| 1 | Percentage BoQ BoQ_Ver3.0 Percentage Normal INR Only INR CIL Hide Select GST Registered Bidder under regular scheme GST Registered Bidder under composition scheme GST Unregistered Bidder Not Applicable Tender Inviting Authority: Staff Officer (Civil), Wani Area, Western Coalfields Limited Name of work: Repairing and strengthening of internal coal transportation roads and other important roads at Penganga OC Mine.NIT no.: WA4350-CIV-E-099-2025-26 . Category of services (To be selected by department) Category of bidder (To be selected by bidder) To be entered by department Service Tax Category ( To Be Selected by Bidder) ITC Available Works Contract Bidder's status (mandatory) Rate of GST (in %) Total GST(in Rs.) GST to be paid by bidder (in Rs.) GST to be paid by WCL (in Rs.) Name of the Bidder/ Bidding Firm / Company : Select 18.0 0.0 0.0 0.0 PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the bidder name and values only.) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # S. No. Item Description Item Code / Make Quantity Units Estimated Rate in Rs. P Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder Rs. P Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category Total amount inRs. P TOTAL AMOUNT With Taxes Total amount in words |
| 2 | Construction of granular sub-base by providing well graded material like natural sand crushed gravel or crushed stone having CBR >30, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator or plant mix method at OMC, and compacting with vibratory rollers of 80 to 100 kN static weight to achieve the desired density, complete as per Clause 401 of Specification.By Mix in Place Method For Grading-I Material |
| 3 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per clause 404 of specification.By Mechanical Means Grading- I (63 to 45mm) Using Screening Type-A (13.2mm |
| 4 | Clearing and Grubbing Road Land Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.By Mechanical Means In area of thorny jungle |
| 5 | Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location with all lifts and lead upto 1000m as per relevent clauses of section-300 of specification. |
| 6 | Compaction of road sub- base/road surface by watering and rolling with vibratory rollar 8 tonne, as per instruction of Engineer in - charge or representative (s), including cost of equipment, fuel, oil, operator, water etc all complete. The work is to be done 8 hour/day in general shift.Only running time shall be measured for payment.In mesurment, number of days shall be calculated as total number of running hours ( as per actual measurment ) divided by 8. (Note : - Rolling / watering done in item no 1,2,$ 3 above shall not be counted for mesurment in this item ) |
| 7 | Total impact of GST for the purpose of CTC Total in Figures 5222724.499999999 5222724.499999999 INR Fifty Two Lakh Twenty Two Thousand Seven Hundred & Twenty Four and Paise Fifty Only 4.0 Construction of chamber for 100mm sluice plates item5 10.0 Nos Quoted Rate in Figures Select 0.0 0.0 INR Zero Only Quoted Rate in Words INR Zero Only Please Enable Macros to View BoQ information |