicable) |
| 10 | Providing and laying of compacted 40mm Gauge brick ballast around and below hume pipe as per Sor mateial item SI no-2A (GSTshall be paid extra as per applicable) |
| 11 | Provinding concrete for plain /reinforced concrete in open foundationcomplete as per drawings and technical specification clauses 802,803,1202&1203. (GSTshall be paid extra as per applicable) |
| 12 | Brick masonary work in cement mortar in foundation complete exluding pointing and plastering as per drawing and technical specification clouses 600,1202,&1203. (GSTshall be paid extra as per applicable) |
| 13 | Pointing with cement mortar (1:3) on brickwork as per drawing and technical specification clauses 613.3 and 1204. (GSTshall be paid extra as per applicable) |
| 14 | Providing and laying RCC hume pipes NP-3 600mm dia ,including collars /Spigoted type joint conmforming to BIS specification As per IS 458:2003.As per SOR material item SI no-60.(GSTshall be paid extra as per applicable) |
| 15 | Maintenance of constructed road for next five year after completion of work shall be paid. as per GO No 17/2024/lk0-113/23-1-2024-23-1099-113/2023 yksd fuekZ.k foHkkx vuqHkkx&1 fnuakd 16-01-2024 ,oa dk;kZy; izeq[k vfHk;Urk ;krk;kr oxZ yks0fu0fo0 y[kuÅ dk i=kad&3689lh&vks0ih0vkj0,e0lh0@ewy&23&24 fnuakd 17-02-2024- Payment shall be done as per satisfaction of engineer in chage regarding maintenance work carried out by contractor (Including Labour Cess but GST will paid extra as applicable). 1st year Maintenance cost total construction of cost Part 1 & 2 Rs 7530039.80 @ Zero percent & for 2nd year @ 0.75% |
| 16 | For 3rd year @ 1.50% |
| 17 | For 4th year @ 2.25% |
| 18 | For 5th year @ 3.00% Please Enable Macros to View BoQ information |