| 1 | Construction of 30,000 Ltr Capacity OHT |
| 2 | Earth work excavation in all classes of soil such as hard stiff clay hard red earth, earth murrams gravel stoney erath, earth mixed with fair size boulders as per SS 20B for foundation.etc., complete |
| 3 | i) a.For first depth of 2 M |
| 4 | ii) Second depth of 1 M |
| 5 | Filling with M.sand including cost and conveyance of all materials to site and all labour charges etc complete |
| 6 | Cement Concrete 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance to work site including all labour charges for filling etc complete |
| 7 | R.C.C. 1:11/2:3 mix using 20mm ISS HBG metal including cost and conveyance to work site and all labour charges for mixing,laying and curing etc complete |
| 8 | A)1.50m to 4.50m Below GL |
| 9 | B) 0m to 1.50m Below GL |
| 10 | C) Above GL (0 to 4.50m) |
| 11 | D) Above GL (4.50 to 7.32m) |
| 12 | E) Above GL (7.32 to 10.98m) |
| 13 | Supplying and errecting centring for sides and soffits of all RCC works including cost and conveyance of all materials to site and labour charges etc. complete |
| 14 | A) PLAIN SURFACE |
| 15 | a) Below GL ( 0 to 3.30m ) |
| 16 | b) Above GL ( 0 to 3.30m ) |
| 17 | c) Above GL ( 5.30 to 6.30m ) |
| 18 | d) Above GL ( 6.30 to 7.30m ) |
| 19 | B) CURVED SURFACE |
| 20 | a) Above GL ( 5.30 to 6.30m ) |
| 21 | b) Above GL ( 6.30 to 7.30m ) |
| 22 | C) SQUARE SURFACE |
| 23 | a) Below GL ( 0 to 3.30m ) |
| 24 | b) Above GL ( 0 to 3.30m) |
| 25 | c) Above GL ( 3.30 to 4.30m) |
| 26 | d) Above GL (4.30 to 5.30m) |
| 27 | Cost and supply of steel with fabrication including cost of steel and binding wire complete with standard specification etc.,complete |
| 28 | Fabrication, supply, delivery and fixing of outside MS Ladder wide 45cm made out of 50x50x6mm MS angle for sides and steps in 16mm MS plain rods fixed at 30cm centre to centre welded, joned etc providing with suitable side supports, clamps, and locking arrangements provided access to roof top of 30,000 lit OHT of suitable inclined length, including bottom anchorage and transportion. |
| 29 | Providing and fixing of RCC inner acess ladder in RCC 1:1.5:3 mix using 20mm metal including cost and conveyance of all material to work site and all labour charges etc. completed and Vertical post of 10cm x 15 cm and step slab of 25mm x 25mm etc. completed |
| 30 | Ventilator made up of 45 stem with 65mm GI pipe and arms made out of 65mm GI Tee ,elbow with 20cm and 65mm pipe nipple and firmly welded |
| 31 | Providing Manhole cover of size 0.60x0.60M in RCC 1:1.5:3 with suitable reinforcement and 50x50x6mm MS angle fixied along edes |
| 32 | Provision for pipe connection arrangement for inlet, outlet, scour and over flow etc. including cost of pipes specials , value,labour charges for lifting, aligning, cutting, therading fixing and painting of GI Pipes with two coats of approved quality enamel paint etc. completed |
| 33 | 65mm dia GI pipes for inlet conection |
| 34 | 65mm dia GI pipes for overflow & rainwater harvesting pipe |
| 35 | 50mm dia GI pipes or scour pipe |
| 36 | 65mm dia GI pipe delivery pipe |
| 37 | 65mm dia GI Tee |
| 38 | 65mm dia GI Bend |
| 39 | 65mm dia GI Coupler |
| 40 | 65mm dia GI Union |
| 41 | 65mm dia GI Elbow |
| 42 | 65mm dia GM Gate valve |
| 43 | Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete. |
| 44 | Refilling the basement with excavated earth other than Sand complying the Standard specification |
| 45 | PIPELINE FOR PUMPING MAIN |
| 46 | Earth work excavation and depositing on bank with initial lead of 10 m and lift of 2 M in narrow trenches for laying of pipes etc |
| 47 | Supply and delivery of following PVC Pipes |
| 48 | 63mm OD PVC 6KSC Pips |
| 49 | Conveyance of the following rigd PVC Pipes, lowering to trenches and laying to proper grade and alignment |
| 50 | 63mm OD PVC 6KSC Pips |
| 51 | Refiiling the excaveted soil charges including cost and conveyamce of all materials to all labour charges etc |
| 52 | PIPELINE FOR DELIVERY MAIN |
| 53 | Earth work excavation and depositing on bank with initial lead of 10 m and lift of 2 M in narrow trenches for laying of pipes etc |
| 54 | Supply and delivery of following PVC Pipes |
| 55 | 63mm OD PVC 4KSC Pips |
| 56 | Conveyance of the following rigd PVC Pipes, lowering to trenches and laying to proper grade and alignment |
| 57 | 63mm OD PVC 4KSC Pips |
| 58 | Refiiling the excaveted soil charges including cost and conveyamce of all materials to all labour charges etc |
| 59 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information |