| 1 | Earth Work in cutting/filling in ordinary soil including dressing and ramming of bottom etc all comp |
| 2 | Earth Work in Excavation for foundation in silty/malva/garbeg soil including dressing and ramming of bottom an disposal of surplus excavated earth as directed by engg |
| 3 | Providing and laying P.C.C. 1:4:8 (cement,coarse sand, 40mm gauge stone ballast) etc all complet. |
| 4 | R.C.C. work with cement approved coarse sand and 20 mm gauge approved stone grit in the proportion of 1:2:4 in for column footing excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour and t & P etc. required for proper completion of the work. Binding wire cost being included in the item |
| 5 | R.C.C. work with cement approved coarse sand and 20 mm gauge approved stone grit in the proportion of 1:2:4 in for column excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour and t & P etc. required for proper completion of the work. Binding wire cost being included in the item |
| 6 | R.C.C. work with cement approved coarse sand and 20 mm gauge approved stone grit in the proportion of 1:2:4 in for Beam excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour and t & P etc. required for proper completion of the work. Binding wire cost being included in the item |
| 7 | R.C.C. work with cement approved coarse sand and 20 mm gauge approved stone grit in the proportion of 1:2:4 in for slab excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour and t & P etc. required for proper completion of the work. Binding wire cost being included in the item |
| 8 | Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not included in overall rates) wrought to required shape as necessary including bending for proper completion of the workl and including supply of steel its watages etc all complet |
| 9 | M-150 class Brick work over base concreate in Cement Mortar 1:3 including all material, labour, T&P etc.in supper strucher etc all complet. SI NO. 307 |
| 10 | Pro & laying 25 mm thick D.P.C work is 1:2:4 cement, c/sand, s/grite with composil powder etc all complet. SI NO.361 |
| 11 | M-150 class Brick work over base concreate in Cement Mortar 1:3 including all material, labour, T&P etc.in supper strucher etc all complet.SI NO. 314(5) |
| 12 | 20 mm thick Plaster with 1:2 mix (cement& C/sand mortor ) wt floting coatith neat finish 3 mm cemen etc all complet . |
| 13 | 15 mm thick Plaster with 1:3mix (cement& C/sand mortor ) wt floting coatith neat finish 3 mm cemen etc all complet . |
| 14 | 40 mm. thick C.C. flooring 1: 2: 4 plain cement concrete floor with cement, approved coarse snad and 20mm. Graded approved stone laid in panels finished with 3 mm. Floating coat of neat cement or cement and marble dust in 5 : 1 as specified over and including 75mm thk. base concrete consisting of cement, local sand and brick ballast 40mm guage in the proportion of 1:4:8 and removing any over lapping mortar at the joints of the panel if any and giving them a uniform finish including supply of all materials, labour and T&P etc.required for proper completion of the work. |
| 15 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete |
| 16 | Finishing walls with water proof cement paint of approved make and quality on new work with three coats to give an even shade i/c supply of all material , labour and t&p etc.required for proper completion of work. S.I.13.46,1 |
| 17 | Cartage of earth up to 4.0 km distance loding and unloding charge including etc all complet. |
| 18 | Mild steel or iron work of heavy size and sections such as trusses, built up gates, door frames etc. wrought to required shape as necessary for bending etc. including supply of steel and its wastage including cost of bolts, nuts if required, welding, grinding and making holes as required for completion of work |
| 19 | Painting 1st coat over priming coat on steel superior synthetic enamel to give an even shade and including cleaning the surface with one coat Priming coat withcost of all materials labour tools and plants etc. required for proper completion of the work. |
| 20 | S/L/R/C of G.S.B. stone grite with water and dust 2.38-6.7 mm gauge consolidation including road roller 8-10 K-N etc all complet. |
| 21 | P/L 80 mm paver Interlocking tiels rabber molded including fine sand coussning and making camber in road etc all complet. |
| 22 | S/f of Name board including frame of b/w ,plaster etc all complet |
| 23 | Add 2% Contengency Please Enable Macros to View BoQ information |