| 1 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 6. Dismantling artificial stone flooring upto 50 mm. thick by carefully chiselling without damaging the base and removing rubbish as directed within a lead of 75 m. a) In ground floor including roof. |
| 2 | BUILDING WORKS(P) SOLING, EDGING AND METALLING??(15)Labour for taking out old soling edging including removing debris. (a) Single flat soling |
| 3 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 4. (A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) |
| 4 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 2. Labour for laying single brick flat soling including ramming and dressing bed to proper level and filling joints with powdered earth. |
| 5 | BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 6 | ORDINARY CEMENT CONCRETE ( MIX 1:2:4 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES |
| 7 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. |
| 8 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (a) In foundation and plinth |
| 9 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. I. HORTICULTURE: 3.Spreading of sludge, dump manure,/farm yard manure/animel dung manure and good earth in required thickness. This includes supply of labour, tools & plants excluding materials. |
| 10 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 15 Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m. |
| 11 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc?36...Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor).(When the height of a particular floor is more than 4 m the equivalent floor height shall be taken as 4 m and extra for works beyond the initial 4 m ht. shall be allowed under 12 (e) for every 4 m or part thereof).(a) 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-In-Charge.Notes:- For shuttering in shell roof, grid roof with vertical faces folded plate, arched roof the rate in 36 (a), 36 (b) & 37 (c ) of subhead B above to be increased by 100 % . For grid roof with splayed faces, rate is to be increased by 150%. |
| 12 | ORDINARY CEMENT CONCRETE ( MIX 1:1.5:3 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES (BASED ON PWD SCHEDULE OF RATES, W.E.F. 01.11.2017 WITH CORRIGENDA DT.04.06.2018) |
| 13 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. |
| 14 | SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(20)Supplying, fitting and fixing yard gully with approved H.C.I. grating complete. (i) 225 mm X 150 mm with 230 mm gratings |
| 15 | (C) III: Labour Rate for Sanitary and Plumbing 4.Methor Mazdoor NOTE:The above rates are exclusive of 10 % profit and 1% Labour welfare cess, which would be admissible to the Contractor, but contractual percentage will not be applicable on the above rates.Page 113 of 124 |
| 16 | Sub Total |
| 17 | GST 18% |
| 18 | CESS 1% Please Enable Macros to View BoQ information |