| 1 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. |
| 2 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete (b) Depth of excavation for additional depth beyond 1,500 mm. and upto 3,000 mm. but not requiring shoring |
| 3 | Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where necessary, curing with water as per direction, mending cracks and depressions by ramming wherever necessary.Note:- Add cost at site of the materials to arrive at the complete rate. The compaction factor for dry, clean sand may be taken as 0.835. (The payment is to be made on the basis of finished compacted volume).(c) For Silver Sand ( Ref :PWD (Rds & Brdgs)-2018, It. No. 4.05 Page No.245 & page-222 sl. No-4) |
| 4 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( Ref :PWD (Bldg.)-2017, It. No. 1, Page No.14 & 3rd Corrigenda Addenda dtd-04.06.18,P-1) |
| 5 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. (i) Pakur Variety ( Ref :PWD (Bldg.)-2017, page-26 (item -10(i), consumption chart pg-B-60, sl-3 and Annexture-II , Format-A, 3rd Corrigenda & addenda p-13 dtd-04.06.2018, PWD(R&B) 2018, Chapter-1, pg-227 I-1.03, pg-230,Table-I , Table III-2 pg-226, ) |
| 6 | Supplying ready mixed concrete of M 25 Grade with well graded stone chips of 20 mm nominal size containing designed quantity of cement per Cu.m of wet concrete produced in computerised batching plant under controlled condition using approved super plastisizer, designing concrete mix following I.S. 10262 and I.S. 456, transporting the mix with agitation in transit mixer to work site depositing the mix on a platform erected for the purpose at required levels of concreting and then placing the mix in its final location of form work compacting and curing the same complete as per specification & direction of the Engineer-in-charge including computerised batching plant transit mixer with all accessories vibrators etc. inclusive of all other incidental charges in this connection complete but excluding cost of hire charge of platform and its supporting staging which would be paid through separate item. [cement to be supplied by the Manufacturer/ supplier]. In Ground Floor and Foundation(i) Without approved concrete pump ( Ref :PWD (Bldg.)-2017, It. No. 18, Page No.32 & 3rd Corrigenda Addenda dtd-04.06.2018, p-15 & 16, PWD(R&B) 2018, Chapter-1, pg-227 I-1.03, pg-230,Table-I , Table III-2 pg-226, ) |
| 7 | Hire and labour charges for 5 cm. thick close timbering with planks battens, runners struts etc. complete removing them incl. penetration of shoring as per direction of the Engineer-in-Charge. (Vertical surface of contact area with supporting earth to be measured, payment for penetration will not be allowed) b) Beyond 2.0 M. and upto 4.0 M. trench width depth upto 6.0 M. below G.L |
| 8 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge. ( Ref :PWD (Bldg.)-2017, It. No. 13, Page No.12) |
| 9 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. ( Ref :PWD (Bldg.)-2017, It. No. 40, Page No. 43 Annexture-I , Format-B, & 2nd Corrigenda Addenda dtd-04.06.2018, p-1,2, I-43) |
| 10 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc?36...Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor).(When the height of a particular floor is more than 4 m the equivalent floor height shall be taken as 4 m and extra for works beyond the initial 4 m ht. shall be allowed under 12 (e) for every 4 m or part thereof).(a) 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-In-Charge.Notes:- For shuttering in shell roof, grid roof with vertical faces folded plate, arched roof the rate in 36 (a), 36 (b) & 37 (c ) of subhead B above to be increased by 100 % . For grid roof with splayed faces, rate is to be increased by 150%. |
| 11 | First class Brick work in cement sand mortar in steining of well, pier, abutment, wing wall, parapets cross drain. H.P. culverts, guard wall etc. including curing, scaffolding, raking out joints etc. complete including cost and carriage of all materials.(a) In 1:4 proportion. ( Ref :PWD (Rds & Brdgs)-2018, It. No. 18.06, Page No. 332, page-222 sl-5 (a), pg-B-49 sl-19) |
| 12 | ERECTION OF BAMBOO FENCING WITH STRONG BAMBOO POST (75MM DIA), RUNNERS (HALF SPLIT OF 75MM DIA BAMBOO) AND VERTICALS, BRACINGS AND OTHERS (QUARTER SPLIT OF 100MM DIA BAMBOO) INCLUDING CUTTING, FINISHING, FIXING WITH NAILS ETC. AND FIXING OF POST IN EMBEDED JHAMA CEMENT CONCRETE (1:4:8) OF SIZE 400(L)X200(W)X350(H) FOR DOUBLE POST AND 200(L)X200(W)X350(H) FOR SINGLE POST AND AS PER THE DRAWING (TYPE-II), SPECIFICATION, AND DERECTION OF ENGINEER-IN-CHARGE.INCLUDING ALL MATERIALS LABOUR ETC.COMPLETE. A)TYPE-II,DOUBLE POST @10.0 M CC AND INTERMEDIATE SINGLE POST @ 2.0 M CC (BASED ON PWD SCHEDULE OF RATES, W.E.F. 01.11.2017 WITH CORRIGENDA DT.04.06.2018) |
| 13 | SUPPLY, INSTALLATION AND OPERATION OF 4\\" DIA PORTABLE PUMP& COMPLETE IN ALL RESPECT FOR RUNNING |
| 14 | SUPPLY, INSTALLATION AND OPERATION OF 4\\" DIA PORTABLE PUMP& COMPLETE IN ALL RESPECT FOR IDLE |
| 15 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (a) 20 mm thick plaster |
| 16 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 15 Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m. |
| 17 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(ii) For Construction of Sub Base by consolidating Brick Bats / Laterite (90 mm to 45 mm) ( Ref :PWD (Rds & Brdgs)-2018, It. No. 4.10 (ii) Page No.247 & page-222 sl. No-5 (f)) |
| 18 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(i) For Construction of Sub Base by consolidating Jhama metal / Laterite (63 mm to 45 mm) (Moorum replaced with course sand) ( Ref :PWD (Rds & Brdgs)-2018, It. No. 4.10(i) Page No.247 & page-222 sl. No- 1 & 5 (e)) |
| 19 | Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(ii) On Granular surfaces treated with primer. (Using Bitumen emulsion at the rate of 0.25 to 0.30 kg per sqm.) ( Ref :PWD (Rds & Brdgs)-2018, Page No.213 (Table No.3.3?1) & Page No. 251, It. No. 5.02, Table no.I-2 of pg-219, pg-220 Format-B, PWD(R&B) 2018, pg-228 item-1.03 (i), Pg-230,Table-I, It-4,) |
| 20 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture)a) without paver finisheri) Day Time ( Ref :As per KMC Rates, taxes, fees & Charges for the year 2019-2020, As per present market Price, Rate appvd. By D.G.(Civil) Circular No-21 of 2016-17 dtd-25.10.16 vide resolution MIC meeting (Item no-M-29.22 dtd-21.09.16), Mpl. Secretary Circullar no-02 of 2018-19 dtd.04.04.2018 ) |
| 21 | SUB TOTAL |
| 22 | GST 18% |
| 23 | CESS 1% Please Enable Macros to View BoQ information |