| 1 | Supply of 110kV Feeder (OH+UG) Control and Relay Panel (Simplex) with annunciator(Not less than 24 Window) suitable for existing AIS 110kV bays compatible to SAS( IEC 61850 Uptodate and amendment to Edition 2) having elegant and compact design with Main 1 and Main 2 protection(different make) comprising of Line differential 87L (for both ends along with chanel) with back up Distance 21 protection and Back up protection(67&67N) with Electrically resettable Master trip/Lock out(86) relays, LBB Trip relay(50BF), Trip circuit Supervision relays, Auxiliary relays, DC supervision relays, VT selection relays, Sup.Relays, DC changeover relays, Energy meter (0.2S class,Optical, 2 nos of RJ45 DLMS port (TCP/IP configurable )), TNC switch, Emergency Shutdown Push button, IED reset button, Master trip reset button, Synchronizing socket, Test Terminal block, AC socket with switch and , DC Source Selection Switch, Multi function meter for Voltage and Current ,carrier in/out manual switch and BCU ( IEC 61850 Uptodate and amendment to Edition 2), ethernet switches and LIU 2 cable entry and adequate ports as per specification (including testing and commisssioning). All panels shall be front entry/rear entry/swing framed decided as per site requirement and BCC layout attached with adequate working space inside for Testing/maitenance works. |
| 2 | Supply of Control and Relay Panels for 110kV side of 110/11kV 20MVA and 110/33kV 16MVA Transformers compatible to SAS (1EC61850 uptodate amendment to Edition 2,) having elegant and compact design with Main 1 and Main 2 protection comprising of Differential Protection, REF Protection, Back up protection, Master trip relays, Trip circuit Supervision relays, Auxiliary relays (for main and OLTC Buchholz, WT/OT trip, Tap changer out of step , PRD 1&2 through high impedance tripping relays, MOLG alarms etc. ), DC supervision relays , VT selection relays, DC changeover relays, Energy meter (0.2S class,Optical, 2 nos of RJ45 DLMS port (TCP/IP configurable )) Test Terminal block, AC socket with switch and emergency TNC switch, BCU (1EC61850 uptodate amendment to Edition 2), ethernet Switch (20% spare ports) and LIU with 2 cable entry and adequate ports not less than 12 ports as per specification and provision for microprocessor based numerical RTCC unit. All panels shall be front entry/rear entry/swing framed decided as per site requirement and BCC layout attached with adequate working space inside for Testing/maitenance works. |
| 3 | Supply of 110kV Bus coupler Control and Relay Panel with annuaunciator(Not less than 24 Window) compatible to SAS (IEC61850 an update and amendment Edition 2 ) having elegant design with in single panel comprising of O/C & E/F Protection numerical relay, Master trip relays,Trip circuit Supervision relays, Auxiliary relays( Breaker failure Inter trip, LBB,Busbar trip), DC supervision relays , DC changeover relays, AC socket with switch, emergency TNC switch, reset button, Synchro Check relay (25),adequate illumination and including BCU (1EC61850 uptodate amendment to Edition 2), ethernet Switch (20% spare ports) and LIU with 2 cable entry with adequate ports not less than 12 ports as per specification. All panels shall be front entry/rear entry/swing framed decided as per site requirement and BCC layout attached with adequate working space inside for Testing/maitenance works. |
| 4 | Supply of 110kV Bus Bar Protection Panel (For 8 Nos of 110kV feeders & 4 Nos of Transformer 10kV side bays ) compatible to SAS an update and amendment to IEC 61850 Edition 2 having elegant and compact design comprising of zone segragate tripping, local HMI for displaying differential current, SLD, isolator position etc, with output tripping relays(drawn out type),Busbar, LBB & Back up Protection, Auxiliary relays, DC supervision relays, IN/OUT switches (Lockable), Test terminal Block, AC socket with switch, adequate illumination as per specification(including testing and commissioning) .All panels shall be front entry/rear entry/swing framed decided as per site requirement and BCC layout attached with adequate working space inside for Testing/maitenance works. |
| 5 | Supply of Control cables and LT AC/DC power cables (PVC/FRLS) of suiltable sizes as per specification from AIS equipments to 110kV Feeder C&R Panel in BCC room as per specification. (Armoured / Unarmoured as per specification) including GI cable support and ladder type trays. |
| 6 | Supply of Control cables and LT AC/DC power cables(PVC/FRLS) of suiltable sizes as per specification from AIS equipments to 110kV transformer C&R Panel in BCC room as per specification. (Armoured / Unarmoured as per specification) including GI cable support and ladder type trays. |
| 7 | Supply of Control cables and LT AC/DC power cables(PVC/FRLS) of suiltable sizes as per specification from AIS equipments to 110kV Bus coupler C&R Panel in BCC room as per specification. (Armoured / Unarmoured as per specification) including GI cable support and ladder type trays. |
| 8 | Supply of Control cables and LT AC/DC power cables(PVC/FRLS) of suiltable sizes as per specification from equipments to LT AC/DC panels, battery, battery charger, 11kV and 33kV SWGR panels, RTU panel, MLDB,ELDB etc in the newly built control room to Auxiliary BCU panels as per specification. including GI cable support and ladder type trays. (Armoured / Unarmoured as per specification) |
| 9 | Supply of Control cables and LT AC/DC armoured power cables(PVC/FRLS) of suiltable sizes as per specification from AIS equipments to 110kV Busbar protection C&R Panel(10 bays) as per specification.(Armoured / Unarmoured as per specification) including GI cable support and ladder type trays. |
| 10 | Supply and Installation of Complete SAS system for 110kV Viyyur AIS Substation as per detailed technical specification, SAS Architecture and SLD, Redundant Servers (2 nos), Redundant Gateways (2 nos), Redundant Routers (2 nos) with hardware firewalls, 2nos operators workstation (one operating workstation with extended up to 200 meter HMI), 2 nos Engineering workstation (laptop and desktop), one metering PC with adequate number of DCU for accessing meter data with DLMS protocol metering and telemetry with all necessary accessories reporting analysing software , cables, converters, GPS based Time synchronising unit IEC compatible to cater data to and from all bays and transformers, SCADA compatible panels, interfacing/integrating protection relays feeders , transformers and busbar) in CR panel, SAS gateway server panel with remote station controls, Network panels ,RTCC , AC/DC System etc… to FODP/communication equipments in communication room as per specification including supply of all necessary converters for interfacing with communication equipment, unarmoured OF cable, 40mm PLB HDPE pipe duct, all interconnecting cables Patch chords devices etc. including mandatory spares as per specification in Annexure including supply of configuration software tools for SAS , Relays and Network Swiches. LAN accessories, FO Cables (including perforated tray and HDPE pipe), NAS(2 TB). Details a Given Below:• GPS server & Antenna, • GPS Clock, • SAS / Server panel, • SAS software, • DR / Engineering workstation with monitor (1 No), • Engineering workstation Laptop (1 No),• Metering PC (1 No), • HMI Opertartor workstation with monitor (2 nos.), • HMI Display 50\\" (1 nos.), • HDMI KVM Swich with range 200m and optical cable (1 nos.), • Ethernet switches (6 nos.), • Gateway (2 nos.), • Invertor with battery (4kVA) - 2 Nos, Static bypass switchs for inverters and Auxiliary AC supply, • Routers (2 nos.), • A3 printer (Colour Laser jet), • Chair high backup (4 nos.), • Workstation desk ,• Printer stand, • Storage Cabinet ( 2 steel almirah). |
| 11 | Supply of Bay Control Unit (for auxiliary functions) as per technical specification- Quantity to be estimated as per the design and sum of total quantity may be indicated as single unit |
| 12 | Supply of panel for mounting Bay Control Units (for auxiliary functions) as per technical specification. |
| 13 | Supplying Mandatory Spares for SAS and C&R panels (separate breakup details to be submitted) |
| 14 | Erection, Installation, Integration, Testing and commissioning of 110kV Feeder Control and Relay Panel (Simplex) with annunciator suitable for existing AIS 110kV bays compatible to SAS( IEC 61850 Uptodate amendment to Edition 2) having elegant and compact design with Main 1 and Main 2 protection(different make) comprising of Line differential 87L (for both ends along with chanel) with back up Distance 21 protection and Back up protection(67&67N) with Electrically resettale Master trip/Lock out(86) relays, LBB Trip relay(50BF), Trip circuit Supervision relays, Auxiliary relays, DC supervision relays, VT selection relays, Sup.Relays, DC changeover relays, Energy meter (0.2S class,Optical, 2 nos of RJ45 DLMS port (TCP/IP configurable )), TNC switch, Emergency Shutdown Push button, IED reset button, Master trip reset button, Synchronizing socket, Test Terminal block, AC socket with switch and , DC Source Selection Switch, Multi function meter for Voltage and Current ,carrier in/out manual switch and BCU ( IEC 61850 Uptodate amendment to Edition 2),ethernet switches and LIU as per specification |
| 15 | Erection,Installation, Integration,Testing and commissioning of Control and Relay Panels compatible to SAS (IEC 61850 uptodate amendment to Edition 2) for 110kV side of 110/11kV, 20MVA and 110/33kV, 16MVA Transformers having elegant and compact design with Main 1 and Main 2 protection (different make)in single panel comprising of Differential Protection, REF Protection, Back up protection, Master trip relays, Trip circuit Supervision relays, Auxiliary relays (for main and OLTC Buchholz, WT/OT trip, Tap changer out of step , PRD), DC supervision relays , VT selection relays, DC changeover relays, Energy meter(0.2S class,Optical, 2 nos of RJ45 DLMS port (TCP/IP configurable )), Test Terminal block, AC socket with switch and emergency TNC switch, BCU (IEC 61850 uptodate amendment to Edition 2), ethernet Switch and LIU as per specification. |
| 16 | Erection, Installation, Integration,Testing and commissioning of of 110kV Bus coupler Control and Relay Panel (Simplex) with Announciator compatible to SAS (IEC 61850 uptodate amendment to Edition 2) having elegant design with in single panel comprising of O/C & E/F Protection numerical relay, Master trip relays,Trip circuit Supervision relays, Auxiliary relays( Breaker failure Inter trip, LBB,Busbar trip), DC supervision relays , DC changeover relays, AC socket with switch, emergency TNC switch, reset button, Synchro Check relay (25),adequate illumination and including BCU (1EC61850 uptodate amendment to Edition 2), ethernet Switch and LIU as per specification. (including testing and commisssioning) The panel doors to be provided in the Rear side of panel with adequate working space inside for Testing/maitenance works. (including testing and commisssioning) |
| 17 | Erection, Installation,Integration,Testing and commissioning of of 110kV Bus Bar Protection Panel having elegant and compact design comprising of zone segragate tripping, local HMI for displaying differential current, SLD, isolator position etc, with output tripping relays(drawn out type), Busbar, LBB & Back up Protection, Auxiliary relays, DC supervision relays, IN/OUT switches (Lockable), Test terminal Block, AC socket with switch, adequate illumination as per specification (including testing and commisssioning) The panel doors to be provided in the Rear side of panel with adequate working space inside for Testing/maitenance works. |
| 18 | Laying of control, LT/Power cables through trench/pipe/cable tray neatly and carefully including for providing loops wherever necessary and cable marker at both ends of cable, existing contol, glanding and termination providing number and letter ferrules in the wires of all cables for control, protection, status and metering from AIS equipments to newly erected SAS compatible 110kV Feeder C&R Panel at BCC as per scheme requirement and as per direction of departmental staff at site. Cost of all accessories such as glands copper lugs, ferrules,cable marker etc except control cable /LT AC DC cable included in this item.(Erection of cable trays of various size withall accessories including earthing of trays with the GI earth strip provides by KSEBL in the trenches from AIS to LCC/MK & LCC/MK to control panel and to where ever necessary for the complete control cabling work as part of implementation of SAS/ Control & Protection.) |
| 19 | Laying of control, LT/Power cables through trench/pipe/cable tray neatly and carefully including for providing loops wherever necessary and cable marker at both ends of cable, existing contol, glanding and termination providing number and letter ferrules in the wires of all cables for control, protection, status and metering from AIS equipments to newly erected SAS compatible 110kV Transformer C&R Panel at BCC as per scheme requirement and as per direction of departmental staff at site. Cost of all accessories such as glands copper lugs, ferrules,cable marker etc except control cable /LT AC DC cable icluded in this item.(Erection of cable trays of various size withall accessories including earthing of trays with the GI earth strip provides by KSEBL in the trenches from AIS to LCC/MK & LCC/MK to control panel and to where ever necessary for the complete control cabling work as part of implementation of SAS/ Control & Protection.) |
| 20 | Laying of control, LT/Power cables through trench/pipe/cable tray neatly and carefully including for providing loops wherever necessary and cable marker at both ends of cable, existing contol, glanding and termination providing number and letter ferrules in the wires of all cables for control, protection, status and metering from AIS equipments to newly erected SAS compatible 110kV Buscoupler C&R Panel at BCC as per scheme requirement and as per direction of departmental staff at site. Cost of all accessories such as glands copper lugs, ferrules,cable marker etc except control cable /LT AC DC cable icluded in this item. (Erection of cable trays of various size withall accessories including earthing of trays with the GI earth strip provides by KSEBL in the trenches from AIS to LCC/MK & LCC/MK to control panel and to where ever necessary for the complete control cabling work as part of implementation of SAS/ Control & Protection.) |
| 21 | Laying of control, LT/Power cables through trench/pipe/cable tray neatly and carefully including for providing loops wherever necessary and cable marker at both ends of cable, existing contol, glanding and termination providing number and letter ferrules in the wires of all cables for control, protection, status and metering from AIS equipments to newly erected SAS compatible from equipments like LT AC/DC panels, battery, battery charger, 11kV and 33kV SWGR panels, RTU panel, MLDB,ELDB etc in the newly built control room to Auxiliary BCU panels as per specification. (Erection of cable trays of various size withall accessories including earthing of trays with the GI earth strip provides by KSEBL in the trenches from AIS to LCC/MK & LCC/MK to control panel and to where ever necessary for the complete control cabling work as part of implementation of SAS/ Control & Protection.) |
| 22 | Laying of control, LT/Power cables through trench/pipe/cable tray neatly and carefully including for providing loops wherever necessary and cable marker at both ends of cable, existing contol, glanding and termination providing number and letter ferrules in the wires of all cables for control, protection, status and metering from AIS equipments to newly erected SAS compatible 110kV Busbar protection C&R Panel(2Nos) at BCC as per scheme requirement and as per direction of departmental staff at site. Cost of all accessories such as glands copper lugs, ferrules,cable marker etc except control cable /LT AC DC cable icluded in this item. (Erection of cable trays of various size withall accessories including earthing of trays with the GI earth strip provides by KSEBL in the trenches from AIS to LCC/MK & LCC/MK to control panel and to where ever necessary for the complete control cabling work as part of implementation of SAS/ Control & Protection.) |
| 23 | Integration,Testing and commissioning of Complete SAS system for 110kV Viyyur AIS Substation as per detailed technical specification, SAS Architecture and SLD, Redundant Servers (2 nos), Redundant Gateways (2 nos), Redundant Routers (2 nos) with hardware firewalls, 2nos operators workstation (one operating workstation with extended up to 200 meter HMI), 2 nos Engineering workstation (laptop and desktop), one metering PC with adequate number of DCU for accessing meter data with DLMS protocol metering and telemetry with all necessary accessories reporting analysing software , cables, converters, GPS based Time synchronising unit IEC compatible to cater data to and from all bays and transformers, SCADA compatible panels, interfacing/integrating protection relays feeders , transformers and busbar) in CR panel, SAS gateway server panel with remote station controls, Network panels ,RTCC , AC/DC System etc… to FODP/communication equipments in communication room as per specification including supply of all necessary converters for interfacing with communication equipment, unarmoured OF cable, 40mm PLB HDPE pipe duct, all interconnecting cables Patch chords devices etc. including mandatory spares as per specification in Annexure including supply of configuration software tools for SAS , Relays and Network Swiches. LAN accessories, FO Cables, NAS(2 TB) |
| 24 | Erection,Installation,Integration,Testing and commissioning of bay control unit in suitable panel(for auxilliary functions) as per technical specification- Quantity to be estimated as per the design and sum of total quantity may be indicated as single unit |
| 25 | Training for the Operation and Maintenance of the substation to the KSEBL Engineers and Staff Include cost of travelling , boarding and lodging food etc. ( 360 man hrs required for SAS and Relays ).Unit job is measured in man hour |
| 26 | Design, manufacture, transportation, installation, testing and commissioning of Remote Terminal Unit (RTU) at 33kV and 11kV indoor panels ( to control 33kV & 11kV switch gears ) and is to be controlled from HMI in the C&R room as per the general specifications including necessary items forAnalog inputs, Status inputs, Outputs from IEDs(61850 protocol), Control output, Accumulator input, GPS and any other external alarm and/or ivent inputs, Network switches, control PC, HMI and FO cable for interconnection.The necessary ethernet to FO convertor shall be provided by the bidder. The RTU ofered shall have sufficient capacity, in all means to provide SCADA for both 11kV and 33kV Switchgears offered. Please Enable Macros to View BoQ information |