| 1 | PART-A (Bldg.) |
| 2 | 1.8Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils |
| 3 | 3.1.2 Providing & Laying in position cement concrete i/c curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering – All work up to plinth level.: (A) M15 grade Nominal Mix 1: 2: 4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size). |
| 4 | 5.1.2/B-5Brick masonry with F.P.S. bricks of class designation 75 in foundation and plinth with bricks cement mortar 1:6 (1- cement: 6- coarse sand). |
| 5 | 16.41.5/BProviding and laying at or near ground level factory made kerb stone of M-25 grade cement in position to the required line, level and curvature jointed with cement mortar 1:3 (1 cement : 3 coarse sand ) including making joints with without grooves (thickness of joints except at sharp curve shall not to more than 5mm) including making drainage opening wherever required complete including painting etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be approved by Engineerin- charge). |
| 6 | 14.2.1Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer-in-charge. 1: 3: 6 or richer mix. |
| 7 | 1.1/BEarth work in surface excavation not exceeding 30cm. in depth but exceeding 1.5 meter in width as well as10 Sqm on plan including disposal of excavated earth up to 50 Mtr. and lift up to 1.5 Mtr. disposed soil to be levelled and neatly dressed : All kinds of soil |
| 8 | 12.3.2/B-12Plaster on new surface on walls in cement sand mortar 1:6 including racking of joint etc. complete fine finish: (A) 20mm thick |
| 9 | 12.42/B-12Finishing walls with Acrylic Smooth exterior paint of required shade including all scaffolding New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including base coat of water proofing cement paint applied @ 2.20 kg/ 10 sqm ). |
| 10 | 12.46.1/BPainting with synthetic enamel paint of approved brand and manufacture to give an even shade: (A) Two or more coats on new work. |
| 11 | 9.2/BStructural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting (height upto 10 m) , fixing in position and applying a priming coat of approved steel primer all complete: |
| 12 | 9.38.3/BProviding and fixing welded mesh/expanded metal mesh in frame work, flat iron beading 20x3mm including top cross laps inside and out sides welding, iron bolts, crews, clips etc. complete (excluding frame work) of size.Welded mesh 25 mmx 25 mm x 2.1 mm |
| 13 | PART- B (Item Rate Basis) |
| 14 | Providing and Fixing of Fibre Reinforced Polymer / Plastic (FRP) Fencing for 11/ 0.4 KV transformers or 33KV substations, comprising panels measuring 2.00 meters in height and upto 1.50 meters in length. The fencing shall be in yellow/ green/ pink /grey, as directed by the Engineer-in-Charge (EIC). The fencing includes vertical posts made of 50x50x4 mm hollow square sections with a height of 2.70 meters, grouted in 1:2:4 cement concrete (hold fast sand cement concrete paid separately). Thes pacing between vertical posts shall not exceed 1.5 meters and must be provided at all corners. The mesh consists of 24 mmouter diameter hollow cylindrical sections with a 3mm thickness, placed vertically at 75 mm center-to-center intervals, and a horizontal 40x40mm hollow square section with a 3mm thickness, all enclosed within a 40x40 mm hollow square pipe frame with a 3mm thickness. The panels are secured to the vertical posts using stainless steel bolts. The fencing includes a single entry gate, with a height of 2.00 meters and a width upto 1.50 meters, a spersite requirements, fitted with stainless steel hinges and aldrops. The gate must also feature a screen-printed name plate with \\"JVVNL\\" and a danger sign on an SMC sheet. The vertical posts and panel sections to be manufactured using an automaticpultrusion process, incorporating at least 45% fiber glass reinforcement with in a polyester-based thermosetres in. The material meets the following specifications: heat deflection temperature ≥ 170°C (IS:13411), self-extinguishing flame resistance (IS:4249), and non-melting characteristics (IS:13360), with a density ≥ 2000 kg/m³. The fencing must also be resistant to chemicals, have a high-gloss finish, and be weatherproof to ensure durability in various environmental conditions. The quality must ensure good fit and finish, with proper strength as per the direction of the EIC. The job includes all necessary loading, unloading, transportation, labor, tools, safety equipment, and installation with stainless steel clamps and fasteners (paid separately), completed as per the EIC’s direction. During installation, all safety protocols must be strictly followed, particularly when working near live electrical equipment. The mode of measurement for this fencing will be in the length of fencing . |
| 15 | Disposal of rubbish un-wanted material dismanted material, away from site at appropirate place including all lead and lift, loading unloading, transportation labour etc. As per direction of Engineer in charges. |
| 16 | P/F stainless steel bolts 150mm long threaded at both sides for fastening members of FRP Fencing fastenend with washer and nuts at both side for extra strengthening of fencing wheever required and direction of E/I |
| 17 | Providing and fixing U shape MS Clamp 200mm long 50mm wide and 1mm thick with 2 holes to accomodate fasteners 65mm long along with 2 nos fastener of 65mm in length i/c all material, labour, T&P complete in all respect and direction of E/I |
| 18 | Supply stacking and spreading of graded broken hard stone aggregate free from organic matter including stacking spreading in yard as per standard specifications of size 40 to 63 mm crusher broken including all lead and left transportation labour loading unloading T&P required fro gravelling work as per direction of Engineer in charhes including dressing of ground upto 15cm depth. |
| 19 | Re-arranging of cable loops of 33/11 KV i/c levelling of ground, for gravelling and fencing work around transformer at various locations under JCC circle i/c shifting the cables using safety gears, gloves complete,Shifting work only to be done during shutdownand under the direction of E/I. Please Enable Macros to View BoQ information |