Name of Work:- PAPANASAM BLOCK PUGF 2025-2026. Strengthening of Eravalli Colony Theru Mayanasalai in Thirumandangudi Panchayat Km 0/0-0/616 R-379
Sl. No.
Item Description
1
Strengthening of Eravalli Colony Theru Mayanasalai in Thirumandangudi Panchayat Km 0/0-0/616 R-379
2
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20B
3
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory Soil Compactor to achieve the desired density, complete as per clause 401
4
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
5
Providing and laying 75mm compacted thick WBM Gr.II using 1 cum of 93 mm to 22.40mm IRC metal and 0.24 cum of Gravel for blindage for 10sqm. Of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and consolidation by power roller and finishing has per MoRT&H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental charges etc., complete for top layer.
6
Providing and laying 75mm compacted thick WBM Gr.III using 1 cum of 63 mm to 11.20mm IRC metal and 0.24 cum of Gravel for blindage for 10sqm. Of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and consolidation by power roller and finishing has per MoRT&H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental charges etc., complete for top layer.
7
Providing and laying tack coat over the WBM surface using 4.00 Kg of rapid setting bituminous emulsion for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MoRT&H specification.
8
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 23.232Kg of bitumen and 1.168 Kg of Plastic waste for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
9
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction
10
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.